Critical Path Analysis in Project Management Flashcards

1
Q

What is the purpose of project scheduling?

A
  • Comprehensive and comprehensible picture of project activities
  • Illustrates relationships between activities
  • Communicates plan to others
  • Tends to be graphical
  • Key means of estimating and controlling the project
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are Gantt charts?

A
  • Developed in early 20th century
  • Give a clear, pictorial model of the project
  • Are simple and require very little training to understand and use
  • Show progress
  • Can be used for resource planning
  • Can show inter-relationships and critical path
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the advantages of Gantt charts?

A
  • Simple to draw and read
  • Good in static environments
  • Useful as an overview
  • Very widely used
  • Graphical interface of most PC project planning systems (e.g. MS Project)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the disadvantages of Gantt charts?

A
  • Difficult to update manually
  • Can become obsolete (and discredited)
  • Does not equate time with cost
  • Does not help in optimising resources
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is Project network analysis?

A
  • Shows the activities, the logical sequence and interdependencies, and the total time required to complete a project
  • Handles inter-relationships between activities
  • Identifies activities critical to the project finishing on time
  • Take time to produce but valuable for all but the smallest of projects
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is the activity?

A

Task or set of tasks required to deliver the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the event?

A

Identifiable state resulting from completion of one or more activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is a milestone?

A

Identifiable and noteworthy events, marking significant progress

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is a network?

A

A diagram of nodes and directional arcs that define the project and illustrate relationships between activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is a path?

A

A series of connected activities between any two events

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is a critical path?

A

The set of activities on a path from the project’s start event to the finish event that, if delayed, will delay the completion of the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is a critical event?

A

The time required to complete all activities on critical path

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

How do you build a network?

A

Activity on Node (AON) Network

Activity A dependency Activity B

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are the basic rules for networks?

A
  • Networks flow from left to right
  • An activity cannot begin until ALL preceding connected activities have been completed
  • Arrows indicate precedence and flow, and can cross over each other
  • Each activity should have a unique identification number (use WBS)
  • LOOPING is not allowed
  • CONDITIONAL STATEMENTS are not allowed
  • It is good practice to use a single ‘Start’ node and a single ‘Finish’ node
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is the CPA analysis?

A
  • Earliest Start Time (ES)
  • Earliest Finish Time (EF)
  • Latest Start Time (LS)
  • Latest Finish Time (LF)
  • Duration (d)
  • Total Float or Slack (TF)
  • Forward Pass
  • Reverse / Backward pass
  • Critical patch
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What are the advantages of AON?

A
  • No dummy activities are used
  • Events not used, just activities
  • AON easy to draw when dependencies and relationships are straightforward
  • Activity emphasis easily understood by all levels in the organisation
17
Q

What are the disadvantages of AON?

A
  • Path tracing by activity number can be difficult to envisage - little sense of flow
  • Network drawing and understanding difficult when dependencies are numerous and complex
18
Q

What are the two types of errors in predicting the future?

A

Random errors = the chances and sizes of over and under-estimates are about equal, these ‘balance’ out when summed

Biased or systematic errors = the chance and size of under and over-estimates are not equal, these errors do not cancel out when summed