STEP ONE
Finalize PR Pkg. –> Market Research, Funding Document, and Final J&A.
STEP TWO
Do Acq. Planning –? Acq. Plan & ASP Required if over $50M on all years OR over $25M on any one FY.
STEP THREE
SB Coordination, Synopsize, Check SAM, Solicit (15 days + 30 days)
STEP FOUR
Receive/Review Proposal (Check SAM upon receipt of proposal)
STEP FIVE
Send to Pricing –> AFSC - >$10M
AFLCMC - >$25M
STEP SIX
Develop Negotiation Objective
STEP SEVEN
BUSINESS CLEARANCE
STEP EIGHT
Conduct and Conclude NEGOTIATIONS. Request Certificate of Certified Cost and Pricing Data if over $2M and Non-Commercial.
STEP NINE
Finalize Contract File (PNM, Contract, Draft CAR)
STEP TEN
Do Contract Clearance (unless waiver was submitted and approved in Step 7)
STEP ELEVEN
Submit 1279 (If greater than $7.5M then wait 3 days.
STEP TWELVE
Check SAM, Award, Finalize CAR.
STEP THIRTEEN
Post the Post-Award Synopsis, Redacted J&A to SAM.