spp 207 Flashcards

1
Q

what is the complete title of spp 207

A

Design Build Services

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

with his education, training and expertise qualifies him to take a direct role in the project, from conceptualization to implementation.

A

an Architect

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

simplifies and expedites the process of project delivery while providing creative cost-effective solutions.

A

Design Build Services

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

The Architect renders professional services in the implementation of his design. In _______, he assumes the professional responsibility and civil liability for both the design and the construction of the project.

A

Design-Build Services

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

2 scope of design build services

A

-Design-Build Services by Administration
-Design-Build Services with Guaranteed Maximum Project Construction Cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

The scope of Design-Build Services by Administration is similar to that of the Architect’s Regular Design Services (reference SPP Document 202)

clue: PSDCC

A

Project Definition Phase
Schematic Design Phase
Design Development Phase
Contract Document Phase
Construction Phase

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

When the various phases of design services are completed, the Construction Phase goes beyond periodic inspection and assessment to include the following

A

a. Preparation of schedule of work, program and estimates of materials, labor, transportation, equipment and services as
reference for the construction.

b. Organization and hiring of construction personnel, designation of duties and
remunerations

c. Negotiation and entering into contract with piecework contractors and evaluation of work accomplishments

d. Procurement of materials, plants and equipment, licenses and permits

e. Authorizing and undertaking payments of accounts

f. Keeping records and books of accounts

g. Negotiation with Government and private agencies having jurisdiction over the project, and

h. Management of all other business transactions related to the project construction / implementation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

This method is essentially the same as Design-Build Services by Administration except that the Architect provides the Owner/ Client a guaranteed maximum project construction
cost for the construction of the project.

A

Design-Build Services with Guaranteed Maximum Project Construction Cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

true or false

The Architect gives the Owner/ Client an estimate of the project. If upon completion there is realized savings from the estimated project construction cost; the savings is divided
equally between the Owner/ Client and the Architect.

A

true

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

The project construction cost is guaranteed by the Architect not to exceed _____ of the estimated project construction cost.

A

10%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

true or false

Should the actual cost exceed the estimated project construction cost plus Ten Percent (10%), the Architect shall be liable for the excess amount but only up to the amount of his administration Fee.

A

true

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

true or false

Should there be additional expenditures beyond the guaranteed maximum project construction cost which are due to legitimate change / variation orders (CVOs), extra work orders (EWOs), substantial escalation of prices of the costs of materials or labor as evidenced by data certified by a nationally recognized agency such as the National Economic Development Authority (NEDA), or to other causes not attributable to the fault of the Architect, the additional costs shall be borne by the project manager.

A

false

Should there be additional expenditures beyond the guaranteed maximum project construction cost which are due to legitimate change / variation orders (CVOs), extra work orders (EWOs), substantial escalation of prices of the costs of materials or labor as evidenced by data certified by a nationally recognized agency such as the National Economic Development Authority (NEDA), or to other causes not attributable to the fault of the Architect, the additional costs shall be borne by the OWNER/CLIENT.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

In methods of compensation

The manner of payment to the Architect follows the progress of construction. The Client directly pays all costs for labor and materials. The Architect does not advance any money for payment of expenditures connected with the work. Generally, ____________is given to the Architect beforehand and is accounted for and subject to periodic auditing by the Client

A

revolving fund

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

true or false

in methods of compensation the architect shall pay for the cost of all permits, licenses and other incidentals to the work.

A

false

in methods of compensation the OWNER/CLIENT shall pay for the cost of all permits, licenses and other incidentals to the work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

True or false

The project manager may appoint, subject to the Owner / Client’s approval, a construction superintendent, purchasing agent, timekeeper and property clerk aside from the usual labor personnel required. Salaries of such persons are paid by the Owner/ Client and not deductible from the Architect’s Fee under this SPP.

A

false

The ARCHITECT may appoint, subject to the Owner / Client’s approval, a construction superintendent, purchasing agent, timekeeper and property clerk aside from the usual labor
personnel required. Salaries of such persons are paid by the Owner/ Client and not deductible from the Architect’s Fee under this SPP.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

what is the percentage of administration in design build services

A

7%

17
Q

percentage of guaranteed maximum project construction cost

A

10%