Schedule Management Ch 6 Flashcards

1
Q

What are the components of Schedule Management?

A
  1. 1 Plan schedule management: process of establishing the policies, procedures and documentation for planning, developing, managing and controlling the project schedule
  2. 2 Define activities: process of identifying and documenting the specific actions to be performed to produce the project deliverables
  3. 3 Sequence activities: Process of identifying and documenting relationships among the project activities
  4. 4 Estimate activity duration: process of estimating the number of work periods needed to complete individual activities with the estimated resources
  5. 5 Develop schedule: process of analyzing activity sequences, durations, resource requirements and schedule constraints to create the project schedule model for project execution and monitoring and controlling
  6. 6 Control schedule: Process of monitoring the status of the project to update the project schedule and manage changes to the schedule baseline
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the project schedule a result of?

A

Selecting scheduling method, then project-specific data (activities, planned dates, durations, resources, dependencies and constraints) are entered into a scheduling tool and create a schedule model for the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is Iterative Scheduling With a Backlog?

A

Form of Rolling Wave Planning and used in Agile

Key benefit: welcomes changes throughout the development life cycle

The requirements are documented as user stories that are prioritized and refined just before construction and the product features are developed using time boxed periods of work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is On-Demand Scheduling?

A

Team members pull work from queue when they have time

Does NOT rely on a schedule that was developed previously but pulls work from a backlog to be done immediately as resources become available

Used for projects that evolve the project incrementally in operational or sustainment environments or where tasks may be made relatively similar in size and scope or can be bundled by size and scope

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Define: Plan Schedule Management (6.1)

A

process of establishing the policies, procedures and documentation for planning, developing, managing and controlling the project schedule

Key benefit: provides guidance and direction on how the project schedule will be managed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Inputs: Plan Schedule Management

A

Project charter

Project Management Plan:

  • scope management plan
  • development approach

EEFs

OPAs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Tools/Techniques: Plan Schedule Management

A

Expert Judgement

Data Analysis (alternatives analysis)

Meetings

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Outputs: Plan Schedule Management

A

Schedule Management Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is a Schedule Management Plan?

A

Establishes the criteria and activities for developing, monitoring and controlling the schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Define: Define Activities (6.2)

A

process of identifying and documenting the specific actions to be performed to produce the project deliverables

Key benefit: it decomposes work packages into schedule activities that provide basis for estimating, scheduling, executing, monitoring and controlling the project work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Inputs: Define Activities

A

Project management plan:
-Schedule management
plan
-scope baseline

EEFs

OPAs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is Scope Baseline?

A

The project WBS, deliverables, constraints and assumptions documents in the scope baseline are considered when defining activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Tools/Techniques: Define Activities

A

Expert Judgement

Decomposition

Rolling Wave Planning

Meetings

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is Rolling Wave Planning?

A

Iterative project planning in waves as the project proceeds and later details become clearer. Work to be done in the near term is based on high level assumptions and high level milestones are set. As work progresses the milestones, risks and assumptions become more reliable and work further in the future is planned at a higher level

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Outputs: Define Activities

A

Activity List

Activity Attributes

Milestone List

Change Requests

Project Management Plan UPDATES:

  • schedule baseline
  • cost baseline
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What are Activity Attributes?

A

Identifying multiple components associated with each activity.

  • Initially includes unique activities identifier (ID), WBS IS and activity label/name
  • When completed, includes activity descriptions, predecessor activities, successor activities, logical relationships, leads and lags, resource requirements, imposed dates, constraints and assumptions
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Define: Sequence Activities (6.3)

A

Process of identifying and documenting relationships among the project activities

Key benefit: defines the logical sequence of work to obtain greatest efficiency give all project constraints

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Inputs: Sequence Activities

A

Project Management Plan:
-Schedule management
plan
-Scope baseline

Project Documents:

  • activity attributes
  • activity list
  • assumption log
  • milestone list

EEFs

OPAs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Tools/Techniques: Sequence Activities

A

Precedence Diagramming Method (PDM)

Dependency Determination and Integration

Leads & Lags

Project Management Information System (PMIS)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

What is Precedence Diagramming Method (PDM):

A

technique used for creating a schedule model where activities are represented by nodes and are graphically linked by one or more logical relationships to show the sequence in which the activities are to be performed

4 relationships

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What is Finish-to-Start (FS)

A

successor activity cannot start until predecessor activity has finished.

