Systems Exam 1 - TRM: Technical Requirements Manual Flashcards

1
Q

Is the TRM an LBD, and how is it revised?

A

Yes, it’s considered an LBD. However, revision requires SORC and Plant Manager approval as long as the changes meet 50.59SC. Otherwise, NRC approval is req’d.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Describe LCO applicability in the TS as it compares to the TRM.

A

Same except there is no 3.0.3 and 3.0.6 in the TRM. For 3.0.3 the TRM either:
1. Directs user to TS
2. Has applicable actions in them
3. Need an IR written but a shutdown is not req’d