1
Q

How do you calculate the Total Variable Overhead Variance?

A

(SH x SR) - (AH x AR)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

How do you calculate the Overhead Efficiency Variance?

A

SR (SH - AH)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How do you calculate the Overhead spending/expenditure Variance?

A

AH (SR - AR)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What happens if the variable overhead is applied on the basis of direct labour hours?

A

The labour efficiency and variable overhead efficiency variances will move in tandem

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is sales price variance?

A

Shows the effect on profit/contribution if it is sold at a different price than expected.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How do you calculate sales price variance?

A

AQ (AP - SP)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the sales volume variance?

A

The difference between the actual quantity and the budgeted quantity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How do you calculate the sales volume variance?

A

SMC (AQ - BQ)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

How do you calculate the standard marginal contribution?

A

Standard selling price - variable costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are the first four rows in an operating statement?

A
  1. Budgeted contribution
  2. Sales volume variance
  3. Standard contribution on actual sales (1+2)
  4. Selling price variance
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are standard costs?

A

Predetermined amounts - the expected cost for one unit

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are practical standards?

A

Standards set at levels that are currently attainable with reasonable and efficient effort

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are ideal standards?

A

Standards based on perfection, which are unattainable and discourage most employees

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

How do you calculate the total material variance?

A

(SQ x SP) - (AQ x AP)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

How do you calculate the materials quantity/usage variance?

A

SP (SQ - AQ)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

How do you calculate the material price variance?

A

AQ (SP - AP)

17
Q

How are the variances computed if the amount purchased differs from the amount used?

A

The PRICE is on quantity purchased
The QUANTITY is on quantity used

18
Q

How do you calculate total labour variance?

A

(SH x SR) - (AH x AR)

19
Q

How do you calculate labour efficiency variance?

A

SR (SH-AH)

20
Q

How do you calculate labour rate efficiency?

A

AH (SR-AR)