RULE I- RULE III Flashcards

1
Q

Presidential Decree 1096 is also known as the ___

A

National Building code of the Philippines

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Who shall serve as the technical staff of the Secretary in the administration and enforcement of the provisions of PD 1096 and its IRR?

A

National Building Code Development Office (NBCDO)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Any new construction which increases the height and/ or floor area of existing building/structures

A

Addition

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Works in buildings/ structures involving changes in the materials used, partitioning, location/ size of openings, structural parts, existing utilities and equipment but does not increase the building height and/or floor area.

A

Alteration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

the Executive Offices of the OBO appointed by the Secretary

A

Building Official

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

A document issued by the Building Official to an owner/ applicant to proceed with the construction, installation, addition, alteration, renovation, conversion, repair, moving, demolition and other work activity of a specific project/ building/ structure or portions thereof after the accompanying principal plans, specifications and other pertinent documents with the duly notarized application are found satisfactory and substantially conforming with the National Building Code of the Philippines ( the Code) and its Implementing Rules and Regulations (IRR)

A

Building Permit

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

PD 1096, otherwise known as the National Building Code of the Philippines

A

Code

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

All on-site work done in the site preparation, excavation, foundation, assembly of all the components and installation of utilities, machineries and equipment of buildings/ structure.

A

Construction

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

A change in the use or occupancy of buildings/ structures or any portion/s thereof, which has different requirements

A

Conversion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

The systematic dismantling or destruction of a building/ structure, in whole or in part.

A

Demolition

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

The Executive Officer or Head of the NBCDO

A

Executive Director

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

The transfer of buildings/ structures or portion/ s thereof from original location or position to another, either within the same lot or to a different one.

A

Moving

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

The office authorized to enforce the provisions of the Code and its IRR in the field as well as the enforcement of orders and decisions made pursuant thereto.

A

Office of the Building Official (OBO)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Any physical change made on buildings /s structures to increase the value, quality and/ or to improve the aesthetic.

A

Renovation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Remedial work done on any damaged or deteriorated portion/s of buildings/ structure to restore to its original condition

A

Repair

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Head or Chief Executive Officer of DPWH

A

Secretary

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

The personnel of the National Building Code Development Office (NBCDO)

A

Staff

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Qualifications of Building Officials

A

A Filipino citizen and of good moral character
A duly registered Architect or Civil Engineer
A member of good standing of a duly accredited organization of his profession for not less than years endorsed or recommended by the accredited professional organization.
Has at least 5 years of diversified and professional experience in building design and construction
Has attended and successfully completed a seminar or workshop on PD1096 and its IRR conducted by the DPWH.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Building Official shall retain not more than __ of the income/collection derived from permit fees and other charges for the operating expenses of his office.

A

20%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

What are exempted from the payment of building permit fees

A

Public Buildings
Traditional Indigenous Family Dwellings - made of native materials and cost does not exceed P15,000

21
Q

Share of the local government and share of the national government

A

80% & 20%

22
Q

Fine for erecting, constructing, altering, repairing, moving, converting, installing, or demolishing a private or public building / structure if without building / demolition permit

A

P 10 000

23
Q

Amount of
Fines: Light Violations, Less Grave Violations
Grave Violations

A

P5,000 ; P8,000; P10,000

24
Q

Violation and Fine: Use or occupancy of building/structure without appropriate Certificate of Occupancy/Use/Operation.

A

Less Grave Violation; P8000

25
Q

Violation and Fine: Failure to post Certificate of Occupancy/Use/Operation

A

Light Violations; P5000

26
Q

Violation and Fine: Non-compliance with order to abate or demolish

A

Grave Violations; P10,000

27
Q

What kind of hazard which whenever any door, aisle, passageway, stairway or other means of exit is not sufficient width or size or is not arranged as to provide safe and adequate means of exit in case of fire and panic

A

Fire Hazards

28
Q

What kind of hazard whenever any portion thereof has been wrecked, warped, buckled or settled to such as extend that the walls or other structural portions have materially less resistance to wind or earthquake than is required in the case of similar new construction

