Which type of business case is used when an organization authorizes a project that adjusts organizational practices because of new federal guidelines?

A

Legal Requirement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is a positive float?

A

The amount of time that a non-critical activity’s start can be delayed without affecting the project completion date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What does VAC represent?

A

Variance at completion (VAC) is the budget variance expected at the end of the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What does the acronym SME denote?

A

Subject Matter expert

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What work should a PMP accept for a project?

A

Only work that supports the project charter and the needs of the stakholders

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are team building activities?

A

activities that are conducted to increase performance and cohesiveness

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is LOE?

A

Level of Effort

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the difference between a Request for Proposal and a Request for Quote?

A

RFP is a detailed proposal including pricing, and RFQ is only a price quote

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are assumptions?

A

Factors considered to be true for planning purposes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

How do you perform a backwards pass?

A

Follow network diagram from project finish to project start. For each activity subtract the activity’s duration from the late finish to derive the late start of the activity.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Who has ultimate accountability for quality of the project?

A

The project manager

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What environment includes the economy, competitive environment, and legislative constraints?

A

External environment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Why is statistical sampling used in measuring quality?

A

because it is not feasible to perform inspection for the entire population

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What does the acronym RDU denote?

A

Remaining duration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What would be the only situation in which you would create a revised schedule baseline?

A

When approved changes are identified

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is identified in the cost management plan?

A

Procedures that will be used to modify the cost baseline and manage costs through the project

17
Q

Which system is the most important in controlling scope creep?

A

Change control system

18
Q

What negotiation is used when acquiring resources?

A

to obtain necessary staff or resources

19
Q

Which term refers to a document that specifies the characteristics of a product, process, or service to which it is mandatory to comply?

A

Regulations

20
Q

The minimum viable product (MVP) is a pillar of what approach?

A

The iterative approach, providing a fully functioning value deliverable, but does not include all possible value.

21
Q

What are the 5 process groups required for any project?

A

Initiative
Planning
Executing
Monitoring
Closing

22
Q

What are three categories of processes?

A

There are three categories of processes—those used only once, those used periodically, and those used continuously.

23
Q

What is the difference between data and information?

A

data is typically an output while information is an input.

24
Q

What are the 4 values of Agile?

A
  1. Individuals and interactions over processes and tools
  2. Working software over comprehensive documentation
  3. Customer collaboration over contract negotiation
  4. Responding to change over following a plan
25
Q

How do you determine the most appropriate project life cycle?

A

Agile Suitability Filter