Settlement Flashcards

1
Q

What is a Part 36 Offer?

A
  • A Settlement Offer Without Prejudice save as to Costs; and
  • With certain automatic Cost consequences.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is a Calderbank Offer?

A
  • A Settlement Offer Without Prejudice save as to Costs; that
  • Lacks the procedural requirements and automatic Cost consequences of a Part 36 Offer.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the Procedural Requirements of a Part 36 Offer?

A

The Offer must:

  • Be Written.
  • Declare itself as a Part 36 Offer.
  • State whether it addresses any Counterclaims.
  • State whether it concerns all or part of the Claim.
  • State the period during which the Offer is may be Accepted (the “Relevant Period”).
    • This cannot be less than 21 Days.
    • Acceptance during the Relevant period has favourable Cost consequences for the Offeree.

Form N242A is the Precedent Document.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the Further Procedural Requirement of a Part 36 Offer made by a Defendant?

A

The Defendant can only offer to pay a lump sum within 14 days.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How can the Offeree of a Part 36 Offer be clarified?

A

By request within 7 Days of Service.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

When can a Part 36 Offer be Withdrawn or Changed to be Less Advantageous to the Offeree?

A

Before Acceptance or Trial Commencement:

  • Upon Expiry of the Relevant Period, whether:
    • Automatically, as per its Terms; or
    • Subject to Notice of Withdrawal or Change.

After Acceptance:

  • With the Court’s permission, requested within:
    • 7 Days from the Notice of Acceptance; or
    • If earlier, First Day of Trial.

Before Trial Commencement:

  • With the Court’s permission, requested as soon as practicable.

Beware: A Part 36 Offer remains Open even after the Relevant Period expires unless its Terms state otherwise.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

When will the Court grant Permission to Withdraw or Change an Offer?

A

It is in the interests of justice considering present circumstances.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the Effect of Changing an Offer to be More Advantageous to the Offeree?

A
  • The Original Offer will continue to run.
  • The Improved Offer is treated as a new Part 36 Offer, whose Relevant Period runs from when the Notice of Change is deemed Served.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

How is a Part 36 Offer Accepted?

A

When a Notice of Acceptance is Served on the Offeror.

Notice must be Filed at the Court if the Case has been Issued.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are the General Consequences of Accepting a Part 36 Offer?

A

Staying:

  • The Claim is stayed and does not continue to Trial.

Settlement Sum:

  • The Defendant must pay the Settlement Sum within 14 Days of the Notice of Acceptance being Served, unless otherwise agreed in writing.
  • Failing which, the Claimant can enter Judgment against the Defendant.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

How do the Cost Consequences of Accepting a Part 36 Offer differ based on When it was Accepted?

A

Acceptance Within the Relevant Period:

  • The Claimant is entitled to Litigation Costs up to when the Notice of Acceptance was Served.

Acceptance Outside the Relevant Period:

  • Unless the Parties can agree Liability for Costs, the Court will determine the issue.
  • Unless it considers it unjust, the Court must Order that:
    • The Claimant be awarded Costs up to the Relevant Period’s expiry; and
    • The Offeree to pay the Offeror’s Costs from the Relevant Period’s expiry to the Date of Acceptance.

Making and Acceptance within 21 Days of Trial:

  • Unless the Parties can agree Liability for Costs, the Court will determine the issue.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

In considering what Order to make regarding a Part 36 Offer Accepted Outside the Relevant Period, what will the Court consider?

A
  • The Offer’s Terms.
  • The Procedural Stage at which the Offer was made.
  • The Offer’s authenticity as a Settlement attempt.
  • The information available to the Parties at the time.
  • The Parties’ conduct regarding the Disclosure of information relevant to the Offer.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are the Cost Consequences of Accepting a Part 36 Claim that only concerns Part of the Claim?

A
  • If the Claimant abandons the Claim at Acceptance, it is only entitled to Costs for the Settled Part.
  • If it does not, and the Parties cannot agree Liability for Costs, the Court will determine the issue.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What determines whether a Defendant’s Non-Acceptance of a Claimant’s Part 36 Offer has Cost Consequences?

A

The Claimant obtains a Judgment that is at least as financially advantageous as the Offer.

This is called the “Defendant Cost Trigger”.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

If Triggered, what are the Cost Consequences for a Defendant’s Non-Acceptance of a Claimant’s Part 36 Offer?

A

The Defendant must pay:

  • Litigation Costs from the Relevant Period’s expiry, or some point thereafter, on an Indemnity Basis.
  • Interest on Litigation Costs at a rate not over 10% above the Base Rate.
  • Interest on the Award at a rate not over 10% above the Base Rate from the Relevant Period’s expiry.
  • A Lump Sum not exceeding £75,000 based on the Award.
    • Sums of 10% are payable on Awards up to £500,000.
    • Sums of 5% are payable on Awards over £500,000.

