Scope Management Flashcards

1
Q

What process are Deliverables defined in?

A

Collect Requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What process is Project Scope Statement output of?

A

Define Scope

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Where would you find a detailed list and description of specific project assumptions associated with the project?

Project charter
Project scope statement
Project configuration document
Change management plan

A

The Project scope statement lists and describes the specific project assumptions associated with project scope and the potential impact of those assumptions if they prove to be false. The assumptions listed in the detailed project scope statement are typically more numerous and detailed than the project assumptions listed in the project charter.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

A management control point where scope, budget and schedule are integrated and compared to earned value for performance measurement is a:

Code of accounts
Control packages
Control account
Account Plan

A

This is a control account. Control accounts are placed at selected management points of the Work Breakdown Structure (WBS). Each control account may include one or more work packages, but each of the work packages must be associated with only one control account.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is missing from constituents of Scope Statement
Scope Description
Deliverables
Project Exclusions

A

Acceptance Criteria

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

WBS Dictionary Comprises of?

A

Description of Work
Schedule Milestones
Quality Requirements
Acceptance Criteria

How well did you know this?
1
Not at all
2
3
4
5
Perfectly