Section 2 Flashcards
12 Stages of Agile Management
1
control tower and others
1
APF
Adaptive project framework (APM)
APF/APM
A group of iterative and incremental methods for completing projects
xPM
Extreme project (programming) management , used for very complex projects that do not have rigid ends or components, alot of shareholder interactions
Scrum
an agile PM framework dedicated to complex projects to help self managed teams work together
areas of scrum
1 what happened since the last one
2 what will happen between now and next one
3 what is preventing you from performing as effectively as possible
scrum master
not the leader, more of a coach that leads by example
scrum meetings
short daily meetings to quickly catch members up to speed on project status.
feature
a part of a product that delivers some useful function to a customer
scaling
adapting Agile PM to larger or small projects
sprint
small planned amount of work in timed iterations
when do clients get involved
1
what decisions do clients make
1
who owns projects?
1
proof of concept testing
does not deliver anything, is simply a test to determine of the project is feasible
lessons learned
analysis shortly after end of a project cycle to identify errors and their causes; areas of improvement
50/50 rule
activities are 0% until started and then 50% when started until completion
0/100 rule
use when activities are short, status is 0% until completed
percentage rule
an agreed upon percentage between PM and management given to individual tasks
PV
(BCWS) budgeted cost of work scheduled, amount planned to spend per period
(Budgeted Value)
EV
(BCWP) actual cost of work accomplished, hard to estimate because it is a percent of work completed
AC
(ACWP) costs charged to a project during a specific period
schedule variance (SV)
EV-PV
difference between earned value (EV) and planned value of where the project should be (PV)
cost variance
EV-AC
difference between earned value (EV) and actual cost for work completed (AC)
what does a positive variance indicate
desirable, more work has been completed than scheduled
what does a negative variance indicate
problems and changes have occurred, setting the project behind
SPI
Scheduling Performance Index
EV/PV
CPI
Cost Performance Index
EV/AC
percent of planned work completed for each dollar spent. less than 1.0 is bad
BAC
budgeted cost at completion
Budgeted Cost
ETC
(Estimated cost to/at completion)
EVM/EVA
a method of combining scope, schedule and resources measurements to determine performance and progress
Project Baseline
starting point for project to base progress and is derived from WBS performance and progress
Penalty Clauses
a clause raising the price of the contract for failure, increases security for issuer
Liquidated Damages
monetary penalties incurred for each period project is not completed
specified in contract
can be incremental or flat rate
Tracking Gantt
chart showing where you are and what progress was made on a particular day with a second bar against the original plan
Resource Loading Tables
charts that show what resources are needed vs. allocated
shows where and how long it will take to complete each task
elevate the constraint
1
subordinate constraint
1
relevant constraint
1
Shortening activity duration
1
Activity cost
1
duration
1
slope
1
student syndrome
1
common cause variation
1
special cause variation
1
dummy activity
1
AOA
Activity on Arrow
less popular form of developing project networks where the activity is on an arrow line
AON
Activity on Node
more popular form of developing project networks where the activity is drawn on a node or box
Slack
amount of time a task can be delayed without delaying the project
Gantt Chart
a bar chart showing activities and their start dates, end dates, and durations
Operating Risk
1
Promotional Risk
1
Financial Risk
1
Economic Risk
1
Organizational Risk
1
Market Risk
1
Political Risk
1
Execution Risk
1
Commercial Risk
1
Technical Risk
1
Past History
1
Brainstorming
1
Budget Reserves
1
Risk tranference
1
risk acceptance
1
risk sharing
1