All of this is unless the Court considers it unjust.

If the Claim is not for a monetary sum, then the Lump Sum is calculated using the Claimant’s Cost Award.

If the Offer is made within 21 Days of Trial, these consequences will not transpire, unless the Court abridges the Relevant Period.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

If Triggered, what are the Cost Consequences for a Defendant’s Non-Acceptance of a Claimant’s Part 36 Offer if Recoverable Costs are Fixed?

A

Instead of recovering on Indemnity, the Claimant is entitled to 35% of the difference between the Fixed Costs for:

  • The Procedural Stage at the Relevant Period expiry; and
  • The Procedural Stage at the Date of Judgement.

The rest is the same.

The Stages set out in PD45, Table 12 (Fast Track) and Table 14 (Intermediate Cases).

17
Q

What determines whether a Claimant’s Non-Acceptance of a Defendant’s Part 36 Offer has Cost Consequences?

A

The Claimant fails to obtain a Judgement that is more financially advantageous than the Offer.

This is called the “Claimant Cost Trigger”.

18
Q

If Triggered, what are the Cost Consequences for a Claimant’s Non-Acceptance of a Defendant’s Part 36 Offer?

A
  • The Claimant must pay the Defendant’s Costs from the Relevant Period’s expiry, plus interest; unless
  • The Court considers it unjust.
19
Q

What will the Court consider when determining whether it is Unjust to impose Cost Consequences following a Trigger?

A
  • The Offer’s Terms.
  • The Procedural Stage at which the Offer was made.
  • The Offer’s authenticity as a Settlement attempt.
  • The information available to the Parties at the time.
  • The Parties’ conduct regarding the Disclosure of information relevant to the Offer.

The Court’s discretion under this provision is much more limited than its general discretion under normal cost rules.

20
Q

When will Part 36 Consequences be avoided?

A
  • The Offer was Withdrawn.
  • The Offer was made within 21 Days of Trial, and the Court did not abridge the Relevant Period.
  • The Offer was Changed to be Less Advantageous to the Offeree, and the Offeree secured a More Advantageous Jugement than the Changed Offer.
21
Q

What must the Offeror do to ensure that Part 36 Consequences will apply?

A
  • Leave the Offer open.
  • Make the Offer as early as possible, and in any case, at least 22 Days before Trial.
22
Q

What are the Cost Consequences if both Parties make Part 36 Offers and neither Offer is Accepted?

A

Judgment Exceeds the Claimant’s Offer:

  • The Claimant’s Offer takes effect, and Consequences are imposed on the Defendant.

Judgment Does Not Exceed Either Offer:

  • Neither Offer takes effect, and Costs are awarded on standard principles.

Judgment Exceeds the Defendant’s Offer:

  • The Defendant’s Offer takes effect, and Consequences are imposed on the Claimant.
23
Q

What are the Potential Court Orders after Settlement?

A
  • Consent Order.
  • Tomlin Order.
24
Q

What is a Consent Order?

A
  • A Court Order that mirrors the Terms of the Parties’ Settlement Agreement.
  • This usually gives rise to the Defence of Estoppel against Fresh Proceedings.
25
Q

What are the Two Types of Consent Order?

A
  • Contractual: A mirror of the Parties’ Settlement Agreement.
  • Non-Contractual: A declaration of the Terms of Settlement themselves, variable by the Court.
26
Q
A
27
Q

What are is the Main Type of Order following Settlement?

A

Consent Order.

These Orders also apply to the Settlement of Interim Issues and Applications.

The Parties must Apply to Court, like any other Order. If one is made during a Stay, it is treated doubly as an Application to Lift Stay.

28
Q

What are the Two Types of Consent Order?

A

Contractual:

  • The Order is a mirror of the Parties’ Settlement Agreement and is largely unalterable by the Court.

Non-Contractual:

  • The Order contains the Term’s of the Parties’ Settlement and is alterable by the Court.
29
Q

What is a Tomlin Order?

A

A type of Contractual Consent Order, used when:

  • The Parties wish to keep certain Terms confidential.
  • The Settlement Terms go beyond what the Court can generally Order, enforceable by a Subsequent Order.

Such provisions are in the Order’s Schedule (i.e. Part 2).

30
Q

Which Provisions in a Tomlin Order must be Public?

A

Directions for:

  • Payment of money out of Court; or
  • Payment of Costs and associated Assessments.