Section 3 Flashcards

1
Q

When concrete contains aggregate larger than allowed for the slump test, the larger aggregate must be______

A

wet screened over 1.5” sieve

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

the mold for making a slump test is in the shape of _____

A

the frustum of a cone

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

the height of the slump mold is

A

12 in

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

true or false: the interior surface of the slump mold is allowed to have minor irregularities

A

false

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

for use in the slump test, the sampling end or both ends of the tamping rod must be

A

rounded to a hemispherical end

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

true or false: the slump mold should be in a dry condition before beginning test

A

false

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

the surface on which the slump mold will be placed must be

A

flat, level, damp, non absorbent, and rigid

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

the slump mold is filled in how many layers

A

3

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

each layer of the slump test should fill about ____ of the volume

A

1/3 of the volume

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

rod each layer _____ times uniformly over the cross section with the rounded end of the rod

A

25

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

How deep should the tamping rod penetrate into the layer below ?

A

through top most layer and 1 inch into previous layer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What must be done if the concrete drops below the top the slump mold while the top layer is being rodded?

A

add additional concrete to keep excess above the mold at all times

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

prior to lifting the mold, concrete must be removed from

A

the area surrounding the base of the mold

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

true or false: after the final rodding the sides of the slump mold should be tapped lightly with the tamping rod

A

false

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

true or false when raising the slump mold it should not be rotated or twisted

A

true

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

how much time is allowed to lift slump mold

A

5 s plus or minus 2

17
Q

The measurement for slump is made from the top of the mold to what point in the concrete specimen?

A

the displaced original center of the top surface of the specimen

18
Q

the slump of the concrete is measure and reported to the nearest

A

1/4 inch

19
Q

How much time is allowed to conduct the slump test from beginning to completion

A

2.5 min