E.G. The foundation for the house must be finished (A) before the framing can start (B)

Most common

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

What is Finish-to-finish (FF)

A

Successor activity (Activity A) cannot finish before a predecessor activity (activity B) has finished

E.G. Writing a document (predecessor) is required to be finished before you can edit the document (successor)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

What is Start-to-Start (SS)

A

Successor activity (Activity A) cannot start until a predecessor activity (activity B) has started

E.G. Cannot level out concrete (successor) until you begin to pour the concrete (precessor) begins

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

What is Start-to-Finish (SF)

A

Successor activity (Activity A) must start before (Activity B) has finished

E.G. A new system (successor) must start before an old one is replaced. ONLY example of this

Least common

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

What kind of relationship is: “The foundation for the house must be finished (A) before the framing can start (B)”?

A

Finish-to-Start

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

What kind of relationship is “A new system (successor) must start before an old one is replaced. ONLY example of this”?

A

Start-to-Finish

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

What kind of relationship is “Cannot level out concrete (successor) until you begin to pour the concrete (precessor) begins”?

A

Start-to-Start

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

What kind of relationship is

“Writing a document (predecessor) is required to be finished before you can edit the document (successor)”?

A

Finish-to-Finish

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

What is Dependency Determination and Integration?

A

Dependencies categorized as mandatory, discretionary, internal or external

Can be two things

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

What is a Mandatory Dependency?

A

legally or contractually required or inherent in the nature of work

Often involve physical limitations

E.G. construction projects where it’s impossible to build structures until the foundation has been built

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

What is a Discretionary Dependency?

A

Established based on knowledge of best practices

Preferred logic, preferential logic or soft logic

E.G. Best practice is that during construction that you start with electrical work after finishing the plumbing. This isn’t required but performing them in this sequence reduces overall project risk

32
Q

What is an External Dependency?

A

involve relationship between project activities and non project activities (usually outside of team’s control)

E.G. the testing of project software is dependent on when the software is delivered

33
Q

What is an Internal Dependency?

A

Involve a precedence relationship between project activities and are generally inside the project team’s control

E.G. Team cannot test a machine until they assemble it

34
Q

What is a Lead?

A

lead in or jumpstart. Amount of time a successor activity can be advanced with respect to a predecessor activity

35
Q

What is a Lag?

A

Amount of time a successor activity will be delayed with respect to predecessor activity

36
Q

Output: Sequence Activities

A

Project Schedule Network Diagrams

Project Document UPDATES:

  • activity attributes
  • activity list
  • assumption log
  • milestone list
37
Q

What is a Schedule Network Diagram?

A

graphical relationship of the logical relationships/ dependencies, among the project schedule activities

38
Q

Define: Estimate Activity Durations (6.4)

A

process of estimating the number of work periods needed to complete individual activities with the estimated resources

Key benefit: provides the amount of time each activity will take to complete

39
Q

Inputs: Estimate Activity Durations

A

Project Management Plan:
-schedule management
plan
-scope baseline

Project Documents

EEFs

OPAs

40
Q

Tools/Techniques: Estimate Activity Durations

A

Expert Judgement

Analogous Estimating

Parametric Estimating

3 Point Estimating

Bottom up Estimating

Data Analysis Techniques

Decision Making

Meetings

41
Q

What is Analogous Estimating?

A

“analogy” of past to estimate

technique for estimating duration or cost of an activity (budget, duration, complexity, etc) of a project using historical data from a similar project

Often used when there’s a little detail on the project

42
Q

What is Parametric Estimating?

A

technique in which an algorithm is used to calculate cost or duration based on historical data and project parameters

Uses a statistical relationship between historical data and other variables

E.G. if assigned resource is capable of installing 25 meters of cable per hour, the duration required to install 1,000 meters is 40 hours (1,000/25 meters per hour= 40 hours)

43
Q

What is 3 Point Estimating?

A

helps to define an approximate range for an activity’s duration:

Expected duration (E)= (O + M +P) /3

  • Most Likely (M)
  • Optimistic (O)
  • Pessimistic (P)

Use when there’s insufficient historical data

44
Q

What is Bottom Up Estimating?

A

“Bottoms up” of WBS

estimating project duration or cost by aggregating the estimates of the lower-level components of the WBS.

45
Q

What is Reserve Analysis?

A

used to determine the amount of contingency and management reserved needed for the project. Used to account for schedule uncertainty.

Estimated duration within the schedule baseline

46
Q

Outputs: Estimate Activity Durations

A

Duration Estimates

Basis of Estimates

Project Document UPDATES:

  • activity attributes
  • assumption log
  • lessons learned register
47
Q

Define: Develop Schedule (6.5)

A

Process of analyzing activity sequences, durations, resource requirements and schedule constraints to create the project schedule model for project execution and monitoring and controlling

Key benefit: generates a schedule model with planned dates for completing project activities
Iterative process

48
Q

Inputs: Define Schedule

A

Project Management Plan:
-schedule management
plan
-scope baseline

Project Documents (activity attributes, activity list, assumption log, basis of estimates, lessons learned register, etc)

Agreements

EEFs

OPAs

49
Q

Tools/Techniques: Define Schedule

A

Schedule network Analysis

Critical Path Method

50
Q

What is Schedule Network Analysis?

