Estimating Flashcards
What is direct cost?
Any cost that can be associated with a discrete physical part of a construction project
What is indirect cost?
Any cost that cannot be associated with a discrete physical part of a construction project
What are the six levels of estimating?
1) Conceptual Estimate for Feasibility Studies
2) Estimate to Evaluate Alternative Designs
3) Owner’s/Engineers Estimate
4) Contractor’s Bid Estimate
5) Alternative Construction Methods Estimate
6) Change Order or Claims Estimate
What are the horizontal format items?
L (Labour) RL (Repair and Service Labour) PM (Permanent Materials) EM (Expendable Materials) S (Subs) EOE (Equipment Operating Expense) R (Rental, Depreciation, and Write-off)
What are the vertical format items?
Direct Cost Indirect Cost Escalations Interest Contingency Markup Bond Fee
Rank the horizontal format items in order from most risky to least risky
L, RL, O&M
EM
EOE, R
S, PM
What are the three identified contingencies?
Productivity Hedge
Soft Subs
Special Risk Events
What estimate is the most detailed?
Contractor’s Bid Estimate
What are the three types of escalations?
Labour
Material
Equipment
What is unidentified contingency covered in?
Markup
What are the three methods for calculating markups?
1) Percent of total cost
2) Percent of labour
3) Broad based