TEST 1 Flashcards
A Project Manager notices stakeholders are not involved in the project. The PM held a few meetings and still, no stakeholder was active during the meeting. This can lead to deliverables not getting accepted.
What should the project manager do in this situation?
a.
Have the team hold the meeting.
b.
Use effective facilitation techniques.
c.
Make use of political awareness techniques.
d.
Add this as a risk to the project.
Use effective facilitation techniques.
Facilitation is the ability to effectively guide a group event to a successful decision, solution, or conclusion. A facilitator ensures that there is effective participation and that participants achieve a mutual understanding.
A Stakeholder on a software development project is constantly calling the project team members for status updates and reporting issues that are not related to the project.
What should the project manager do in this situation?
a.
Have the team tell the stakeholder to stop this
b.
Inform the project sponsor of this situation and have the sponsor speak with the stakeholder
c.
Meet with the stakeholder to understand why this is happening and what solutions can be implemented
d.
Meet with the stakeholder and review the communications management plan
Meet with the stakeholder to understand why this is happening and what solutions can be implemented
It would be best to meet with the stakeholder to understand why he is doing this and how it can be fixed to stop interrupting the project team.
The PMO requires a project team to be made up of people that live in multiple different countries. The project sponsor believes that the distribution will provide a team with many ideas and might save costs.
Where should this be documented in the project charter?
a.
As part of the overall project risks.
b.
As part of high-level scope.
c.
As part of the risk management plan within the charter.
d.
As part of stakeholder list.
As part of the overall project risks.
Having a distributed project team comes with risks. These risks need to be identified in the charter as an overall risk for the project.
A project manager has reviewed a partially complete deliverable and found that it has a few minor defects. These defects may cause complications when it’s being used by the customer. The project has a CPI of .97 and an SPI of .98.
What should the project manager do in this situation?
a.
Have the team fixed the issue since the project has an adequate budget and time left
b.
Initiate a change request with the change control board
c.
Reinspected the deliverable to ensure of the defect
d.
Report this issue to the project sponsor and seek guidance
Initiate a change request with the change control board
Since this will require additional time and cost to fix, it would be best to initiate a change request to add additional time and costs to complete the repairs on this defect.
During a hybrid project, a team member is reassigned to a new agile project. The team is disappointed since this member was one of their key mentors.
What should the project manager do in this situation?
a.
Have the team meet with the sponsor to voice their disagreement.
b.
Add a member with the same skills to replace the key team member.
c.
Implement a change to bring the member back.
d.
Use your leadership and emotional intelligence techniques to motivate the team.
Use your leadership and emotional intelligence techniques to motivate the team.
Since this is more of a personal issue within the team, which manager should use his leadership emotional intelligence to keep the team motivated to stay work on the project.
The project team has completed the project budget. The team used a combination of their expertise and previous lessons learned to complete the budget. The company’s senior management has informed the project manager that the project is too expensive and will not be approved.
What should the project manager do next?
a.
Inform the team they will need to redo the entire budget because it was done incorrectly
b.
Inform senior management that you will remove all contingency from the project budget to lower the overall budget
c.
Inform senior management that the budget is accurate
d.
Review the method the team use and if it was applicable to this project
Review the method the team use and if it was applicable to this project
The next step would be to first review the method the team created the budgeting to ensure that it is accurate and it applies to this project before taking any other action.
A major disagreement has occurred on the project between the project manager and one of the suppliers. The supplier keeps sending the wrong materials to the project team, causing a delay in the schedule.
Which type of communication should the Project Manager use first when contacting the supplier about this issue?
a.
Instant message
b.
Face-to-face
c.
Email
d.
Virtual Meeting
Face-to-face
Face-to-face interaction is usually the most effective way to resolve issues in most circumstances. Face-to-face interaction is known to be the most productive way to communicate.
Team members have been unable to complete the second half of a deliverable due to working with operations to help users with the finished product. The project manager wants to confirm that the deliverable was transferred to operation.
