Scheduling and Monitoring Projects Flashcards

1
Q

What is the scheduling problem?

A

Projects tend to be either:
1. Time constrained
- must be completed by fixed end date
- add resources as required to meet the deadline
- focus on resource utilisation (smooth the demand)
- delay non-critical activities by using slack to reduce peak demands and fill troughs in demand

  1. Resource restrained (people, materials, equipment, cost)
    - must be completed with a fixed level or resources
    - project may be delayed in order to keep within the resource constraint
    - allocate resources so as to minimise project delay without exceeding resource constraints
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What impact to constraints have on the project schedule?

A
  • Can delay start or completion of project activities
    -Resources can be increased to speed ip activity/ project completion
  • Delaying or bringing forward activities to optimise use of resources is called either ‘smoothing’ or ‘levelling’ depending on the effect on the critical path
  • Shortening the critical path is called ‘CRASHING’ the project
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the purpose of float (slack)?

A
  • Start/ finish dates for activities can be shifted
  • Activities can run concurrently
  • Float can be manipulated to optimise project duration AND use of resources (i.e. cost)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What happens when resources are not capable of meeting peak demand requirements and are constrained?

A

The project manager has to:
- Level resource usage
- Prioritise and allocate resources to minimise project delay
- If resources and people are over-allocated, consider reallocating work activities
- Consider crashing activity times

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How do you schedule for efficient resource utilisation?

A

It is invariably inefficient to always start activities at their ES time:
- causes peaks and troughs in resource usage (people, materials, equipment and working capital)

It is often desirable to ‘level’ or ‘smooth’ resource usage throughout the project:
- sometimes via redrawing of the network
- more likely via adjusting project start, completion, and/ or crashing/ lengthening duration times

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the activity crash times and costs?

A

Normal time = realistic, cost-effective, efficient method for completing an activity under normal conditions

Normal cost = the cost of completing the activity in normal time

Crash time = the shortest possible time an activity can be completed if resources are not constrained

Crash cost = the cost of completing the activity in crash time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the formula for the Cost Slope?

A

Cost Slope = (crash cost - normal cost) / (normal time - crash time)

Cost slope = crash cost per day

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How do you approach crashing a project?

A
  • Ignore tasks not on the critical path
  • Select the critical path task(s) with the lowest crash cost(s) to crash first
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are the options for crashing project activities?

A
  • Adding additional resources
  • Outsourcing project work
  • Scheduling overtime working
  • Establishing a team-concerted effort
  • Quick and dirty attempt (sometimes works)
  • Fast tracking (concurrent activities)
  • Brainstorm time saving ideas (value management)
  • Reduce scope of project
  • Rephase project delivery (part delivery)
  • Compromise quality

POTENTIALLY KEEP GOING UNTIL ALL ACTIVITIES ARE CRITICAL

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What can changes to projects arise from?

A
  • Customer request (external)
  • Project failures (internal)
    • e.g. functional deficiencies, slippage, cost variances
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What can the need for recovery action be triggered by?

A

Adverse variance on a number of measures. e.g.:
- Budgeted costs vs actual costs
- Budgeted man-hours vs actual man-hours
- Budgeted % complete vs actual % complete
- Scheduled date of milestone vs actual date of milestone

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What data needs to be monitored?

A
  • Cost data (only available at the end of the accounting period - does not include commitments)
  • Man-hours (normally accurate and up-to-date, as time sheets are completed weekly)
  • % complete (subjective and optimistic)
  • Milestones (accurate but too late for remedial action)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What performance criteria will the project manager need to monitor?

A
  • Time performance
  • Cost/ budgetary performance
  • Technical and quality performance

All in time to take corrective action

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

How do you evaluate project progress?

A

There are different ways to do this, which are often derived from methods of project scheduling:
- the project network (AOA or AON)
- individual reports for WBS work elements or packages (accountability)
- Gantt charts and control charts

Gantt charts and control charts are most usually used for reporting purposes:
- easy to understand
- provide an overview (not overly detailed)
- don’t include connection with cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly