Processes for which EEF is not an Input?
- Close Project/Phase
- Validate Scope
- Control Scope
- Control Costs
- Control Schedule
- Manage Quality
- Control Resources
- Implement Risk Responses
- Monitor Risks
Processes for which EEF is updated?
- Acquire Resources
- Develop Team
- Manage Team
Processes for which OPA is updated?
- Integration (Direct and Manage Proj Work, Manage Project Knowledge, Close Project/Phase)
- Resources (Acquire Res, Develop Team)
- Communication (Manage Communications)
- Risk (Monitor Risks)
- Procurement (All Processes)
Processes for which OPA is Only an Update?
Monitor Risks
Processes for which Lessons Learnt is ONLY UPDATE?
- Direct and Manage Project Work
- Plan Quality Management
- Estimate Activity Resources
- Acquire Resources
- Plan Procurement Management
Processes for which Lessons Learnt is UPDATED and OUT?
Manage Project Knowledge
Processes for which Lessons Learnt is ONLY IN?
Collect Requirements
What are some high points about Lessons Learnt?
LLR is Out from 1 Process
LLR is Input in 26 Processes
LLR is Updated in 29 Process
LLR is Untouched in 18 Processes
LLR is only Updated in 5 Processes
LLR is Only IN from 1 process
Lessons Learnt untouched in Integration Management for?
- Develop Project Charter
- Develop Project Management Plan
- Perform Integrated Change Control
Lessons Learnt untouched in Scope Management for?
- Plan Scope Management
- Define Scope
- Create WBS
Lessons Learnt untouched in Schedule Management for?
- Plan Schedule Management
- Define Activities
- Sequence Activities
Lessons Learnt untouched in Cost Management for?
- Plan Cost Management
2. Determine Budget
Lessons Learnt untouched in Resource Management for?
Plan Resource Management
Lessons Learnt untouched in Risk Management for?
- Plan Risk Management
2. Quant / Qual Risk Analysis
Lessons Learnt untouched in Stakeholder Management for?
- Identify Stakeholder
2. Plan Stakeholder Management