Termination for Breach Flashcards

You may prefer our related Brainscape-certified flashcards:
0
Q

The Hannah Blumenthal (1983)

A

A contract can be ended by implication arising from conduct.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
1
Q

British Russian Gazette v Associated Newspaper Ltd (1933)

A

If one party has already performed their side of a contract before discharge by agreement, accord and satisfaction is necessary.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

The Mihalis Angelos (1970)

A

Claimant agreed to lease a ship from the defendant at a specified date, the ship was not ready for this date, held: the ready to load date was a condition - necessary for legal certainty.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Hong Kong Fir v Kawasaki (1962)

A

Ship was chartered for 24 months, was not available for 5 months due to damages, was held that this did not amount to substantial deprivation of the whole benefit, breach was not repudiatory.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

The Hansa Nord (1976)

A

Some of a load of goods was damaged, buyer rejected load, seller sold to a third party cheaply, the original buyer then bought the goods from this party, held: no repudiatory breach, the buyer shouldn’t have terminated, a price reduction would have been sufficient.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Arcos v Ranaason (1933)

A

Implied term found that goods must match their description.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Bunge Corporation v Tradax (1981)

A

Buyer was required to give 15 days notice for loading of goods, only gave 13, court held it was a condition, necessary for legal certainty.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Schuler v Wickman

A

Agreed weekly visits would occur, called it a condition in the contract, whole contract was examined, held: it wouldn’t be reasonable for the term to be held to be a condition.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Lombard North Central v Butterworth (1987)

A

Contract for lease of computer contained clause requiring prompt payment, held to be a condition, parties had demonstrated that it was an essential term.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Poussard v Spiers (1876)

A

P was an opera singer engaged to perform for 3 months, she missed the first few days due to illness and was fired, held: performance of the first few days was extremely important, could be a condition.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Bettini v Gye (1876)

A

Opera singer missed a few days of rehearsals, not a condition, they did not go to the core of the contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

The Santa Clara (1996)

A

Communication need not be in language of acceptance, may be implicit in conduct.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Photo Production v Securicor (1980)

A

Company had exclusion clause in their contract excluding liability for damages, it was argued that contract (including exclusion clause) ceased to exist when it was broken, held contract still existed, secondary obligations were now in force.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

White & Carter v McGregor (1962)

A

One party wished to end the contract, committed repudiatory breach, the other party affirmed the contract as punishment, held they could do this, affirming only not an option if the contract requires cooperation or there is no legitimate interest financial or otherwise in affirming.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Attica v Ferrostaal (1976)

A

Ship was rented but not returned due to damages, leaser was willing to pay damages rather than return the ship, held: there was no legitimate interest in requiring the ship to be returned.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Hochster v De La Tour

A

On 11 May a contract was cancelled (before performance), court action was taken on 22 May, held: damages could be claimed from 11 May when the anticipatory breach occurred

16
Q

Woodar v Wimpey

A

Defendant tried to terminate a contract based on a termination clause that turned out not to exist, held: there was no anticipatory breach, simply a reliance by a party on a clause that didn’t exist.