Technical Competencies Flashcards
Commercial management. Can you give me an example when you’ve completed a value engineering exercise?
At HMP Wood Hill as commercial manager I carried out a commercial impact assessment of a change in design to reduce the still support components working alongside the structure engineer I assessed in quantified the design cost in time of the revised design and material process. Presented this back as an ad admit to the original allowance to the client.
Have you ever produced monthly project cost reports?
At Peak East I produced monthly CVR reports to compare the overall project cost and value. All works in progress accounted for including liabilities and across within the period. I have reviewed the risk and contingency items within the project budget and identified completed items.
Can you explain your advice on risk? Allow allowances for excavation?
At Branford substation the risk allowances for work area one were not required due to a GPR survey being completed. Management team that any remaining risk allowance be carried over into the remaining work areas. Hard ground conditions have been encountered in work area one which meant a transfer contingency into phase 2 works ground conditions item
Please can you explain your advice at Barking substation for commercial management?
Project manager issued guidance on dealing with COVID-19 restrictions and how they should be a deer to on site. I assess the impact of the restrictions and conducted an analysis of the commercial implications on the project budget and program. I advised the project manager that resequencing of works would enable staggered brakes and social distancing. I assess the financial implications on time and cost in comparison to the previous project outputs.
Construction technology. Can you explain your advice at Polypipe manufacturing facility?
I assessed the cost impact of a changing design for a 2000 mm reinforced concrete slab. CV is requested by a design team which found the bearing value of the saw below was not suitable to carry the weight of the slab. I assessed the commercial impact of an additional A303 mesh required to achieve the design
Construction technology. What advice was provided at Channing Wood?
H&P Channing Wood assessed a concept design layout which was generic and did not make consideration for ground make up and bridging over services. After a GPS survey the services positions were confirmed and I assess the impact of the design changes on time and cost.
Can you explain your assessment of protecting steelwork?
Project Sunrise the still work became damaged due to the harsh coastal conditions. Three options. Offsite manufacturing a marine grade powder coating. In situ covering the affected areas with brown thorax and zinc galvanising spray. Remove and reinstall. In situ painting was the most commercial advantageous as shipping to the UK and removal and reinstalled other significant impact and time and cost.
Can you explain your work at Branford substation for construction technology
Concrete cracking repairs were required and I assess the impact of three options. Resident injection. Concrete patching. Remove and reinstall. Recommended resin injection as it provided suitable long-term solution and could be delivered in a median time and cost impact. Presented the works in a slide deck to the main contractor.
Can you explain your responsibilities for submitting compensation events
At Branford substation I was responsible for submitting CE notifications in line with the NEC3 option A impact on the defined cost and planned completion. I also completed AFP’s assessing the current work completed an amount due within the period.
Can you explain when you were involved in a contractual strategy to engage a civil works contractor on site?
At Project sunrise or reviewed the main contract in line with the clients requirements and advised on the appropriate option secondary option and causes. I drafted the NEC3 contract and documentation such as data part one.
Can you provide me an example of when you have prepared to subcontract order?
At Branford substation for the supply and install and commissioning of earthing works. I stated out LEDs would be applied and defect responsibilities. I’m sure little fencing risk exposure was delegated through track core clauses four and Z clauses to prevent ambiguity. I outlined the LAD and how they would apply to each sectional completion date within contract date part one
Give me an example of when you produce an activity schedule
Barking substation under NEC3 option a subcontract. I undertook a review of the subcontractors works information contract obligations project timeline and deliverables. I advised program requirements and sub activities would be incorporated to avoid cash flow issues.
Procurement and tendering. Can you give me an example of where you have assisted in preparing tender documents?
A project sunrise I drafted the RFP including works information site information and drawings. I issued the ITT and was responsible for commercial tender queries, clarification and negotiation.
Can you give me an example of when you have led attend tender bed
A Bradford substation liaise with the estimating department to ensure attend the queries issued in a prompt manner along with risk clarification. I reviewed the activity schedule and worked alongside the plan to ensure bid was comprehensive and competitive. I then drafted track data part two and it should all required documentation was returned to the contractor within time stated.
What work did you carry out for UK PN services?
I was responsible for developing the procurement stress to improve efficiency and overall profitability for the materials category. I worked on the strategy to review business objectives and online procurement objectives to develop the overall improvement plan.