A site whose future is affected by possible contamination is called a
Brownfield
SLL Credit 1 - Preferred Locations - encourages teams to develop within existing cities, suburbs, and towns to reduce adverse environmental and public health effects associated with sprawl. Which project location type will achieve the most points for this credit?
Locating on an infill site that is also previously developed - 5 points
Locating in an area with existing connectivity within 1/2 mike of project boundary of 400 or more intersections per square mile - 5 points
10 points total
2 species inside project boundary are threatened under the ESA. How do you comply with SLL prerequisite 2 - Imperiled Species and Ecological Communities Conservation?
Comply with an approved habitat conservation plan or equivalent, if the species is threatened, endangered, or GH, G1 or G2 by NatureServe
A project has 1,200,000 sf of total nonresidential floor area and 350,000 sf of buildable land. What is the total nonresidential density, expressed as FAR?
Total nonresidential density = total nonresidential floor area sf / total nonresidential buildable land sf. 1,200,000/350,000 = 3.42 nonresidential buildable land.
The project site contains 10,000 sf of a previously developed area with slopes above 40%, 20,000 sf of previously developed area with slopes between 26% and 40%, and 50,000 sf of previously developed area with slopes between 15% and 25%. How much combined sloped area must be restored with native or adapted planting’s to meet SLL Credit 6 - Steep Slope Protection?
Slopes over 40% must be 100% restored (10,000sf)
Between 26-40% must be 60% restored (12,000sf)
Between 15-25% must be 40% restored (20,000sf)
= 42,000sf restored with native and adaptive planting’s
Which locations would earn a project points for SLL Credit preferred locations?
Locate the project on an infill site that is not previously developed - this would earn points for option 1 of SLL Credit 1.
A project for a previously developed site has a slope over 40% that will require 100% restoration to earn SLL Credit steep slope protection. What else will the project team need to do to earn the credit?
Develop covenants, conditions, and restrictions (CC&R) to protect the slope in perpetuity. Development is not permitted on slopes greater than 40%
A planned multi unit residential project will have 50 planned occupants living in 30 residential dwelling units. How many residential long-term bicycle parking spaces are needed to earn SLL Credit bicycle facilities?
Take the greater of the following: 30% of regular building occupants or 1 storage space per residential unit.
50*30% = 15 spaces
1 space per unit = 30 spaces
A previously developed site has a slope over 15%. What must occur to protect the slope to earn SLL Credit steep slope protection?
Locate development such that the % of the development footprint that is on existing slopes less than 15% is greater than the % of buildable land that has existing slopes less than 15%
Impervious bike and per pathways
May be 12’ but only 8’ may be impervious
How many intersections per square mile will earn a project SLL credit preferred locations?
200 - earns 1 point
SLL Credit five housing and jobs proximity: how many existing dwelling units must be located within half mile walk distance for option three?
50 percent of new jobs created
What is the shortest time A management plan must be funded for SLL credit long-term conservation management of habitat for wetlands and water bodies?
10 years
What requirements must be met to achieve SLL credit brownfield redevelopment?
Documenting any part of a project site as contaminated or As a Brownfield
Remediating contamination
The vehicle miles traveled per capita must not exceed how much of the average of the metropolitan region to earn points under SLL credit access to quality transit?
90 percent must not be exceeded too earn 1 point
What’s the minimum number of long-term bicycle storage space is required for workers in a retail project that will have planned occupancy?
Five percent of regular building occupants. No fewer than two storage spaces per building.
What defines a floodplain for SLL pre-requisite floodplain avoidance?
Any areas noted on a legally adopted flood hazard map.
How do buildings meet the storage and shower requirements for SL credit bicycle facilities?
90 percent of all new multi unit residential buildings and all new non-residential buildings must individually Meet the storage and shower requirements.
How many acres must patches of predominately native vegetation Be To qualify a significant habitat?
150 acres
When can intersections within a site be counted for connectivity forSL credit preferred locations?
Only when the intersections we’re not constructed or funded by the developer within the past 10 Years
How close must diverse uses be to the project boundary to contribute towards a bicycle network?
3 miles biking distance
What type of plants can be used for restoration for SLL credit restoration of habitat or wetlands and water bodies?
Native plants only
What is not considered a minor improvement within the 100 foot buffer of a water body for SLL prerequisite wet land and water body conservation?
Adding a 500 ft.² off street parking area
A previously developed site has a slope over 15%. What must occur to protect the slope to earn SLL credit steep slope protection?
Locate development so that the percentage of the development footprint on existing slopes less than 15% is greater than the percentage of buildable land that has existing slopes less than 15%
How many secure a bicycle storage spaces Are needed to earn SLL credit bicycles network and storage?
The greater of the following: 30% of planned multiunit occupants or the number of multiunit residential dwelling units
Previously developed site has a slope of 20%. What must be done to earn SLL credit six steep slope protection?
Restore 40% of the slope area with native plants or non-native adapted plants. Restoration is required on previously developed slopes over 15%
Mitigation ratio
Area of easement per area of project on prime unique or significant farmland
Which of the following smart location and linkage credits have exemplary performance?
Access to quality transit
Restoration of habitat or wetlands and water bodies
Which will not meet requirements of ongoing management activities for SLL credit restoration of habitat or wetlands and water bodies?
Earn SLL credit site design for habitat or wet land and water body conservation - does not meet the requirements of ongoing maintenance. Can help flag areas of concern however
A project is located near an existing bike network. How close must diverse uses be to the project foundry to contribute towards a bicycle network
Within 3 miles biking distance from the project boundary