CM Notes Flashcards
What are the Seven aspects of a Vertical Cost Breakdown?
IBID-CM-E
- Indirect Costs
- Bonds
- Interest
- Direct Costs
- Contingency
- Markup
- Escalation
List 2 methods of pricing out direct cost estimates
- Crew Method
- Individual Method
Define Swing Shift
the work shift between the day and the night shifts, commonly from 4:00 PM to midnight
3 Types of Estimate for an Owner
- Conceptual Estimate
- Alternative Design Estimate
- Owner’s Engineer Estimate
3 Types of estimate for a contractor
- Contractor’s bid estimate
- alternative methods
- claims / change orders
Two different breakdowns of cost:
Horizontal and Vertical
Horizontal: 7 Categories
PEE-RSLL
- Permanent Materials
- Expendable Materials
- Equipment Operations
- Rentals
- Sub Contractors
- Labour
- Labour Service
Vertical: 7 Categories
IBIDCM-E
- Indirect Costs
- Bonds
- Interest
- Direct Costs
- Contingency
- Markup
- Escalation
List 3 types of mark-up
Home office, Profit, and Risk
List The 4 Types of EOE
Equipment Operating Expense
- FOG: Fuel Oil Grease
- Small Repair Parts
- Tires
- 3rd Party Overhaul
List the 5 Types of Indirect Costs
- Salaries / Payroll
- Time-related O/H expense
- Non-time related expense
- Insurance + taxes
- Construction Plant in + out
Contingency
Safety net accounting for risks
2 Types of Contingency
Identified & Unidentified
3 Categories of Unidentified Contingency
- Soft Subs
- Construction Hedge
- Special Events (i.e. strike)
What is an unidentified contingency?
A little bit of padding thrown into your estimate for small, unanticipated events.
List the 2 categories of risk.
Quantifiable & Unquantifiable risk
2 Types of Network Diagrams
AoA - Activity on Arrow
AoN - Activity on Node
What is a schedule?
A schedule is a logical representation of logical relationships / sequences of tasks or activities.
IPA
Immediately Preceding Activity
Dummy Relationship
Logical relationship with no time associated
(CP) Critical Path
The longest path through the network.
Activities with zero float are considered critical path tasks.
Critical Activity
Any activity on the critical path
- CA’s have zero float
- if a CA is delayed, the entire duration is delayed by the same time
Float
The difference between the available time to complete an activity and the required time.
a. non-critical activities have float
b. critical activities have no float
4 Types of Logical Relationships
Start-Start
Start-Finish
Finish-Finish
Finish-Start
The default is Finish-Start relationship
CPM
Critical Path Method
ES ID EF
DUR
LS LF
Why would an Owner shorten a schedule?
Why would a Contractor shorten a schedule?
Owner: To complete project sooner and start generating revenue
Contractor: To finish the job and start the next one
Direct Cost
Any cost associated with the PHYSICAL CONSTRUCTION of a DISCRETE part of the construction (ie concrete workers)
Indirect Cost
Any cost that is NOT associated with physical construction of a discrete part of the construction (i.e. supervisor)
If you shorten a project, Direct Cost will _____ and Indirect Cost will _______.
Direct Cost will INCREASE & Indirect Cost will DECREASE
To shorten a schedule:
- Must be shorter than critical path
- Must be aware that as CP is shortened, may create new CP’s
- Comes down to shortening duration of Critical Activity
A single Critical Activity has 2 limits that need to be considered
Physical Limit & Logical Limit
Physical Limit of a Critical Activity
Maximum time that an activity can be reduced in duration.
Logical Limit of a Critical Activity
of days (time units) an activity can be reduced before creating an additional Critical Path
When crashing a schedule, crash to the _____ of physical limit and logical limit.
LESSER
Before scheduling, you must ____
PLAN
WBS
Work Breakdown Structure
The progressive hierarchical breakdown of a project into smaller components to the lowest practical level to which costs can be applied.
equation for PLANNING
Planning = Work Breakdown + Work Sequencing
Contract documents will lay out the ______ of work
SCOPE
equation for PROJECT
Project = Sum of Sub elements OR work packages
the Sum of work packages can be shown in a hierarchical format called a WBS (Work Breakdown Structure)
Float / Slack
If there is more time to complete an activity than required, that activity is said to have float or slack.
Free Float
The maximum delay in the ES (Early Start) of an activity without affecting the ES of any IFA (immediately following activity)
Interfering float (IF)
The reduction in the float of an activity if the IPA is delayed by its TF
Formula for TF (Total Float)
TF = FF + IF
Total Float = Free Float + Interfering Float
also:
TF = LS-ES or LF-EF
ES or EF from the SUCCEEDING activity.
ex: TF-b = LS,b - ES,c
Beginning-To-End Planning
Begin with mobilization and proceed step by step through the project to completion.
Although intuitive, this method has some drawbacks.
Some projects are so complex that it is difficult to visualize the best way to sequence it.
Top-Down Planning & WBS
- Preferred by Industry
Start with an overall view of the project and then break it into its major components, then break down the major components into more detail.
3 Common Methods of Bid Markup Determination
- % of Total Cost
- % of Labour
- % Broad-based method
Horizontal Format of Cost Expression
L + PM + EM + S + EOE + RL + R = Total
Labour (L)
Permanent Materials (PM)
Expendable Materials (EM)
Subtracts (S)
Equipment Operating Expense (EOE)
Repair and Service Labor (RL)
Rental (R)
Estimation Risk
Labour (L & RL): Highest Risk
- Expendable Materials (EM)
- Equipment (EOE, R) Subcontracts (S),
Permanent Materials (PM): Low Risk
AOA - Activity on Arrow
A graphical representation of a schedule showing tasks or activities as arrows connected by nodes that allows for overlapping construction activities
AON - Activity On Node
A graphical representation of a schedule showing tasks or activities as nodes connected by arrows that allows for overlapping construction activities
Network Diagram
1) A representation of logical relationships
2) A sequence of activities or tasks
IPA - Immediately Preceding Activity
The activity or task that must occur prior to the commencement of a task or activity
SS - Sequence Steps
The steps of tasks or activities in a network diagram
CP - Critical Path
Continuous sequence of connected activities that form the longest duration/path through the network