Test 2 Flashcards
A note on a drawing states: “Beam-to-column connections to be H.S. bolted.”
The abbreviation “H.S.” stands for:
high strength
The final operation in the placement of a structural steel member is:
placing permanent fasteners
A type of truss that beams are arranged in rectangles or squares, doesn’t have diagonal braces like other trusses, but it uses sturdy connections at the corners to stay strong is called?
Vierendeel truss
What type of crane would be used to construction a high-rise building?
Tower crane
What is name of the most commonly used wire rope used in a tower crane?
(IWCR) independent wire rope core
When erecting a building with a crane, where should you start?
Start away and work towards the crane
Name the type of weld that joins two pieces of metal at a right angle by creating a triangular shaped weld.
Fillet weld
Name the type of weld where a hole or a slot is filled with molten metal to join to overlapping metal pieces.
Plug weld
aka. Slot weld
Name the type of weld, where two metal pieces with a curved edge are joined by creating a weld bead the gradually widens to form a flared shape
Flare bevel groove weld
Name the type of weld where two metal pieces are joined together, with one having a straight edge and the other piece having a curved concave groove.
J Groove weld
Name the type of joint in which two pieces of metal are joined together by creating a groove in the shape of a “U” and filling it with molten metal through welding.
U-groove
Name the welding technique where the joint between two pieces of metal is welded along the entire circumference or perimeter of the joint.
Weld all around
Aka continuous weld or 360-degree weld
Name the weld that refers to the welding operation performed on-site, rather than in a controlled workshop environment.
Field weld
A ton of steel has 250 square feet of paintable surface and you must paint 800 tons. If each gallon of paint covers 400 square feet, how many gallons of paint are needed?
A. 400 gal
B. 500 gal
C. 560 gal
D. 600 gal
B. 500 gal
Surface Area:
800 T × 250 sq ft/T = 200,000 sq ft.
Paint:
200,000 sq ft - 400 sq ft/gal =
500 gal.
Which tool is used to remove the head of a rivet?
A. dolly
B. punch
C. buster
D. impact wrench
C. buster
Three laborers have each worked 10 hours overtime. Their straight-time rate is $18.50. If the overtime rate is 1-1/2 times straight time, how much overtime pay is due?
A. $422.50
B. $527.00
C. $687.25
D. $832.50
D. $832.50
$18.50/hr x 1.5 hr = $27.75.
$27.75/hr x 10 hr/worker = $277.50.
$277.50/worker x 3 workers =
$832.50
A crew consists of a foreman ($16.20/hr), three journeymen ($13.50/hr each), and an apprentice ($11.00/hr). The crew works an 8-hour day. What are the total wages?
A. $433.60
B. $541.60
C. $651.20
D. $733.60
B. $541.60
$16.20 ÷ $13.50 + $13.50 + $13.50
+ $11.00 = $67.70 /hr.
$67.70/hr x 8/hr = $541.60
What is a maul used for?
A. hitting steel members into place
B. driving drift pins and bull pins into connection holes
C. used for straightening bent material
D. all of the above
D. all of the above
What is a “headache ball” used for?
A. temporary scaffolding
B. hoist the mast
C. to help overhaul the load falls
D. migraines
C. to help overhaul the load falls
The overhauling ball or headache pill is used to overhaul the main or auxiliary load falls to help bring the load block and lifting hook down after a load has been lifted and the hook has been freed.
What does the term “to plumb” mean in the erection of structural steel?
A. to true columns vertically
B. to square columns
C. to make columns level
D. to install pipes
A. to true columns vertically
After the first panel of steel is
erected, the plumbing-up gang starts installing guys. By tightening or loosening the turnbuckles on the guys, the tops of columns can be moved one way or another. A plumb bob is used to true the columns up vertically.
“W14 x 74” means:
A. a 14” deep wide-flange beam weighing
74 lb per ft
B. a 14” deep wide-flange beam weighing
74 lb per inch
C. a wide-flange beam 14 ft long weighing 74 lb per ft
D. a wide-flange beam 74 ft long weighing 14 Ib per ft
A. a 14” deep wide-flange beam weighing
74 lb per ft
On an erection drawing, “W14 x 211” indicates:
A. the size of the piece
B. the weight of the piece
C. both the size and weight of the piece
D. the size, weight, and location of the piece
C. both the size and weight of the piece
Which of the following has the lowest yield strength?
A. quenched and tempered carbon steel
B. low-alloy steel
C. quenched and tempered low-alloy steel
D. carbon steel
D. carbon steel
If you and another worker are carrying a long piece of material, how should you carry it?