A

Iterative process. Used until a viable schedule model is developed.

Used to generate the project schedule model. It employs several other techniques (critical path method, resource optimization techniques and modeling techniques).

51
Q

What a Critical Path?

A

sequence of activities that represents the longest path through a project, which determines the shortest possible duration.

Has the least total float (usually 0)

52
Q

How is the Critical Path Method used in scheduling?

A

Used to estimate the minimum project duration and determine the amount of schedule flexibility on the logical network paths within the scheduled model

53
Q

What is Total Float

A

amount of time that a schedule activity can be delayed or extended from its early start date without delaying the project finish date/end date

54
Q

What is Positive Total Float?

A

caused when the backward pass is calculated from a schedule constraint that is latter than the early finish date that has been calculated during forward pass calculation

55
Q

What is Negative Total Float?

A

caused when a constraint on the late dates is violated by duration and logic.

Negative float analysis helps to find possible accelerated ways of bringing a delayed schedule back on track

56
Q

What is Free Float?

A

amount of time that a schedule activity can be delayed without delaying the early start date of the next activity/ between activities

57
Q

What is Resource Leveling?

A

start and finish dates are adjusted based on resource constraints with the goal of balancing the demand for resources with the available supply.

Used when shared resources are available only at certain times/limited quantities, are over allocated or there is a need to keep resource usage at a constant level

Often causes critical path to change

58
Q

What is Resource Smoothing?

A

adjusts the activities of a schedule model such that the requirements for resources on the project do not exceed certain predefined resource limits. Activities may only be delayed within their free and total float

Critical path is NOT changed and the completion date may not be delayed

59
Q

What is Monte Carlo?

A

Simulation used to model the probability of different outcomes in a process that cannot easily be predicted due to random variables.

Used to predict the probability of different outcomes when the intervention of random variables is present.

Most common simulation

60
Q

What is Crashing?

A

Technique used to shorten the schedule duration for the least incremental cost by adding resources

E.G. paying OT to get the job done

61
Q

What is Fast Tracking?

A

Schedule compression technique in which activities/phases normally done in sequence are performed in parallel for a portion of their duration

62
Q

What is Agile Release Planning?

A

provides a high-level summary timeline of the release schedule (3-6 months) based on the product roadmap and the product visions for the product’s evolution

Shows customer which feature will be available at end of each iteration

63
Q

Outputs: Define Schedule

A

Schedule Baseline

Project Schedule

Schedule Data

Project Calendars

Change Requests

Project Management plan UPDATES

Project Document UPDATES

64
Q

What is a Schedule Baseline?

A

approved version of a schedule model that can only be changed through a formal change control

65
Q

What do Bar Chart/Gannt Charts show and how are they used?

A

Used to present project status to upper management

High level detail

Shows start & end dates, duration and order, precedence relationships and % completion

66
Q

What do Milestone Charts show and how are they used?

A

Shows major milestone deliverables and provides summary level view of project milestones

Uses icons/symbols

Used to show upper management

67
Q

What do Project Schedule Network Diagrams show and how are they used?

A

show activities and relationships without a time scale

“logic diagrams”

Communicates the project status in terms of activities in relation to each other

68
Q

Define: Control Schedule (6.6)

A

Process of monitoring the status of the project to update the project schedule and manage changes to the schedule baseline
Key benefit= schedule baseline is maintained throughout project

69
Q

If an Agile Approach is used, what is the focus of Control Schedule?

A

Determining current status of schedule by (comparing total amount of work delivered and accepted against the estimates of work completed for the time cycle)

Conducting retrospectives

Reprioritizing (backlog)

Determining the rate at which the deliverables are produced, validated and accepted (velocity) in the given time per iteration (agreed-upon work cycle duration, typically 2-4 weeks)

Determining that the schedule changed

Managing actual changes as they occur

70
Q

Inputs: Control Schedule

A

Project Management Plan

Project Documents

Work Performance Data

OPAS

71
Q

Tools/Techniques: Control Schedule

A

Data Analysis

Critical Path Method

Project Management System

Resource Optimization

Leads & Lags

Schedule Compression

72
Q

What is Earned Value Analysis?

A

Schedule performance measurements such as schedule variance (SV) and schedule performance index (SPI) are used to assess the magnitude of variation to the original schedule baseline

73
Q

What is Earned Value?

A

the measure of work performed expressed in terms of the budget authorized for that work

74
Q

What is an Iteration Burndown Chart?

A

graphical representation and projection of remaining unfinished work in that Iteration.

75
Q

Outputs: Control Schedule

A

Work Performance Information

Schedule Forecasts

Change Requests

Project Management Plan UPDATES

Project Document UPDATES