A

Structural Hazard

29
Q

Lack of adequate garbage and rubbish storage and removal or disposal facilities

A

Inadequate Sanitation/ Plumbing and Health Facilities

30
Q

Lack of or improper operation of required ventilating equipment or air-conditioning systems

A

Unsafe Mechanical Installation

31
Q

All wiring systems or installations which do not conform to the rules and regulations embodied in the latest Philippine Electrical Code

A

Unsafe Electrical Wiring

32
Q

Insufficient amount of natural light and ventilation due to inadequate open spaces such as courts and yards as required

A

Architectural Deficiency

33
Q

What is the prescribed application form to apply building permit

A

NBC Form B-01

34
Q

The building permit is null and void if not accompanied by the _____

A

ancillary permits

35
Q

What are the Ancillary Permits

A

Architectural Permit
Civil/ Structural Permit
Electrical Permit
Mechanical Permit
Sanitary Permit
Plumbing Permit
Electronics Permit

36
Q

___ are issued by the Building Official for accessory parts of the project with very special functions or use which are indicated in plans and specifications that accompany the building permit application

A

Accessory Permits

37
Q

Exemption from Building Permits

A

Minor Construction and Repair Works

38
Q

How many sets of of plans needed for the application of building permit?

A

5

39
Q

What are the requirements for application of permits if the applicant is the registered owner of the lot?

A

application forms for ancillary and accessory permits
Certified True copy of Original Certificate of Title (OCT) / Transfer Certificate of Title (TCT)
Tax Declaration
Current Real Property Tax receipt

40
Q

What are the requirements for application of permits if the applicant is not the registered owner of the lot?

A

Application Forms for Ancillary and Accessory Permits
Certified True Copy of Original Certificate of Title (OCT) / Transfer Certificate of Title (TCT)
Tax Declaration
Current Real Property Tax receipt
Notarized copy of the Contract of Lease or Deed of Absolute Sale

41
Q

The Building Official shall within ____ days from payment of the required fees by the applicant, issue the building permit applied for.

A

15 days

42
Q

How many years shall the Architect/ Engineer who drew up the plans and specifications for building/structure be liable for any collapse due to defect in plans or specifications or defects in the ground.

A

15 years

43
Q

What shall be kept at the jobsite at all times wherein the actual daily progress of construction including test conducted, weather condition and other pertinent data are to be recorded.

A

Logbook of Daily Construction Activites

44
Q

What shall the owner/permittee submits to the OBO for application of Certificate of Occupancy

A

Construction Logbook
As-built plans and specifications
Building Inspection Sheet - signed by contractor, owner and licensed Architect or CE

45
Q

What certificate needed to obtain so the building/structure shall be used

A

Certificate of Occupancy

46
Q

What law governs the licensed and registered contractor?

A

Contractor’s License Law (RA 4566)

47
Q

A building permit issued under the provisions of the Code shall expire and become null and void if the building or work authorized is not commened within a period of?

A

1 year / 12 months

48
Q

A building permit issued under the provisions of the Code shall expire and become null and void if the building or work is suspended or abandoned at any time after it has been commenced for a period of ___

A

120 days

49
Q

What are the Rules of National Building Code

A

Rule
1 - General Provisions
2 - Administration and Enforcement
3 - Permits and Inspections
4 - Types of Construction
5 - Requirements for Fire Zones
6 - Fire Restrictive Requirements in Construction
7 - Classification and General Requirement for all Building types by Use or Occupancy
8 - Light and Ventilation
9 - Sanitation
10 - Building Projection over Public Street
11 - Protection of Pedestrian during Construction or Demolition
12 - General Design and Construction Requirements
13 - Electrical and Mechanical Regulation
14 - Photographic and X-ray Films
15 - Prefabricated Constructions
16 - Plastics
17 - Sheet Metal Paint Spray Booths
18 - Glass and Glazing
19 - The use of Computers
20 - Signs
21- Transitory and Final Provisions