SPP 202 Flashcards

1
Q

Simple
● Buildings of the simplest utilization and character and are without
complication of plan, design or detail.
● These buildings require only a minimum of architectural finishes,
engineering, and allied architectural elements.

A

Group 1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Armories

A

Group 1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Bakeries

A

Group 1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Habitable agricultural buildings

A

Group 1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Hangars

A

Group 1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Industrial buildings

A

Group 1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Parking structures

A

Group 1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Public markets

A

Group 1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Warehouses

A

Group 1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Project Construction Cost in PHP (50M and less) Recommended Professional Fee

RPF for Group 1 (DAEDS)

A

5%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Project Construction Cost in PHP (50M and less) Recommended Professional Fee

RPF for Group 1 (DADS)

A

3%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Moderate Complexity
● Buildings of moderate complexity of plan and design, requiring a
moderate amount of research and of engineering and allied
architectural design

A

Group 2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Banks, exchange and other
buildings

A

Group 2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Art galleries

A

Group 2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Call centers

A

Group 2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Churches and religious facilities

A

Group 2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

City hall, town hall, civic centers

A

Group 2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Office buildings

A

Group 2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Park, playgrounds., open-air
recreational facilities

A

Group 2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Convents, monasteries,
seminaries

A

Group 2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Project Construction Cost in PHP (50M and less) Recommended Professional Fee

RPF for Group 2 (DAEDS)

A

6%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Project Construction Cost in PHP (50M and less) Recommended Professional Fee

RPF for Group 2 (DADS)

A

3.6%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Exceptional Complexity
● Buildings of exceptional character and complexity of plan or design,
requiring large amounts of research and of engineering and allies
architectural design.

A

Group 3

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

Airports, wet/dry ports

A

Group 3

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

Auditoriums

A

Group 3

26
Q

Mental institutions

A

Group 3

27
Q

Hotels

A

Group 3

28
Q

Theaters

A

Group 3

29
Q

Veterinary hospitals

A

Group 3

30
Q

Laboratories

A

Group 3

31
Q

Mortuaries

A

Group 3

32
Q

Project Construction Cost in PHP (50M and less) Recommended Professional Fee

RPF for Group 3 (DAEDS)

A

7%

33
Q

Project Construction Cost in PHP (50M and less) Recommended Professional Fee

RPF for Group 3 (DADS)

A

4.2%

34
Q

Residences

A

Group 4

35
Q

Small apartment houses

A

Group 4

36
Q

Townhouses

A

Group 4

37
Q

DAEDS

RPF for Group 4

A

10% of PCC

38
Q

DADS

RPF for Group 4

A

6% of PCC

39
Q

Monumental
● Monumental buildings and other facilities requiring consummate
design skill and much precise detailing

A

Group 5

40
Q

Mausoleums, memorials, and monuments

A

Group 5

41
Q

Museums

A

Group 5

42
Q

Specialized decorative buildings

A

Group 5

43
Q

DAEDS

RPF for Group 5

A

12% of PCC

44
Q

DADS

RPF for Group 5

A

7.5% of PCC

45
Q

Repetitive Construction
● The design is reused for the repetitive construction of similar
buildings without amending the drawing and the specifications

A

Group 6

46
Q

RPF for Group 6 Recommended:
First building

A

100% of RPF for type of building

47
Q

RPF for Group 6 Recommended:
Second building

A

50% of RPF for type of building

48
Q

RPF for Group 6 Recommended:
Third building

A

40% of RPF for type of building

49
Q

RPF for Group 6 Recommended:
Fourth and succeeding buildings

A

30% of RPF for type of building

50
Q

Housing Projects
● Involves the construction of several residential units on a single site
with the use of one set of plans

A

Group 7

51
Q

Extensive Detail

A

Group 8

52
Q

Special fittings

A

Group 8

53
Q

Architectural interiors

A

Group 8

54
Q

Development planning and/or design

A

Group 8

55
Q

RPF: (Group 8)

A

15% of PCC

56
Q

Alterations/Additions
● Alterations, renovations, rehabilitations, retrofit and
expansion/additions to existing buildings belonging to Groups 1-5

A

Group 9

57
Q

RPF: (Group 9)

A

150% of RPF (increased the professional fee by 50%)

58
Q

Rendering Advice

A

Group 10

59
Q

RPF: (Group 10)

A

RPF shall be at least PHP 1,000 per hour

60
Q

The Architect is entitled to____of his fee once the
Contract Documents Phase are completed.

A

90%