Test 2 Jeopardy Flashcards
_______ in a defense system’s development and acquisition program helps reduce or manage risks.
Test and Evaluation (T&E)
The Test and Evaluation Master Plan (TEMP) is prepared by the _____ in conjunction with principal __________.
PM / Integration Working Group (TIWG) members
The _________ is the principal staff assistant and senior advisor to the Secretary of Defense on operational test and evaluation (OT&E) in the Department of Defense (DoD).
Director, Operational Test and Evaluation
Testing event emphasized later in the life cycle, focuses on the system and determines operational effectiveness and suitability.
Operational Testing
Testing event which is normally conducted on those tasks performed at field level and some sustainment level by user representatives.
Logistics Demonstration
Two principles of Lean Manufacturing
Minimization of Waste
Responsive to Change
Involves proving the design can actually produce a product that meets customer functional requirements in a realistic, “factory floor” type situation.
Process proofing
Cost of Quality (3 areas)
- Prevention
- Appraisal
- Correcting Failures
The five major causes of production problems
- Unstable Rates and Quantities
- Design Instability
- Undue emphasis on Schedule
- Inadequate Configuration Management System
- Inattention to Environmental Impacts
Five top level design goals for producible products
- Design for Ease of Fabrication
- Design for Ease of Assemble
- Design for Multiuse
- Minimize Number of Parts
- Maximize Number of Common Parts
An event-based plan that identifies the work that must be accomplished to complete the key program activities and events
Integrated Master Plan (IMP)
The ________ for estimating schedule durations includes an optimistic, pessimistic, and most likely estimates.
Three Point Estimate
Longest path through the network
Critical path
These schedules tie (or roll up) the detailed tasks in the detailed schedules to the key events and milestones in the master schedule(s), and provide traceability between the two levels.
Intermediate
These charts depicts information about significant project events, focusing on specific points in time.
Milestone
This level of the WBS includes Major Elements of the defense materiel item, such as hardware, software elements, program management, training, data, etc.
Level 2
The WBS is used for: (four events)
- Planning logistics
- Establishing schedules
- Tracking cost
- Predicting variations
Develops the Contract WBS
Contractor
A WBS is an output of the ________ process.
Systems Engineering
There are _______ WBS categories and ________ common elements (level 2).
11/10
3 Leadership Styles
- Supervisory
- Participative
- Team