Test Method C231: Air Content of Freshly Mixed Concrete by the Pressure Method Flashcards

1
Q

The pressure method of determining air content can be used on concrete containing ___ ___ aggregate.

A

Relatively dense

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

The pressure method of determining air content cannot be used on concrete containing the following types of aggregates: ____, ____, ____

A

Lightweight, air-cooled blast furnace slag, or aggregates of high porosity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the minimum allowable capacity of the measuring bowl used in this test method?

A

6 L (0.2 ft3)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the required characteristics of the tamping rod used in this test method?

A

Round, straight steel rod, with a 16 mm [5/8 in.] +- 2 mm [1/16 in.] diameter, length at least 100 mm [4 in.] greater than the depth of the measuring bowl, but not greater than 600 mm [24 in.] in overall length, with the tamping end rounded to a hemispherical tip of the same diameter as the rod.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the specified size of the mallet required for this test method when the measuring bowl has the capacity of 14 L (0.5 ft3) or less?

A

0.60 +- 0.25 kg (1.25 +- 0.5 lb)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

The sample of concrete used for this test is to be obtained in accordance with what ASTM Standard?

A

C172

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

The max size aggregate allowed for this test method is ____.

A

2 inches (50mm)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

If the concrete contains aggregate larger than the max allowed for this test, the sample must be _____.

A

Wet sieved over a 1.5 in sieve

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

If the concrete sample is to be consolidated by rodding, the measure is filled in ___ layers.

A

3 equal

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

If the concrete sample is to be consolidated by vibration, the measure is filled in ___ layers.

A

2 equal

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

When rodding the concrete sample, what is the number of strokes required for each layer?

A

25

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Vibration of the concrete sample is not allowed when the slump of concrete exceeds ____.

A

75 mm (3 inches)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

In rodding the sample, how deep should the rod penetrate each layer?

A

1 inch into previous layer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

After rodding each layer, what should be done to the measure before adding another layer of concrete?

A

Tap the sides of the measure smartly 10 to 15 times with the mallet.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

When consolidating the concrete by vibration, how many times should the vibrator be inserted into each layer?

A

3

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What tools may be used to strike off the top surface of the concrete following consolidation of the final layer?

A

A strike-off bar, a metal, glass, or acrylic plate

17
Q

What must be done if there is a slight deficiency in the quantity of concrete in the measure of consolidation of final layer?

A

Add a quantity of representative concrete before strike off

18
Q

What must be done if there is an excessive amount of concrete in measure following consolidation of the final layer?

A

Remove a representative quantity of concrete with the scoop or trowel before the strike off