Stepwise Project Planning Flashcards

1
Q

Step 0: Select Project

A

A clear and concise name that identifies the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Step 1: Identify project scope and objectives

A

Identify objectives and practical measures of the effectiveness in meeting those objectives
Establish a project authority
Stakeholder analysis - identify all stakeholders in the project and their interests.
Establish methods of communication with all parties.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Step 2 : Identify project infrastructure

A

Identify relationship between project and strategic planning
Identify installation standards and procedures
Identify project team organization

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Step 3 : Analyse project characteristics

A

Distinguish the project as either objectives- or product-driven.
Analyse other project characteristics
Identify high-level project risks
Select development methodology and life-cycle approach
Review overall resource estimates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Step 4 : Identify project products and activities

A

Identify and describe project products (or deliverables)
Document generic product flows
Recognize product instances
Produce ideal activity network
Modify the ideal to take into account need for stages and checkpoints

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Step 5 : Estimate effort for each activity

A

Carry out bottom-up estimates
Revise plan to create controllable activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Step 6 : Identify activity risks

A

Identify and quantify activity based risks
Plan risk reduction and contingency measures
Adjust overall plans and estimates to take account of risks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Step 7 : Allocate resources

A

Identify and allocate resources
Revise plans and estimates to take into account resource constraints

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Step 8 : Review/ Publicize plans

A

Review quality aspects of the project plan
Document plans and obtain agreement or approval

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Steps 9 & 10: Execute plan. Lower levels of planning

A

The project team members, under the direction of the project manager, begin to carry out the tasks and activities as per the project plan.