Standards: PM Process Group & Knowledge Area Mapping Flashcards
Project Management Knowledge Areas
An identified area of project management defined by its knowledge requirements and described in terms of it’s processes, practices, inputs, outputs, tools and techniques
Areas of specialization and set of processes associated with a particular topic in project management
10 knowledge areas
Name the 10 knowledge areas
1) project integration management
2) scope management
3) schedule management
4) cost management
5) quality management
6) resource management
7) communications management
8) risk management
9) procurement management
10) stakeholder management
Project Management Process Groups
Logical grouping of project management inputs, tools and techniques and outputs.
All process groups can happen within a phase as goal is to repeat each Process Group until the completion criteria for each phase is met
Name the 5 Process Groups
1) initiating
2) planning
3) executing
4) monitoring and controlling
5) closing
Initiating Process Group
Consists of processes performed to define, document, and authorize a new project or project phase start and identify and analyze stakeholders
Happens at the start of each project and process group
Important to revisit information from this phase at the start of all the others to ensure project is focused on the business need identified at start of project
Purpose of Initiating Process Group?
Align stakeholders’ expectations and the project purpose, inform them on scope, objectives and discuss how their participation can ensure expectations are met
During this phase the following occurs:
- Initial scope defined
- Initial financial resources committed
- Stakeholders identified
- Project manager appointed
Initiating Process Group includes what project management processes?
1) Develop project charter
2) Identify stakeholders
Develop Project Charter: Inputs and Outputs?
Inputs:
-Business Documents, agreements, EEFs and OPAs
Outputs:
-Project charter and Assumption Log
Identify Stakeholders: Inputs and Outputs?
Inputs:
-Project charter, business documents, project management plan, project documents, agreements, EEFs and OPAs
Outputs:
-Stakeholder register, change requests, project management plan UPDATES and project document UPDATES
Planning Process Group
Processes that establish the total scope of effort, define and refine the objectives, and develop the course of action required to attain those objectives
Purpose of Planning Process Group?
Purpose: develop Project Management Plan and Project Documents
Define the course of action to successfully complete the project or phase
What is a Project Management Plan?
Document that describes how the project will be executed, monitored and controlled and closed
What is Progressive Elaboration?
Ongoing refinement of and increasing level of detail of the Project Management Plan
What is a Project Charter
Document issued by project initiator/sponsor that formally authorizes the existence of a project and allows PM to start allocating project resources and activities
Develop Project Management Plan: Inputs & Outputs
Inputs:
-Project charter, Outputs from other processes, EEFs, and OPAs
Outputs:
-Project Management Plan
Plan Scope Management: Inputs & Outputs
Documents how scope is defined, validated and controlled
Inputs: -Project charter, Project management plan, EEFs and OPAs Outputs: -Scope Management Plan and Requirements Management Plan
Collect Requirements: Inputs & Outputs
Process of determining, documenting and managing stakeholder requirements to meet objectives
Inputs:
-project charter, project management plan, project documents, business documents, Agreements, EEFs, and OPAs
Outputs:
- Requirements documentation
- Requirements traceability matrix
Define Scope: Inputs & Outputs
Developing detailed description of project and product
Inputs:
-Project charter, project management plan, project documents, EEFs, OPAs
Outputs:
-Project scope statement and project documents UPDATES
Purpose of Define Scope
Describes the product, service or result boundaries and acceptance criteria
Define Work Breakdown Structure (WBS) and it’s benefit
Process of subdividing project deliverables and work into smaller more manageable components so as to provide framework of what has to be delivered
Work Breakdown Structure (WBS): inputs & outputs
Inputs:
-Project management plan, project documents, EEFS and OPAs
Outputs:
-Scope baseline and Project document UPDATES
Plan Schedule Management and it’s benefit
Process of establishing policies, procedures and documents for sequencing project schedule
Outlines how project will take shape over time
Plan Schedule Management: Inputs & Outputs
Inputs:
-Project charter, project management plan, EEFS and OPAs
Outputs: Schedule Management plan
Define Activities and it’s benefit
Identifying action steps needed to produce deliverables so the project breaks down work packages into scheduled activities that provide a basis for estimating, scheduling, executing, monitoring and controlling the project
Define Activities: Inputs & Outputs
Inputs:
-Project management plan, EEFs and OPAs
Outputs:
-Activity list, activity attributes, milestone list, change requests, and project management plan UPDATES
Sequence Activities and it’s benefit
Process of identifying and documenting relationships among project activities and defines logical sequence
Sequence activities: Inputs and Outputs
Inputs:
-Project management plan, project documents, EEFs and OPAs
Outputs:
-Project schedule network diagrams and project document UPDATES
Estimate Activity Durations and it’s benefit
Estimation of how many work periods are needed to complete individual activities with resources.
Key Benefit: provides amount of time each activity will take to complete
Estimate Activity: Inputs & Outputs
Inputs:
-Project management plan, project documents, EEFs and OPAs
Outputs:
-Duration estimates, basis of estimates and project documents UPDATES
Develop Schedule and it’s benefit
Analyzing activity sequences, duration, resource requirements and schedule constraints to create a schedule model for the project and monitor/control it. Generates schedule model with planned dates for completing project activities
Develop Schedule: Inputs & Outputs
Inputs:
-Project management plan, project documents, agreements, EEFs and OPAs
Outputs:
-Schedule baseline, project schedule, schedule data, project calendars, change requests, project management plan UPDATES and project document UPDATES
Plan Cost Management and it’s benefit
Defining how project costs are estimated, budgeted, managed, monitored and controlled. Provides guidance and direction on how costs are managed throughout
Plan Cost Management: Inputs & Outputs
Inputs:
-Project charter, project management plan, EEFs and OPAs
Outputs:
-Cost management plan
Estimate Costs and it’s benefit
Developing an approximation of monetary resources needed to complete project
Estimate Costs: Inputs & Outputs
Inputs:
-Project management plan, project documents, EEFs and OPAs
Outputs:
-Cost estimates, basis of estimates and project document UPDATES
Determine Budget and it’s benefit
Aggregating estimated costs of individual activities/work packages to establish a cost baseline
Determines cost baseline that measured project performance and risk
Determine Budget: Inputs & Outputs
Inputs:
-Project management plan, project documents, business documents, agreements, EEFs and OPAs
Outputs:
-Cost baseline, project funding requirements and project document UPDATES
Plan Quality Management and it’s benefit
Identifying quality requirements and documenting how projects will achieve them. Provides quality assurance and management
Plan Quality Management: Inputs & Outputs
Inputs:
-Project charter, project management plan, project documents, EEFs and OPAs
Outputs:
-Quality management plan, quality metrics, project management plan UPDATES and project documents UPDATES
Plan Resource Management and it’s benefits
Defining how to estimate, acquire, manage and utilize resources. Establishes the approach and level of management effort needed for managing resources based on complexity
Plan Resource Management: Inputs & Outputs
Inputs:
-Project charter, project management plan, project documents, EEFs and OPAs
Outputs:
-Resource management plan, team charter and project documents UPDATES
Estimate Activity Resources and it’s benefits
Estimating team resources and quantity needed (equipment, material and supplies). These are physical and not people
Estimate Activity Resources: Inputs & Outputs
Inputs:
-Project management plan, project documents, EEFs and OPAs
Outputs:
-Resource requirements, basis of estimates, resource breakdown structure and project documents UPDATES