What will if implemented not help meet the credit requirements for GIB credit rain water management?
Stormwater pond (conventional stormwater controls do not qualify)
Which would not be included in the calculations for recycled content for GIB credit recycled content in infrastructure?
Play ground covered in recycled tire chips
Concrete building foundation
(Not infrastructure items)
GIB pre-requisite and credit indoor water use reduction Percentage goals
Prerequisite - 20% savings
Credit - 40% savings
Exemplary - 55%
What average percentage improvement over ASHRAE 90.1-2010 with the major renovation of a non-residential building need to achieve for GIB pre-requisite minimum building energy efficiency?
Major renovations must demonstrate an average of 3% improvement over ASHRAE 90.1-2010
A project will have 2 existing mixed-use buildings that will be renovated. The project team is considering a district heating and cooling system. What is true about the project’s ability to earn GIB credit district heating and cooling?
The project can earn the credit if at least 80% of the annual heating and/or cooling consumption is provided by the district plant.
- 2 bldgs must be services
- single family residential and existing bldgs of any type can be excluded, but they can be one of the 2 required bldg types
How many gallons of waste water must be treated and used to replace potable water for the project to earn credit GIB wastewater management?
Reuse and replace 25% of potable water exclusive of existing buildings
Which is a stabilization control for construction activity pollution prevention?
Temporary seeding
Permanent seeding
Mulching
What type of renewable energy sources is not acceptable towards earning GIB credit on site renewable energy sources?
Geothermal energy systems that use vapor compression systems for heat transfer
A project has residential density of 10 dwelling units per acre. The nonresidential density is .5 FAR. What minimum percentage of the undeveloped area must remain undisturbed to earn GIB credit minimize site disturbance?
20%. 10÷.5
A project will have 10 habitable buildings. Eight of the buildings will be new and 2 will be retrofitted.
How many of the buildings and what type must be leed certified to earn the maximum number of points available under GIB credit certified green buildings?
Six buildings any combination of newer retrofitted under option one. Pre-requisite requires one certified building. Five more buildings earns five more points
Which roof would not help earn GIB credit heat island reduction option 2 high reflectance and vegetated Roofs?
Low <= 2:12
Roof slope covered with material with a three year aged SRI 55.
Low sloped roofs must have an SRI of 82 or higher to qualify
What amount of recycled content would a project team need to use to earn GIB credit recycled content in infrastructure?
50% of the total mass of all infrastructure materials
What amount of recycled content would a project team need to use to earn GIB credit recycled content in infrastructure?
50% of the total mass of all infrastructure materials
Which Are not objectives of the best management practices to control erosion and sedimentation in runoff during construction?
Limit disturbance to a minimum of 40 feet beyond the building perimeter; 10 feet beyond surface walkways, patios, surface parking and utilities less than 12 feet in diameter.
This is an objective of GIB credit minimize site disturbance
A project will use an ashtray advanced energy design guide to document energy efficiency. What will determine what prescriptive Measures the project must follow?
The square footage of the building
The climate zone the project is located
The use of the building
A project team has determine the mass of infrastructure materials as:
20 tons postconsumer recycled content of new materials
20 tons pre-consumer recycled content of new materials
30 tons in place reclaimed materials
100 tons total materials
What is the percent of recycled content for the project?
60%
20 tons new post consumer +10 tons new pre-consumer (Half the preconsumer amount) + 30 tons in place equals 60 times total recycled content. 60 out of 100 equals 60%. At least 50% is needed to earn GIB credit 15
A redevelopment project will include the addition of a new neighborhood to an existing block of office buildings. What would a project need to do for GIB credit infrastructure energy efficiency?
Install all new infrastructure that will help achieve a 15% annual energy reduction below an estimated baseline energy use
Which of the following would not meet the requirements for GIB credit solid waste management?
Recycling station available to 50% of the project occupants. These need to be available to all occupants
What minimum average percent improvement over ASHRAE 90.1–2010 must buildings undergoing major renovations achieve to earn credit GIB building energy efficiency?
10% is the minimum average needed for existing buildings
What systems are used for on site treatment and reuse of waste water?
Constructed wetlands
Anaerobic biological treatment facility
Mechanical recirculating sand filters
A project team has designed and constructed an anaerobic biological treatment facility to retain on site 80% of the average annual wastewater generated by the project. How many points with this design on the project?
3.
Two points for reusing 50% of waste water one more point for exemplary performance by reusing 75%
Parking lot is next to a low density residential area LZ2. The greater part of the parking lots edge is adjacent to the LZ3 area. What designation should the project team use for exterior lighting requirements?
Bug ratings for LZ2 - the more stringent zone requirements
Which is not an approved low impact development approach to earn GIB credit rain water management
Selling harvested rainwater to nearby businesses
Which project scenario would not meet the requirements for green infrastructure and buildings credit certified green buildings?
Two mixed use renovations certified to a local green building rating system based on peer reviews
A project would like to reduce the heat island for 50% of non-roof site hard scapes. What strategy would qualify for GIB credit heat island reduction?
Install an open grid pavement system that is 50% pervious.
A project has 10 new buildings. Eight of the new buildings have low sloped roofs and two of the buildings have steep slope roofs. What design strategy would qualify for GIB credit heat island reduction option 2 high reflectance and vegetated Roofs?
The weighted rooftop SRI Average must collectively cover 75% or more of the roof area. When more than one type of roof exists a weighted average is used
Which building it certified would qualify for GIB Prerequisite certified green building?
A building designed and constructed as part of the project - The whole building
A project will have eight habitable buildings. Five of the buildings will be new and three will be retrofitted. how many of the buildings must be LEED certified to GIB credit certified green buildings?
2 - prerequisite and credit each have 1
Best management practices to control erosion and sedimentation must be selected from
The most stringent of the EPA’s BMP For construction and post-construction site run off or locally approved equivalent
A project total building square footage is 500,000 ft.² what amount of square footage must be certified to own five points under GIB credit certified green buildings?
250,000 square-foot or more
50%
Why are project developers encouraged to pursue lead certification for GIB prerequisite certified green building?
Documentation is streamlined for leed buildings
A project contains 2 historic buildings. The project team would like to demolish one historic building and make an addition to the other historic building. What is true about the projects ability to earn GIB credit historic reuse prevention and adaptive use?
The project can earn the credit if a certificate of appropriateness is granted by the local historic preservation review board
To earn GIB credit outdoor water use reduction what must a project team do?
Avoid installing a well specifically to collect ground water for irrigation
Which credits cannot earn a project any additional points for GIB credit rain water management?
NPD credit reduced parking footprint