thanks liang notes Flashcards

1
Q

List the 6 types of estimation?

A

For owners:
Conceptual
Alternative Design Estimates
Owners Engineer’s Estimate

For contractors:
Contractors Bid Estimate
Alternative Construction Methods
Changes/Claims

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is a conceptual estimate?

A

Feasibility Study - Hires A/E to provide order of magnitude estimate of cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is an alternative design estimate?

A

Architect/Engineer shows different designs giving owner more options
Perform a Quantity Take-off (QTO)
Rely on bid abstracts for cost info

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is an Owner’s Engineer’s Estimate?

A

Engineer gives owner a cost to compare when evaluating bids
Performs another QTO

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is a Contractor’s Bid Estimate?

A

QTO (very detailed)
Based on in-house cost database
Consider construction methods

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is an Alternative Construction Methods?

A

Contractor has been awarded the job
Detailed review on how he priced job
Finds better ways to approach project
Eg. better construction methods?
Trying to maximize profits

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Changes/Claims

A

Need to be priced
When owner wants to make a big change that’s not part of the scope, contractor can make a claim for that

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is a direct cost?

A

Any cost that can be associated with a discrete, physical part of a construction project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is an indirect cost?

A

Any cost that cannot be associated with a discrete, physical part of a construction project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are permanent materials (PM)?

A

Any material that falls within the neat lines of the drawing
LOW RISK

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are Expendable Material (EM)?

A

Any material that falls outside the neat lines of the drawing + temporary structures like falsework and framework
HIGH RISK

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are labourers (L)?

A

Related to productivity
Difficult to estimate
HIGHEST RISK

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are subcontractors (S)?

A

Covered by performance bond
LOW RISK

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are Equipment Operating Expense (EOE)?

A

FOG (Fuel, Oil, Grease)
Tires
Small repair parts
3rd part overhaul
MID RISK

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are Repair and Service Labour (RL)?

A

Direct costs
HIGH RISK

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What are Rental, Depreciation, and Writeoff (R)?

A

In-house equipped division -> Rent equipment to that own project
Rent/Lease
Operated + Maintained (HIGH RISK) -> Renting equipment and an operator
MID RISK

17
Q

What are the 7 horizontal cost types? PEE-RSLL

A
  1. Permanent Materials
  2. Expendable Materials
  3. Equipment Operations
  4. Rentals
  5. Sub Contractors
  6. Labour
  7. Labour Service
18
Q

What are the two bid formats we consider in CM2?

A

Lump Sum Bid -> Only shows final price of bid
Schedule-of-bid-items Bid -> Calculate each individual item

19
Q

What makes up the rows in the Bid Formats table…?

A

Directed Costs
Fixed Costs
——->Indirect Costs
——————->Salaried Payroll
——————->Time-related overhead
——————->Non-time-related overhead
——————->Insurance and Taxes
——————->Construction plant in & out
——->Escalation
——————->Labour
——————->Material
——————->Equipment
——->Interest
——->Contingency
——->Markup
Bond (Premium)

20
Q

What makes up the columns in the Bid Formats table…?

A

Labor
PM
EM
Subs
EOE
RL
Rent

21
Q

What are the three kinds of shifts when considering labour premium?

A

Regular - 8AM to 4:30PM - 8 hours worked - 8 hours paid
Swing - 4:30PM to 12:30AM - 7.5 hours worked - 8 hours paid
Night - 12:30AM to 8AM - 7 hours worked - 8 hours paid

22
Q

What is the Shift Differential Equation? What is it use for?

A

(Hrs paid - Hrs worked)/Hrs worked

This is used to find the pay premium amount, by multiplying it with the total dollar value labour cost

23
Q

What are the types of Overtime?

A

1.5/1.5/2
1.5 applies to weekdays and saturdays
2.0 applies to sundays and holidays

2.0/2.0/3.0
2.0 applies to weekdays and saturdays
3.0 applies to sundays and holidays