Test 1 Flashcards
- 0POP04-AE-0003 Loss of power to 13.8 kV Standby Bus*
- *
What is a major concern if RCB chillwater is lost to the RCFCs?
Could cause RCB Chillwater relief to lift
Could cause low flow trip of RCB Chillers
- 0POP04-RP-0001 Loss of Automatic PZR Pressure Control*
- *
What conditions would cause you to enter 0POP04-RP-0001 Loss of Automatic PZR Pressure Control?
PZR Pressure Controller fails in Auto
PZR pressure control instrument fails
- 0POP04-TM-0003 Turbine Trip < P-9*
- *
At what Tavg would the operator place rods in manual?
577 ˚F
- 0POP04-CD-0001 Loss of Condensate Flow*
- *
What must be done if DA Level reaches 30%?
Trip the Rx
Go to 0POP05-EO-EO00
- 0POP04-TM-0003 Turbine Trip < P-9*
- *
What are the operator actions if the Throttle valves fail to close during a turbine trip?
Trip the Rx
Close MSIVs and MSIBs
Go To 0POP05-EO-EO00
- 0POP04-NI-0001 Nuclear Instrumentation Malfunction*
- *
If a power range NI fails, the operator must check that P-7, P-8, P-9, and P-10 are in their correct state within 1 hr. If they are not in their correct state, what must the operator do?
Enter LCO 3.0.3
- 0POP04-RC-0006 Shutdown LOCA*
- *
When is 0POP04-RC-0006 Shutdown LOCA applicable?
MODE 3 < 1000 psig
MODE 4
- 0POP04-CW-0001 Loss of Circulating Water Flow*
- *
If water boxes must be isolated for a loss of circulating water, then what precautions must be followed?
Do not isolate both water boxes in the same condenser shell
Do not isolate 11 North and 13 South b/c FW heater high level dumps enter the condenser in those water boxes
- With a reduction in CW flow isolating a water box will raise CW discharge pressure.
- CW discharge pressure needs to be maintained at least 3 psig to prevent pump runout.
- 0POP04-RC-0002 RCP Off Normal*
- *
What RCP Case and Shaft Vibrations would require the operator to trip the RCP?
Case Vibration:
≥ 5 mils
≥ 3 mils and rising ≥ 0.2 mils/hr
- Shaft Vibration:*
- *≥ 20 mils**
- *≥ 15 mils and rising ≥ 1 mils/hr**
- Ensure Rx Tripped
- Ensure Turbine Tripped
- Stop affected RCPs
- Perform 0POP05-EO-EO00
- 0POP04-OC-0001 Loss of OL-ACW*
- *
At what motor temperature should the operator secure the affected OL-ACW pump?
266 ˚F
Motor insulation starts to degrade.
- 0POP04-RC-0004 SG Tube Leakage*
- *
What must the operator do if PZR level reaches 17% and PZR level is still lowering?
Ensure Rx Tripped
Initiate SI
Perform 0POP05-EO-EO00
Must also take actions if:
- VCT Level cannot be maintained > 15% with CCP suction aligned to VCT.
- RCS leakrate exceeds 200 gpm and PZR level is lowering
- 0POP04-AE-0001 Loss of AC Power*
- *
If a Class 1E battery is realigned to an operating battery charger in ≤ 15 min AND ≤ 1 battery cell is jumpered, then what must be done to declare it OPERABLE?
Verify Operating Battery Charger normal float voltage ≥ 128.5 VDC
Note:
A Class 1E battery is INOPERABLE anytime it is NOT aligned to an operating battery charger.
- 0POP04-IA-0001 Loss of Instrument Air*
- *
What would the operator do if Instrument air were lost and VCT level reaches 10%?
Re-align suction of CCP to RWST
- 0POP04-RC-0006 Shutdown LOCA*
- *
When must the operator manually switch to cold leg recirc?
RWST < 75,000 gal (14%)
AND
Containment WR Sump Level > 15”
Must also place FHB Exhaust in service.
0POP04-TM-0004 Failure of PT-505/PT-506
Do rods have to be taken to manual if PT-506 fails?
Yes
Step 1.0 in 0POP04-TM-0004 places rods in manual regardless of instrument (PT-505/PT-506) or failure (High/Low).
Note:
Step 8.0 has the operator check which instrument failed and then take rods back to auto at US discretion.
- 0POP04-FW-0002 SGFP Trip*
- *
Operation in what power levels is not permitted with > 1 GV out of service?
20 - 75% Power
Could result in rotor damage due to Double Shock Condition.
- 0POP04-CR-0001 Loss of Condenser Vacuum*
- *
What must be done if main turbine vacuum is < 21” Hg?
Ensure Rx Tripped
Ensure Turbine Tripped
Perform 0POP05-EO-EO00
- 0POP04-TM-0005 Fast Load Reduction*
- *
What are the boration thumbrules to perform a fast load reduction from 100% to 10% RTP at EOL? (16,000 MWD/MTU or 190 ppm boron)
- 100% - 50%:*
- *191 gal / 10% RTP reduction**
- 50% - 10%:*
- *31 gal / 10% RTP reduction**
- The differential rod worth almost doubles as the ‘C’ control bank inserts; thus, compensating for power defect. Therefore, boron addition values less than 50% decrease sharply.*
Assumptions:
- 100% RTP
- Rods in Auto
- Tavg/Tref ≤ 3 ˚F
- ≥ 50 steps above RIL
Note:
≈ 5 min - 7 min delay before boration addition is observed in plant response.
- 0POP04-AE-0007 Loss of all AC while on S/D Cooling*
- *
What are the criteria to verify natural circulation?
SG Pressures - Stable or Lowering
RCS Hot Leg Temp - Stable or Lowering
CETs - Stable or Lowering
RCS Cold Leg Temp - Saturation Temp of SG Pressure
- 0POP04-TM-0005 Fast Load Reduction*
- *
Below what Rx Power level are we able to trip the Rx per 0POP04-TM-0005 Fast Load Reduction?
< 10% Rx Power
- 0POP04-AE-0007 Loss of all AC while on S/D Cooling*
- *
What is the preferred order for re-energizing ESF busses?
C-A-B
- 0POP04-AE-0005 Offsite Power System Degraded Voltage*
- *
What voltage on the north AND south bus would cause you to enter 0POP04-AE-0005 Offsite power system degraded voltage?
339 kV
- 0POP04-RC-0002 RCP Off Normal*
- *
What must the operator do if all seal cooling is lost to the #1 RCP seal?
Trip Rx
Ensure Main Turbine Tripped
Trip affected RCP within 1 minute
Perform 0POP05-EO-EO00
If RCP Seal temp < 230 ˚F:
- Ensure PDP Recirc Valve 100% open
- Start PDP
- Slowly close PDP Recirc Valve to lower seal water bearing temp < 1˚F/min
- 0POP04-NI-0001 Nuclear Instrumentation Malfunction*
- *
What are the operator immediate actions if the power range NIs are not functioning properly?
Place Rods in Manual
- *Place LPFRVs in Manual**
- If being used to feed SG*
Control SGWL between 68% - 74%








