PROJECT TEAM
Constructs a project to convert a design into a physical facility.
Includes estimating, scheduling, subcontracting, and overall
project management.

A

Contractor Team

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

PROJECT TEAM
Initiates the project; assumes the risk; provides funding, control,
and management of the design and construction process;
approves design and construction activities, and acts as the
principal stakeholder.

A

Owner Team

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

PROJECT TEAM
A wide variety of companies that furnish the materials and
products for the project to be constructed; they typically do not
install materials, but may be required to certify installers
or observe installation for complicated work.

A

Supplier Team

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

PROJECT TEAM
Works with the owner to deliver a facility meeting the owner’s
aspirations and requirements; transforms the owner’s vision from
original concepts and ideas into the documentation required.

A

Design Team

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

PROJECT TEAM COMPOSITION
Public and
private owners,
owner advisors,
owner consultants,
occupants, utility
service providers,
and authorities
having jurisdiction.

A

Owner Team

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

PROJECT TEAM COMPOSITION
Architects,
engineering
consultants, and
specialty consultants.

A

Design Team

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

PROJECT TEAM COMPOSITION
Contractors and
subcontractors.

A

Contractor Team

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

PROJECT TEAM COMPOSITION
Manufacturers,
distributors,
suppliers, and
fabricators.

A

Supplier Team

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

PROJECT TEAM/RESPONSIBLE PARTICIPANT
Arranges project financing

A

PROJECT TEAM:
Owner

RESPONSIBLE PARTICIPANT:
Financial Institutions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

PROJECT TEAM/RESPONSIBLE PARTICIPANT
Advises, assists, makes
recommendations, and evaluates
the design for compliance with
the applicable building codes

A

PROJECT TEAM:
Design

RESPONSIBLE PARTICIPANT:
Architect

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

PROJECT TEAM/RESPONSIBLE PARTICIPANT
Answers technical inquiries from
the design and construction teams,
presents seminars, and performs
other educational activities

A

PROJECT TEAM:
Supplier

RESPONSIBLE PARTICIPANT:
Manufacturer’s technical employee

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

PROJECT TEAM/RESPONSIBLE PARTICIPANT
Arranges sales appointments,
quotes pricing information, takes
purchase orders, and arranges for
product shipment

A

PROJECT TEAM:
Supplier

RESPONSIBLE PARTICIPANT:
Manufacturer’s sales employee

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

PROJECT TEAM/RESPONSIBLE PARTICIPANT
Buys, inventories, and resells
materials, products, components,
assemblies, and equipment that
can be either fabricated or directly
incorporated into projects

A

PROJECT TEAM:
Supplier

RESPONSIBLE PARTICIPANT:
Independent Sales Representative

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

PROJECT TEAM/RESPONSIBLE PARTICIPANT
Contracts with a manufacturer to
promote products within a defined
geographic area

A

PROJECT TEAM:
Supplier

RESPONSIBLE PARTICIPANT:
Distributors

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

PROJECT TEAM/RESPONSIBLE PARTICIPANT
Designs the aesthetic and
technical aspects of a project

A

PROJECT TEAM:
Design

RESPONSIBLE PARTICIPANT:
Architect

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

PROJECT TEAM/RESPONSIBLE PARTICIPANT
Determines the cost of the work

A

PROJECT TEAM:
Contractor

RESPONSIBLE PARTICIPANT:
Estimator

17
Q

PROJECT TEAM/RESPONSIBLE PARTICIPANT
Directs, manages, and coordinates
the day-to-day activities of a
construction project

A

PROJECT TEAM:
Contractor

RESPONSIBLE PARTICIPANT:
Superintendent

18
Q

PROJECT TEAM/RESPONSIBLE PARTICIPANT
Establishes, monitors, and maintains
safety on the construction site

A

PROJECT TEAM:
Contractor

RESPONSIBLE PARTICIPANT:
Safety Director

19
Q

PROJECT TEAM/RESPONSIBLE PARTICIPANT
Examines the soil strata beneath
the surface of the ground and
subsurface geological formations
and makes recommendations for
the design of the facility foundations

A

PROJECT TEAM:
Owner

RESPONSIBLE PARTICIPANT:
Geotechnical Engineer

20
Q

PROJECT TEAM/RESPONSIBLE PARTICIPANT
Manages information about building
technology and sciences

A

PROJECT TEAM:
Design

RESPONSIBLE PARTICIPANT:
Specifier/Knowledge Manager

21
Q

PROJECT TEAM/RESPONSIBLE PARTICIPANT
Occupies the facility for which it
was designed and constructed to
conduct activities in accordance
with its intended purpose

A

PROJECT TEAM:
Owner

RESPONSIBLE PARTICIPANT:
Facility Users

22
Q

PROJECT TEAM/RESPONSIBLE PARTICIPANT
Oversees the construction contract

A

PROJECT TEAM:
Contractor

RESPONSIBLE PARTICIPANT:
Construction Contract Administrator

23
Q

PROJECT TEAM/RESPONSIBLE PARTICIPANT
Provides general management
of the contractor’s staff, suppliers,
and subcontractors, and guides
the project through the
construction portion of the
project delivery method

A

PROJECT TEAM:
Contractor

RESPONSIBLE PARTICIPANT:
Construction Project Manager

24
Q

PROJECT TEAM/RESPONSIBLE PARTICIPANT
Provides risk coverage

A

PROJECT TEAM:
Owner

RESPONSIBLE PARTICIPANT:
Life Insurance Companies

25
Q

PROJECT TEAM/RESPONSIBLE PARTICIPANT
Provides the labor, materials,
and services required for the
construction of a specific portion
of the work

A

PROJECT TEAM:
Contractor

RESPONSIBLE PARTICIPANT:
Subcontractor

26
Q

PROJECT TEAM/RESPONSIBLE PARTICIPANT
Researches the market to
determine what is important
to buyers and decision makers

A

PROJECT TEAM:
Supplier

RESPONSIBLE PARTICIPANT:
Manufacturer’s Marketing Employees

27
Q

PROJECT TEAM/RESPONSIBLE PARTICIPANT
Surveys land on which projects
are constructed to document the
existing conditions and features

A

PROJECT TEAM:
Owner

RESPONSIBLE PARTICIPANT:
Surveyor

28
Q

PROJECT TEAM/RESPONSIBLE PARTICIPANT
Technical and engineering designer
of structures that resist or support
static and dynamic loads

A

PROJECT TEAM:
Design

RESPONSIBLE PARTICIPANT:
Structural Engineer

29
Q

4 “C’s” OF COMMUNICATION
Use proper grammar and simple sentence construction
to avoid ambiguity.

A
30
Q

4 “C’s” OF COMMUNICATION
Do not leave out important information.

A
31
Q

4 “C’s” OF COMMUNICATION
Present information accurately and precisely.
Carefully select words that convey exact meanings.

A
32
Q

4 “C’s” OF COMMUNICATION
Eliminate unnecessary words, but not at the expense of clarity,
correctness, or completeness.

A
33
Q

What are the project life cycle stages?

A

Project conception, design, construction documents, procurement, construction, facility management