Specifications, Bids and Contracts Flashcards
Acceleration Cost
Cost incurred by a contractor when the project is interfered with by the owner in such a way that the contractor must employ more manpower or work more hours. If the contractor contributes to the cause of its own delays, acceleration cost may not be granted.
Bid
An offer to perform a contract for work and labor or for supplying materials at a specified price. In the construction industry, a bid is considered an offer by the contractor to the owner. A bid, as an offer, becomes a contract once the owner accepts the bidder’s offer with all other contractual requirements in order
Bid (Solicitation of)
The 3 primary documents used in the solicitation of bids by an owner are 1. Instructions to Bidders, 2. Invitation to Bid, 3. Bid Form
Bid, Public Works Project (Advertisements for)
This process is governed by law and must be followed a specific way (depending on municipality rules). Generally it follows the following procedure: 1. Notice must be given to interested and qualified members of the construction community in advance of the bidding. This notice must be placed in a publicly accessible place (newspaper, magazine, government website, trade publication, etc.) This is typically called the “Notice to Bidders” and contains the following: Type of project, Location, Type of Contract, Bonding requirements, Dates to perform work, Terms of payment, Estimated construction cost (some may exclude this), time/manner/place to submit bids, location to obtain bid documents, deposit required on bid docs, Owner’s right to reject any and all bids, req’s regarding wage rates. 2. The Invitation for bids must be posted in public places and distributed to the local construction community. 3. All bidders must be treated alike and be afforded an opportunity to bid under the same terms and conditions. 4. Prequalification may be required.
Bid, Prequalification
Prequalifying contractors allows for a select list of bidders (or short list) be available for various projects. It averts construction problems by limiting bidding to contractors who have the experience and financial stability to complete the project. It is more desirable to eliminate a contractor before bidding rather than show that a contractor is not qualified after that firm has submitted the low bid.
Bid, Regular
While not always the same, typically anything that would lead to bid rejection constitutes a “regular bid”. So bids without a bid security, bids that fail to acknowledge addendum, late bids, not dated or missing minor info, etc.
Bidding, Accuracy of
The owner is typically responsible for any errors in the bid documents, however, statements are often included which place direct responsibility for the info on the contractor.
Bidding, The Award of
While contract award is given to the lowest bidder, there are stipulations that make this not all about the final $ amount. A phrase like “lowest responsible bidder submitting a regular bid” might be used.
Bidding, The Award Phase
Proceeds in this manor generally: 1. Bids are opened; 2. Owner evaluates the bids; 3. Notice of Award is issued; 4. Contractor acquires the required bonds and insurance; 5. Owner conducts pre-construction conference; 6. Owner awards the construction contract; 7. Notice to proceed is issued/Contractor signs the contract; 8. First day of construction is counted… and construction begins
Bidding (The Bid Form)
The form to be used by all bidders to submit their bids. It typically includes: Price (lump sum or unit price), Time of completion (if not given by owner), Bid Surety, Agreement to provide contract surety, acknowledgment of having reviewed addenda (list # of addenda reviewed), list of subs used in the bid, experience record/financial statement, plant & equipment inventory, Declaration regarding fraud and collusion, statement regarding site examination, signature.
Bidding (Notice to Proceed)
Issued by the owner and stating the contract start date. Note that the contract may not be signed by the contractor when the notice to proceed is issued, or to have the contract “clock” started without the contract docs having been fully executed. Generally the notice to proceed obligates the owner to the contract, so signed or not it is official once notice is provided to the contractor.
Bidding (Lump Sum)
Lump sum contracts set a fixed fee for a scope of work.
Bidding (Unit Price)
Because the bidding information outlines the type of work required, but not the amount, a unit price contract would be an ideal way to address an uncertain scope of work. Unit price contracts price a unit of work, and the total project cost is determined by the number of units required in a project. For example, excavation could be priced at $10/cubic yard and a total fee would be based on the number of units of excavation required (ex. 5,000 cubic yards). Unit prices can incorporate any and all anticipated costs associated with the installation of the unit, including labor, overhead, profit and materials, and would thus be an ideal way of ensuring that the contractor could profit from a defined type of work with an uncertain scope.
