Starting a Project Flashcards
Purpose of Starting a Project process
To ensure pre-requisites for starting a project are in place by answering “Do we have a viable and worthwhile project”
Objective of Starting a Project
6
Ensure:
1.business justification to initiate a project
2.proj brief - to define proj scope
3.proj mgmt team appointment
4.options explored and approach selected
5.stage plan for initiating a proj
6.no unsound assumptions leading to wasted time
———- is the trigger for a PRINCE2 Project.
Project Mandate
Starting Up a Project: Activities
6
I.corporate appoints executive and PM
II.capture lessons
III.appoint proj mgmt team
IV.prep outline business case
V.select approach and prep proj brief
VI.plan initiation stage
—- represents business interests of the three primary project stakeholders.
I.appoint executive and PM
executive
appointment of —— is a prerequisite for the project to be justified.
I.appoint executive and PM
executive
To appoint executive, corporate has to do…
6
I.appoint executive and PM
- establish RnR
- time and effort needed for role
- identify candidates and select
- confirm selected person’s availabiliy, acceptance and commitment
- assign selected person as executive
who appoints PM
executive
To appoint PM, executive has to do…
- establish RnR
- time and effort needed for role
- identify candidates and select
- confirm selected person’s availabiliy, acceptance and commitment
- assign selected person as PM
- confirm PM appointment to corporate
where does PM capture project info not captured anywhere else
daily log