Which three documents should the project manager use for this decision?
a.
Procurement agreements, and organizational process assets updates, and scope statement
b.
Final report, project document updates, and organizational process assets updates.
c.
Final report, organizational process assets updates, and risk register.
d.
Procurement agreements, scope statement, and organizational process assets.
Final report, project document updates, and organizational process assets updates.
When closing the project, the Project Manager reviews the project management plan to ensure that all project work is completed and that the project has met its objectives. The project documents are updated accordingly.
A group of customers has complained that their expectations are not met on a hybrid project. They say the main deliverable has failed a basic performance test and it is not useable for their needs.
What should the project manager do to prevent this from happening again?
a.
Collect feedback from them throughout the project.
b.
Document their needs once the project executes.
c.
Make use of conflict management techniques.
d.
Have them conduct risk assessments throughout the project.
Collect feedback from them throughout the project.
One method to ensure work is accepted once completed is to have more engagement of customers throughout your project.
A hybrid project has a change request that was approved to develop a fix to one of the original requirements. The team conducted data analysis and the change request was approved.
What should the project manager do next?
a.
Review the data analysis.
b.
Have the sponsor review the data analysis.
c.
Execute the change request.
d.
Deny the change request.
Execute the change request.
Once a change is approved, it should be implemented.
A project manager is being assigned to an ongoing company project. After approving the project management plan and the work has started the project manager has determined that this project will most likely fail to meet its objectives.
What should the project manager do in this situation?
a.
Review any assumptions and do more research on why the project may fail
b.
Meet with the organization PMO and terminate the project
c.
Alert project sponsor and informed him of this
d.
Add this to the issue log and inform the project team
Review any assumptions and do more research on why the project may fail
The best choice here would be to do more research and determine if any assumptions are actually correct since the project manager feels this project may fail.
As part of active leadership on an agile project, project managers support team member’s growth and keep them driven throughout each project.
What is one trait that supports this effective leadership?
a.
Use daily conversation sessions to solicit and respond to the team’s concerns.
b.
Provide a team reward for each successfully completed sprint
c.
Stand up for the team’s views.
d.
Challenge the team by giving project tasks.
Stand up for the team’s views.
It is important on an agile project to be a servant leader and that means supporting and standing for the team.
Before the team starts the third sprint on an agile project, the project manager is unsure whether or how much work they can complete in the next sprint.
What should the project manager do in this situation?
a.
Have the team create a detailed plan of how they will complete the work in the product backlog
b.
Replace any team member that lacks skills needed to complete the work in the next sprint
c.
Ask the team to work overtime to complete the work in the next sprint to ensure the project stays on schedule
d.
Have the team compute the velocity and then choose work based on the velocity
Have the team compute the velocity and then choose work based on the velocity
The team should choose work based on their velocity. Since the team completed a few sprints, they can easily compute this velocity to determine how much work they can get done in the next sprint.
While working on an agile project, the project manager notices two team members have been complaining about the same issue for the last two weeks. The issue seems to be something about the product owner not being happy with their work.
What should the project manager do?
a.
Inform the product owner they’re not allowed to speak to team members
b.
Review what the main cause of this issue is and help them to remove this impediment
c.
Inform the team members to ignore the product owner and complete the work
d.
Report this issue to the PMO and ask for help
Review what the main cause of this issue is and help them to remove this impediment
The best course of action would be to find the main cause of this issue and then remove this impediment that the team can get back to work.
A project manager is starting a project using an agile approach and notices most team members only have knowledge of the traditional approach.
What does the project manager need to do first?
a.
Have the team start the project and learn as they go
b.
Have the team go through e-learning courses to learn more about agile methods
c.
Remove team members without the correct knowledge and replace them with team members that know agile
d.
Meet with the team to determine what the training requirements would be and then implement a solution to get the training done
Meet with the team to determine what the training requirements would be and then implement a solution to get the training done
The best choice would be to meet with the team and determine what training requirements they will need and then implement those training requirements.