A. by your sides
B. on the same shoulder
C. on opposite shoulders
D. one carries it with hands in back and the other worker follows
B. on the same shoulder
In erecting structural steel, when the holes do not align, it may be necessary to create oversize holes and use an oversize bolt.
Which of the following terms refers to enlarging a bolt hole?
A. coping
B. reaming
C. scything
D. plumbing
B. reaming
How does a slot weld differ from other types of welds?
A. It requires a slot or groove to be cut into the base metal
B. It is only used for cosmetic purposes
C. It uses a different welding technique than other weld types
D. None of the above
A. It requires a slot or groove to be cut into the base metal
Name the type of weld where two pieces of metal are joined together along their edges in a single plane, creating a strong and continuous connection.
Butt weld
Name the type of weld where two pieces of metal overlap each other, and the weld is applied along the overlapping area to join them together.
Lap weld
When erecting structural steel, what is the hand signal for bringing down the boom?
A. arm straight, fingers closed, thumb pointing down, move hand up and down repeatedly a short distance
B. give boom down signal and repeatedly open and close fingers
C. clasp fingers of one hand with the fingers of the other, palms facing
D. both arms extended, hands open, palms down, move hands quickly back and forth repeatedly
A. arm straight, fingers closed, thumb pointing down, move hand up and down repeatedly a short distance
When erecting structural steel, what is the hand signal for lower boom and raise load?
A. arm straight, fingers closed, thumb pointing down, move hand up and down repeatedly a short distance
B. arm extended, palm down, move arm back and forth
C. forearm vertical, forefinger pointing up
D. give boom down signal and repeatedly
open and close fingers
D. give boom down signal and repeatedly
open and close fingers
When erecting steel, at what height is it necessary to provide a safety net for workers?
A 15 ft
B. 25 ft
C. 36 ft
D. 42 ft
B. 25 ft
The minimum scale allowed by AISC
(American Institute of Steel Construction)
for shop drawings is:
A. 1/8”: 1 ft
B. 1/4”: 1 ft
C. 1/16”: 1 ft
D. 1/3”: 1 ft
A. 1/8”: 1 ft
A contractor must choose between hiring a crane with an operator at a cost of $9,600 for the job or renting a crane for $600/day and paying an operator $120/day. After how many days would it not be worth it to rent the crane and pay the operator?
A. 7 davs
B. 13 days
C. 15 days
D. 20 days
B. 13 days
$9,600 ÷ $720/day = 13.33 days.
How many protective coats must the erecting contractor apply to steel joists and accessories?
A. none
B. 1
C. 2
D. 3
A. none
A contractor estimates total labor at
$180,000. Labor costs include a crew of 40 workers at an average wage of $18.00
per hour for an 8-hour day. Labor also includes two ironworkers. One is at journey level at $11.00 per hour, and the other is a foreman at $19.00 per hour. If the contractor can only afford 10% of the labor estimate for rain delays, how many
8-hour days has the contractor allowed for the weather factor?
A. 1 day
B. 3 days
C. 4.5 days
D. 7 days
B. 3 days
Crew:
$18/hr x 8 hr/day x 40 workers =
$5,760/day.
Iron workers:
$19/hr + $11/hr = $30/hr.
$30/hr x 8 hr/day = $240/day.
$5,760 + $240 = $6,000/day.
$180,000 x 0.10 = $18,000.
$18,000 - $6,000/day = 3 days.
The average working hours per ton used in estimating structural steel erection is:
A. 1 br
B. 9 hr
C. 12 hr
D. 24 hr
B. 9 hr
What does the abbreviation “do” mean on a plan?
A. ditto
B. down only
C. drain out
D. do over
A. ditto
A crew installs 60 bolts per day. If the crew consists of 1 foreman at $19.50 per hour, 2 journeymen at $16.00 per hour apiece, and 2 apprentices at $11.00 per hour apiece, what is the cost per bolt in an
8-hour day?
A. $ 4.40
B. $ 6.20
C. $ 9.80
D. $12.40
C. $ 9.80
2 x $16/hr = $32/hr.
2 x $11/hr = $22/hr.
$19.50/hr + $32/hr + $22/hr =
$73.50 total hourly wages.
$73.50/hr x 8 hr/day = $588 per day.
$588.00/day - 60 bolts/day = $9.80
per bolt.
Who marks the beams for location?
A. the mill
B. the fabricator
C. the general contractor
D. the architect
B. the fabricator
On buildings or structures not adaptable to temporary floors, and where scaffolds are not used, safety nets must be installed and maintained whenever the potential fall distance exceeds _____ stories or _____ feet.
A. 1… 10
B. 2… 10
C. 2… 25
D. 3… 30
C. 2… 25