Bidding, Process of
After the design phase: 1. Advertisement for bidders; 2. Contractors acquire bid docs; 3. Contractor conducts quantity takeoff; 4. Addenda issued; 5. Contractor determines prices for all quantities (gets additional info from subs); 6. Contractor finalizes bid; 7. Contractor submits bid; 8. Bids are opened
Bidders, Instructions to
The purpose of this form is to outline the requirements necessary to prepare and submit a bid properly, and, as such, provide detail guidance to bidders, including the process for the award of contract and the rejection of bids. The rules by which the project will be bid include: 1. Instructions relative to the procedure for writing and submitting the bid (forms, items to be priced, alternatives only allowed where called for, etc.); 2. Contractor may be required to submit an experience record (used for post qualification); 3. Listing of all documents that are in the bid docs (dwg’s, specs, alternates, instructions, etc.); 4. The construction time period; 5. Indication of who is responsible for subsoil data, test borings, errors in the plans, etc. and if a site visit is required; 6. The req’s of the bid guarantee; 7. The insurance to be provided; 8. Bonding req’s; 9. Conditions for handling bid irregularities; 10. Where and when to deliver the bids; 11. Closed or public opening of the bids stated; 12. Prebid conference may be described.
Bidders, Responsible
This issue involves post qualification and allows the owner to look at more than just the $ amount submitted. It allows them to review the contractors work history, if they are over extended on other projects, underfinanced, or simply inexperienced. The endorsement of a contractor by a surety is often deemed sufficient to satisfy this criteria.
Bidders, Responsive
One who has submitted a bid under a competitive sealed bid which conformed in all respects to the invitation for bids so that all bidders may stand on equal footing. One is responsive if one replies to the specific questions set forth.
Bid (Design-Bid-Build Process)
Design completed before Bid, Bid completed before build. Advantages of this process include: 1. Owner benefits from competitive marketplace; 2. owner has the appearance of being impartial; 3. process fully embraces free market system; 4. may be the only viable method available for some gov. agencies. Disadvantages include: 1. Accurate costs cannot be known until the design is completed; 2. bids that exceed the owner’s budget cannot be constructed without jeopardizing the project; 3. various parties tend to be adversarial under this process; 4. Errors or Omissions in the design may lead to costly change orders.
Bid Depository
A local for subcontractors to submit their bids for a particular project.
Bid Rejection
The act of not allowing a bid to be included because of an impropriety in the process of submission or as a result of the owner’s arbitrary decision to reject the bid (which they reserve the right to do in a typical contract). However, in rejecting a bid, they run the risk of interfering with the bidder’s right to do work or of defamation of character.
Bid Rigging
Scheme in which businesses collude so that a competing business can secure a contact for good or services at a pre-determined price.
Bid - Additive and Deductive Alternates
These are ways to increase or decrease a Base Bid. Typically Additive Alternates favor the Owner (i.e. if the contractor forgets to include any work or costs, they are out the money and the owner gets a freebe), while Deductive Alternates favor the Contractor (i.e. again if the contractor forgets to include any work, then when the work is deducted from scope they don’t have to credit the owner making them not lose as much money). It is always better to do Additive Alternates, but limit the amount of them used (if any) in a bid to keep it from getting to complicated.
Change Order
Document issued directing the contractor to erect some portion of the project in a manner different than described in the original plans and spec’s. This change MUST have an effect on the price and/or time of the contract, otherwise is considered a field order or minor change.
Competitive Bidding
A process whereby sealed proposal are submitted to the owner for consideration. This is mandatory on public works projects. A private owner may use competitive bidding but is not legally bound by the process.