Q

Tac vent def:

A

Planned, systemic and coordinated removal of hot smoke and fire gases and their replacement with fresh air

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Never commence if..

A

Ff teams could be adversely affected

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Establishing the Tac V plan

A

Assess prevailing wind conditions affecting potential vent pathways

Availability of suitable vent in & outlets

Ident vent pathway

Secure vent pathway

Weight of attack

Covering jets

Ff activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

360 survey will provide info relating to L - F - B. What is this?

A

L life risk (obvious signs)

F fire (location and vented?

B Building (access points, construction, fixed installations)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

PPV should improve conditions and reduce temps. If not then…

A

Fans must be switched off and crews should consider alternative options whilst being protected from fore compartment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Smoke blocker must avoid contact with fire. Temps in excess of

A

260 will slowly degrade the fabric

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Establish a suitable outlet before creating inlet

A

Yes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

PPV. How many and on what

A

2
SAWD special all wheel drive vehicles

Only used by appropriately trained

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Tac vent for

A

Limit or reduce spread of fore and products…

Improve conditions

Dilute and remove products…

Assist with building evac

Improve working conditions & cas survivability

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

During Tac vent comms fail

A

Cease offensive ventilation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Vent pathway must inc

A

Inlet

Outlet

Enclosed route from inlet to fire

Enclosed route from fire to outlet (to avoid uncontrolled spread of products

Charged covering jets (in & outlet)

Consider all available info to assist
Plans, PIB, TIC, SFSO,MDT, TL, etc

360 with TIC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Inlet size

A

Twice as large as outlet

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Outlet made first followed by inlet

A

Yes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

3 levels of PPV

A

1 defensive. Post fire, fire out

2 offensive. Fire under control but still burning

3 offensive. On before committing crews, outlets made

How well did you know this?