1
Q
Tender Package
A
Notice to tenders ' Conditions of tendering conditions of contract (as 4000) Contract schedules Schedule of provisional sums Tender form (for consistency) Technical specification Drawings Information only documents
2
Q
SW vs MW
A
SW owner occupier is staged (ie at lock up)
MW is monthly payments
3
Q
Contract schedules
A
Clause Al - overall conduct of the parties
Clause A2 ç and A3- obligations and warranties of the builder.
Clause A4 and A5- obligations of the owner.
Clause A6- architects obligations as administrator
Clauses A7 and A8- instructions and disputed decisions
B1 - discrepancies
B2 - order of documents
B3 - documents for the architect
C- Security (cash retention or unconditional guarantees)
4
Q
Security
A
Half released on practical completion
Half released an final completion
Architect issues negative certificates for the owner to claim security.