Q

what is case-by-case screening?

A

Screen In- Screen Out

screens a project against a checklist of regulations or guidelines

time consuming, inconsistent, vague–> can be worded sneaky to ‘work around’ screening

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is List Based Screening?

A

-projects falling on the inclusion list require an EA
-type of screening use in IAA2019
-Exclusion lists exists ex: national emergencies

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is threshold based screening?

A

-categorizes projects
-sets thresholds but can have issues with projects just falling short and not needing one

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is Hybrid Screening?

A
  • the preferred/common method
    -threshold with case-to-case considerations
    -used by IAA2019
    ex: hydro development that uses over ___mWatts during production
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are Physical Activities Regulations? (aka Project List)

A

IAA2019: when the physical activity associated with the proponent’s project is described on The List, the proponent must provide the Agency with an Initial Project Description

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What was the criticism of the past Project List? How has it been rectified?

A

was decided by the Ministry for Environment which created a power imbalance

now is decided by the Government in Council, group of ministries that operates under collective decision making

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

T/F only environmental aspects are considered in an EA

A

false, the decision to do an EA is not entirely an environmental decision it is also a social and political one

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What environmental elements are valued the most under federal jurisdiction?

A
  1. fish & fish habitat
  2. aquatic species at risk
  3. migratory birds
  4. changes to environment on federal land (+ reserves)
  5. federally regulated project effects like nuclear, rail, port, pipelines, offshore energy
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

example of oil & gas hybrid screening

A

New oil refinery, including a heavy oil upgrader, with an input capacity of 10 000 m3 per day or more; Expansion of an existing oil refinery, including a heavy oil upgrader, that would result in an increase in input capacity of 50% or more and a total input capacity of 10 000 m3 per day or more.

input + output = thresholds
oil refinery= project list

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Transportation related project hybrid screening process

A

New freight or inter-city passenger railway line that requires a total of 50 km or more of new right of way.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

example of a new mining operation hybrid screening

A

New metal mill with an ore input capacity of 5 000 t/day or more; Expansion of an existing metal mill that would result in an increase in the area of mine operations of 50% or more and a total ore input capacity of 5 000 t/day or more

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

“federal lands and protected areas”

A
  • aerodrome or runway
  • aquaculture facility
    *canal or lock…
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Manitoba EA screening operates under a __ (type)____ process, and it determined by the _____.

A

operates under List Based screening (Class I, II, III)

determined by the gov

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

what is the precautionary principle

A

“if a product, an action or a policy has a suspected risk of causing harm to the public or to the environment, protective action should be supported before there is complete scientific proof of a risk”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

4 steps to facilitate EA scoping process

A
  1. scope project alternative
  2. identify valued environmental components (VEC)
  3. Delineate the assessments spatial and temporal boundaries
  4. identify potential impacts/ concerns
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is scoping?

A

determining the important issues and parameters that should be addressed in an EA, establish spatial & temporal boundaries, and focusing the ass on relevant issues and concerns

17
Q

define Terms of Reference (TOR)

A

parameters already given to base the project off of.

need to have knowledge and skills to identify parameters depending on project

ex: sea port vs wind mill vs mine

18
Q

2 types of scoping are:

A

open and closed scoping

19
Q

define closed scoping

A

-the content and scope is predetermined by law
-any modification is closed consultation b/w Agency and proponent

20
Q

3 most common parameters

A

-air quality
-water quality
-soil quality

21
Q

define open scoping

A

scope of the EA determined by transparent process based on consultation with varied interests

more recent and progressive

22
Q

Scoping Step 1: scope project alternative

A

-explore and consider alternatives to the proposed project
-often skipped/ignored

ex: do we need a new E building or can we buy it from somewhere else? can we try an alt E source?

23
Q

difference between alternative to and alternative means

A

alt to: before planning the project, you ask if its even needed

alt means: the project is going ahead, are there alt means to the current plan that mitigate issues/ are more efficient

24
Q

Step 2 of Scoping: Identify Values Environmental Components (VEC/EC/VC)

A

choosing publicly or scientifically valued components that warrant consideration in the EA

technically not just environmental, but human and physical

25
Q

In addition to social and ecological importance, VECs are considered based on:

A

-rarity
-fragility
-scientific value for study
-legal compliance
-economic importance
-professional judgement
-biodiversity and conservation value
-medicinal importance
-recreational value
-spiritual value

26
Q

how should you decide what VECs to look at for you EA?

A

look up previous EAs that follow a similar project

27
Q

the leopold matrix is represented by #/#, which ranks a resources (____)/(____)

A

magnitude / significance

28
Q

a good Indicator for a VEC is:

A

-measurable
-indicative of the VEC
-sensitive and detectable
-appropriate to spatial scale
-temporally reliable
-diagnostic to change
-applicable across develop project
-cheap to measure
-predictable and accurate
-easy to comprehend by all
-useful for informing management and decisions

29
Q

how to establish VEC objective??

A

Benchmark: standard/baseline/point of reference against which change is measured
Threshold:
established limits of change

30
Q

questions to ask when conducting a baseline study?

A

what do we need to know about the baseline environment to make a decision on the project?

what are the relevant background conditions that have influenced the current environment?

what is the likely baseline conditions in the future in the absence of the project?

31
Q

why is baseline data relevant to EA?

A

baseline data forms the basis on which impacts will be assessed

helps assess trends, rats, patterns, magnitude of change, and significance of VEC