Presidential Decree 1096 is also known as the ___
National Building code of the Philippines
Who shall serve as the technical staff of the Secretary in the administration and enforcement of the provisions of PD 1096 and its IRR?
National Building Code Development Office (NBCDO)
Any new construction which increases the height and/ or floor area of existing building/structures
Addition
Works in buildings/ structures involving changes in the materials used, partitioning, location/ size of openings, structural parts, existing utilities and equipment but does not increase the building height and/or floor area.
Alteration
the Executive Offices of the OBO appointed by the Secretary
Building Official
A document issued by the Building Official to an owner/ applicant to proceed with the construction, installation, addition, alteration, renovation, conversion, repair, moving, demolition and other work activity of a specific project/ building/ structure or portions thereof after the accompanying principal plans, specifications and other pertinent documents with the duly notarized application are found satisfactory and substantially conforming with the National Building Code of the Philippines ( the Code) and its Implementing Rules and Regulations (IRR)
Building Permit
PD 1096, otherwise known as the National Building Code of the Philippines
Code
All on-site work done in the site preparation, excavation, foundation, assembly of all the components and installation of utilities, machineries and equipment of buildings/ structure.
Construction
A change in the use or occupancy of buildings/ structures or any portion/s thereof, which has different requirements
Conversion
The systematic dismantling or destruction of a building/ structure, in whole or in part.
Demolition
The Executive Officer or Head of the NBCDO
Executive Director
The transfer of buildings/ structures or portion/ s thereof from original location or position to another, either within the same lot or to a different one.
Moving
The office authorized to enforce the provisions of the Code and its IRR in the field as well as the enforcement of orders and decisions made pursuant thereto.
Office of the Building Official (OBO)
Any physical change made on buildings /s structures to increase the value, quality and/ or to improve the aesthetic.
Renovation
Remedial work done on any damaged or deteriorated portion/s of buildings/ structure to restore to its original condition
Repair
Head or Chief Executive Officer of DPWH
Secretary
The personnel of the National Building Code Development Office (NBCDO)
Staff
Qualifications of Building Officials
A Filipino citizen and of good moral character
A duly registered Architect or Civil Engineer
A member of good standing of a duly accredited organization of his profession for not less than years endorsed or recommended by the accredited professional organization.
Has at least 5 years of diversified and professional experience in building design and construction
Has attended and successfully completed a seminar or workshop on PD1096 and its IRR conducted by the DPWH.
Building Official shall retain not more than __ of the income/collection derived from permit fees and other charges for the operating expenses of his office.
20%
What are exempted from the payment of building permit fees
Public Buildings
Traditional Indigenous Family Dwellings - made of native materials and cost does not exceed P15,000
Share of the local government and share of the national government
80% & 20%
Fine for erecting, constructing, altering, repairing, moving, converting, installing, or demolishing a private or public building / structure if without building / demolition permit
P 10 000
Amount of
Fines: Light Violations, Less Grave Violations
Grave Violations
P5,000 ; P8,000; P10,000
Violation and Fine: Use or occupancy of building/structure without appropriate Certificate of Occupancy/Use/Operation.
Less Grave Violation; P8000
Violation and Fine: Failure to post Certificate of Occupancy/Use/Operation
Light Violations; P5000
Violation and Fine: Non-compliance with order to abate or demolish
Grave Violations; P10,000
What kind of hazard which whenever any door, aisle, passageway, stairway or other means of exit is not sufficient width or size or is not arranged as to provide safe and adequate means of exit in case of fire and panic
Fire Hazards
What kind of hazard whenever any portion thereof has been wrecked, warped, buckled or settled to such as extend that the walls or other structural portions have materially less resistance to wind or earthquake than is required in the case of similar new construction
Structural Hazard
Lack of adequate garbage and rubbish storage and removal or disposal facilities
Inadequate Sanitation/ Plumbing and Health Facilities
Lack of or improper operation of required ventilating equipment or air-conditioning systems
Unsafe Mechanical Installation
All wiring systems or installations which do not conform to the rules and regulations embodied in the latest Philippine Electrical Code
Unsafe Electrical Wiring
Insufficient amount of natural light and ventilation due to inadequate open spaces such as courts and yards as required
Architectural Deficiency
What is the prescribed application form to apply building permit
NBC Form B-01
The building permit is null and void if not accompanied by the _____
ancillary permits
What are the Ancillary Permits
Architectural Permit
Civil/ Structural Permit
Electrical Permit
Mechanical Permit
Sanitary Permit
Plumbing Permit
Electronics Permit
___ are issued by the Building Official for accessory parts of the project with very special functions or use which are indicated in plans and specifications that accompany the building permit application
Accessory Permits
Exemption from Building Permits
Minor Construction and Repair Works
How many sets of of plans needed for the application of building permit?
5
What are the requirements for application of permits if the applicant is the registered owner of the lot?
application forms for ancillary and accessory permits
Certified True copy of Original Certificate of Title (OCT) / Transfer Certificate of Title (TCT)
Tax Declaration
Current Real Property Tax receipt
What are the requirements for application of permits if the applicant is not the registered owner of the lot?
Application Forms for Ancillary and Accessory Permits
Certified True Copy of Original Certificate of Title (OCT) / Transfer Certificate of Title (TCT)
Tax Declaration
Current Real Property Tax receipt
Notarized copy of the Contract of Lease or Deed of Absolute Sale
The Building Official shall within ____ days from payment of the required fees by the applicant, issue the building permit applied for.
15 days
How many years shall the Architect/ Engineer who drew up the plans and specifications for building/structure be liable for any collapse due to defect in plans or specifications or defects in the ground.
15 years
What shall be kept at the jobsite at all times wherein the actual daily progress of construction including test conducted, weather condition and other pertinent data are to be recorded.
Logbook of Daily Construction Activites
What shall the owner/permittee submits to the OBO for application of Certificate of Occupancy
Construction Logbook
As-built plans and specifications
Building Inspection Sheet - signed by contractor, owner and licensed Architect or CE
What certificate needed to obtain so the building/structure shall be used
Certificate of Occupancy
What law governs the licensed and registered contractor?
Contractor’s License Law (RA 4566)
A building permit issued under the provisions of the Code shall expire and become null and void if the building or work authorized is not commened within a period of?
1 year / 12 months
A building permit issued under the provisions of the Code shall expire and become null and void if the building or work is suspended or abandoned at any time after it has been commenced for a period of ___
120 days
What are the Rules of National Building Code
Rule
1 - General Provisions
2 - Administration and Enforcement
3 - Permits and Inspections
4 - Types of Construction
5 - Requirements for Fire Zones
6 - Fire Restrictive Requirements in Construction
7 - Classification and General Requirement for all Building types by Use or Occupancy
8 - Light and Ventilation
9 - Sanitation
10 - Building Projection over Public Street
11 - Protection of Pedestrian during Construction or Demolition
12 - General Design and Construction Requirements
13 - Electrical and Mechanical Regulation
14 - Photographic and X-ray Films
15 - Prefabricated Constructions
16 - Plastics
17 - Sheet Metal Paint Spray Booths
18 - Glass and Glazing
19 - The use of Computers
20 - Signs
21- Transitory and Final Provisions