Scheduling Flashcards
What does CPM stand for?
Critical Path Method
What are the 2 CPM diagrams?
Activity on Arrow and Activity on Node (AOA and AON)
What determines the project duration?
The critical path activities
What is Early Start (ES)?
Latest EF (early finish) of all IPA’s
What is Early Finish (EF)?
Early Start + Duration
What is Late Finish (LF)?
Earliest late start of succeeding activities
What is Late Start (LS)?
Late Finish - Duration
What is Total Float (TF)?
The time an activity can be delayed without affecting project completion (LS - ES)
What is Free Float (FF)?
The time an activity may be delayed without affecting the early start of any of the next immediate activities
What is Critical Path (CP)?
The longest interconnected path through the network which has a length equal to the project duration
What is the procedure for network calculations?
1) Do and forward pass and calculate all ES’s and EF’s
2) Do a backwards pass and calculate all LF’s and LS’s
3) Calculate floats
4) Determine critical path
For resource levelling, which activities are proceeded with first and given the most importance?
The activity with the earliest late start
What is Interfering Float (IF)?
The amount of time an activity can be delayed or extended from its ES without delaying the total float (TF)
What are the values for TF, FF, IF for critical path activities?
0
What does a negative total float (TF) represent?
Means you have to make up (save) that duration
For example if activity B has a TF of -3 then activity B must be cut short by 3 days in order to not disrupt the project completion date