To determine which features to create first, the product owner did a feasibility study. After the feasibility study was done, the product owner prioritizes the product backlog. However, the project team disagrees with the prioritized product backlog, claiming the work is infeasible in that order.
What should the project manager do first in this situation?
a.
Review the results of the feasibility study.
b.
Reprioritize the product backlog with the team.
c.
Inform the product owner the work will need to be reprioritized.
d.
Meet with the team to understand why the work is infeasible before meeting with the product owner.
Meet with the team to understand why the work is infeasible before meeting with the product owner.
The best course of action would be to meet with the team to understand why they feel this way and then inform the product owner of the result.
M5Q36 A project manager has just been informed by the sponsor that the project will need to be completed three months earlier than expected. This is due to an early launch date that the CEO has requested.
What should the project manager do in this situation?
a.
Have the team implement the change request to reduce the schedule
b.
Schedule a meeting with the sponsor to review the impact of this change
c.
Update the project management plan to finish the project three months earlier by removing certain parts of the scope
d.
Implement resource leveling to finish it sooner
The correct answer is: Schedule a meeting with the sponsor to review the impact of this change
The best solution would be to meet with the sponsor to let him know that finishing the project earlier could result in scope and cost changes.
A project has three sponsors that will need to be active to ensure the finished product is accepted. A few weeks into the project, one sponsor informs the PM she will be out for the next three months.
What should the Project Manager do?
a.
Update the stakeholder engagement plan.
b.
Update the risk management plan.
c.
Update the stakeholder register.
d.
Revise the project management plan.
The correct answer is: Update the stakeholder engagement plan.
The stakeholder engagement plan is updated to reflect any issues that might impact the engagement of a stakeholder.
An organization is currently using predictive approaches to design a new product. The new product has many uncertain requirements. The organization hires a new project manager for this project to implement agile methods.
What should the project manager do to deliver this project?
a.
Inform the organization it would be best to continue using predictive methods
b.
Ask the project sponsor for a detailed list of requirements in order to proceed on the project
c.
Create a project management plan with a set scope statement
d.
Create the backlog and complete the work in iterations
The correct answer is: Create the backlog and complete the work in iterations
Since the requirements are unclear. Best create this product using agile methods and building the product in increments. This way stakeholders would be able to give feedback to clarify the scope.
Place agile meeting in order done during a sprint
The correct answer is:
1 → Sprint Planning Meeting,
2 → Sprint Review,
3 → Sprint Retrospective
A new project is about to be initiated to create a new product. After meeting with the project sponsor, the project manager realizes that the sponsor is not too sure about the functionality of the final product.
What should the project manager do in this situation?
a.
Have the sponsor meet with the team to clarify the functionality
b.
Work with the project sponsor to help define the main functionality and suggest that the product be developed in iterations
c.
Meet with the PMO to review how previous projects have dealt with this issue
d.
Update the risk register with this risk
The correct answer is: Work with the project sponsor to help define the main functionality and suggest that the product be developed in iterations
The best solution would be to work with the sponsor or to help define the main functionality and suggest an iteration approach to help refine the functionality.
The PMO has assigned a new Project Manager to a project, and the sponsor asks the new Project Manager to develop the quality management plan.
How should the new Project Manager proceed?
a.
Obtain the necessary benchmarking scores from the customers.
b.
Schedule a meeting with the sponsor to collect requirements for the plan.
c.
Meet with the PMO to identify established plans and processes.
d.
Wait for the PMO to provide the quality management plan.
The correct answer is: Meet with the PMO to identify established plans and processes.
The new Project Manager needs to consult with the PMO to find out what practices and processes are already in place.
M5Q41 A project manager working on a software development project following a traditional approach has been informed that the project sponsors are having a disagreement on what some of the core functionalities should be.
What should the project manager do in this situation?
a.
Review the project charter to better understand the overall objectives of the project
b.
Meet with the project sponsors better to understand what this disagreement is and what is causing it
c.
Review the project management plan to gain a better understanding of where the disagreements can come from
d.
Meet with the project team to review the disagreements
The correct answer is: Meet with the project sponsors better to understand what this disagreement is and what is causing it
The best choice here would be to first meet with the sponsors to gain a better understand of what this disagreement is and then find a solution to resolve it.
Match the Agile roles
Self-directed and self-managing → Agile project team,
Servant leader → Agile Project manager,
Creation and maintenance of the product backlog → Product owner
M5Q49 The project sponsor is dissatisfied with how a feature of a project has been developed on the hybrid project. He says the product was not ready for deployment, yet the team allowed it.
What should the Project Manager do first to resolve this issue?
a.
Identify the reasons for issues with the feature, then address the issue.
b.
Meet with the project team for a brainstorming session and identify a solution.
c.
Have the deployment team assess if the team made a bad decision.
d.
Have the team explain to the sponsor why they said it was complete.
The correct answer is: Identify the reasons for issues with the feature, then address the issue.
The project manager should first identify the reasons that cause the feature to fail then address those reasons are.
M5Q18 An organization has just approved a new office renovation project. After being assigned to the project, the project manager would like to know what is his power level on the project.
What document should the project manager refer to?
a.
Stakeholder engagement plan
b.
Communication management plan
c.
Project charter
d.
Issue log
The correct answer is: Project charter
The project charter is a document that will assign the project manager and also outlined his authority level.
M5Q30 A new team member will be joining a hybrid project team. This team member has a few physical disabilities that make communicating difficult.
What should the project manager and team do next?
a.
Have the team meet with the new team member and have them implement a communications solution.
b.
Update the team charter for the project team and inform them of the changes
c.
Have a meeting with the team to understand the issue and what communications will need to be changed
d.
Redesign the communications management plan
The correct answer is: Have a meeting with the team to understand the issue and what communications will need to be changed
The next step here would be to meet with the team and to understand what the main issue would be and then implement solutions to fix this.
M5Q27 The project manager has met with the product owner to discuss an issue about the project team being unhappy with the overall project. This has been going on since the project started.
What could the project manager have done to prevent this?
a.
Create the team ground rules have them follow it
b.
Ensure the team understands the product owner role on the project
c.
Work with the team to understand the goals of the project vision
d.
Have the product owner meet with the team to implement a solution
The correct answer is: Work with the team to understand the goals of the project vision
The best solution here would be to work with the team to help them understand the main cause of the project and understand the project vision.
M5Q33 A hybrid team has met with the project manager to seek advice on the best ways to estimate the amount of time it can take to complete the work. What are two techniques the team can use? (Choose 2)?
a.
Story points
b.
Decision making
c.
Cause and effect diagram
d.
Prototyping
e.
Bottom-up estimating
The correct answers are: Bottom-up estimating, Story points
The predictive portion of the project can use bottom-up estimating the agile portion of new story points.
M5Q13 A team member has submitted the change to the change control board and the change control board rejected the change. The team member feels this is unfair.
What should the project manager do to ensure this does not happen again?
a.
Verify the change was cost-efficient
b.
Assess the change against all of the project objectives
c.
Approved the change yourself since it was from a team member
d.
Have the change control board reassess the change
The correct answer is: Assess the change against all of the project objectives
The best solution here would be to ensure the changes are assessed against all of the project objectives. These are the changes rejected the project team member would feel and understand why it was.