SoE - Contract administration Flashcards
Can you expand on your knowledge of the JCT/SBCC Standard Building Contract
The JCT/SBCC SBC allows for additional to the intermediate contract such as:
Employers’ representative, listed sub-contractors, retention bonds, variation and acceleration quotations, third party rights.
What SBCC contracts allow for a clerk of works?
Standard Building Contract (& JCT Intermediate)
What contract allow for sectional completion and named sub-contractors ?
Standard Building Contract (& JCT Intermediate)
What are the main types of tendering?
- Open
- Selective
- Negotiated
- Serial
- Framework
What are the main updates from the previous version (JCT/SBCC MW updates)?
JCT/SBCC MW 2016 updates include :
* Amendments to reflect CDM 2015
* Increased flexibility regarding insurance and ‘insured by other means’
* Simplified payment provision including the interim payment provision under the Housing Grant, Construction and Regeneration Act 1996
What are the main updates from the previous version (JCT/SBCC MW updates)?
JCT/SBCC MW 2016 updates include:
* Amendments to reflect CDM 2015
* Increased flexibility regarding insurance and ‘insured by other means’
* Simplified payment provision including the interim payment provision under the Housing Grant, Construction and Regeneration Act 1996
What is a traditional lump sum contract?
A lump sum contract is the traditional means of procuring construction, and involves a single ‘lump sum’ price for all the works being agreed before the works begin. This means that the contractor is able to accurately price the works they are being asked to carry out.
What is the role of the contract administrator?
To administer the conditions/works under the terms of the contract. Acting impartially.
What is a contract instruction and how would you deal with it?
In simple terms, a contract variation occurs when the parties agree to do something differently from the way they originally agreed, whilst the remainder of the contract otherwise operates unchanged. Such an agreement, if valid, would amount to a variation of the existing contract.
What is traditional procurement?
Traditional procurement remains the most commonly-used method of procuring building works. It comprises a tripartite arrangement involving a client, consultants and contractor.
The traditional procurement route involves separating design from construction. The client first appoints consultants to design the project in detail and to ensure cost control and inspect the construction works as they proceed. Contractors are then invited to submit tenders for the construction of the project on a single-stage competitive basis.
Included in the contractor’s responsibilities are workmanship, materials and work undertaken by suppliers and subcontractors. The contractor is not responsible for the design (other than temporary works), although some traditional contracts may provide for the contractor to design specific parts of the works (see key criteria below).
Traditional procurement is typically undertaken under a lump sum contract. A single ‘lump sum’ price for all the works is agreed before the works begin, then stage payments are made as the works proceed. This is appropriate where the project is well defined when tenders are sought, and significant changes to requirements are unlikely. This allows the contractor to accurately price the works they are being asked to carry out.
What are the others available JCT Contracts?
- Standard Building Contract;
- Design & Build;
- Intermediate Contract;
- Intermediate Contract with Design;
- Minor Works;
- Minor Works with Design;
- Major Projects (MP)
- Framework, non-binding and binding;
What are the others available SBCC Contracts?
- Standard Building Contract (with, without and approximate quantities);
- Minor Works;
- Minor Works with CD;
- Major Projects (D&B);
- Measured term;
- Homeowner contract
What is a letter of intent?
A letter of intent is a document outlining the understanding between two or more parties which they intend to formalize in a legally binding agreement. The concept is similar to a head of agreement, term sheet or memorandum of understanding
What does the Housing, Grants Construction and Regeneration Act 1996 allow for within the contract?
- the right to stage payments
- the right to notice of the amount to be paid
- the right to suspend work for non-payment
- the right to take any dispute arising out of the contract to adjudication
What are the types of specifications?
Specifications describe the products, materials, and work required by a construction contract. They do not include cost, quantity, or drawn information, and so need to be read alongside other information such as quantities, schedules, and drawings.
Specifications vary considerably depending on the stage to which the design has been developed, ranging from performance specifications (open specifications) that require further design work to be carried out, to prescriptive specifications (closed specifications) where the design is already complete.
- Prescriptive specifications give the client much more certainty about the end product when making investment decisions (such as when they appoint the contractor), and place a greater burden on the designer to ensure proper installation rather than the contractor.
- Typically, performance specifications are written on projects that are straight-forward, standard building types, whereas prescriptive specifications are written for more complex buildings, or buildings where the client has requirements that might not be familiar to contractors and where certainty regarding the exact nature of the completed development is more important to the client.”
What are the types of procurement?
- Traditional contract 86%
- Single-stage design and build 41%
- Two-stage design and build 39%
- Management contract 18%
- PFI 10%
Under JCT MW does the programme form part of the contract?
No however the contract promotes the use of one for reference generally.
Under JCT what are included within the contract documents?
- drawings;
- specification;
- work schedules;
What is the base date?
Base date: the base date is usually set at around the time of return of tenders. base date’ is a reference date from which changes in conditions can be assessed.
Does JCT MW make reference to a possession date?
MW16 does not refer to the contractor being given ‘possession’ of the site, but states simply that ‘The Works may be commenced’ on the date stated in the contract
What are the ground for termination from the client/corruption?
- Insolvency
- CDM breaches
- Corruption of the contractor
- Contractor failing to proceed regally and diligently
- Employer failing to pay amounts
- Either party can terminate is the works are suspended for a period of more than one month due to neutral events
Why is it important to define a completion date?
The significance of having a completion date is that it provides a fixed point from which damages may be payable in the event of non-completion. Generally in construction contracts the damages are ‘liquidated’, and usually expressed as a rate per week of overrun.
What is the reason for an extension of time?
One important reason for an extension of time clause is to preserve the employer’s right to liquidated damages in the event that the contractor fails to complete on time due wholly or in part to some action for which the employer is responsible
What is ‘time at large’?
Construction contracts will usually include a date by which the works described in the contract should be completed. This is generally the date by which practical completion must be certified.
The phrase ‘time at large’ describes the situation where there is no date for completion, or where the date for completion has become invalid. The contractor is then no longer bound by the obligation to complete the works by a certain date.
Time can become at large because there is no clear completion date specified in the contract, or can be a situation that arises as a result of events (typically by agreement of the parties or by failure of the contract ‘machinery’), or if the contract does not allow the construction period to be extended.