1
Q

Triangular shape with one side horizontal

A

Danger warning signs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Average dept of embankment material needed to place on top of natural ground

A

Fill

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

A road by which a job is connected to the highway system, used in connection with borrow pits

A

Access Roads

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Lines laid ACROSS the direction of travel

A

Transverse

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Lines laid IN the direction of Travel

A

Longitudinal

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Employed to inform road users of route, destinations and other pertinent traffic

A

Guiding Device

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Marker that are Rectangular w/ series of alternating black & white bands

A

Hazards

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Provide space for the expansion of the pavement, preventing compressive stress

A

Expansion Joint

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Road Marking should be of ____ and should protrude more than 6mm above level of the carriage way

A

Non skid material

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Measure of concrete fluidity

A

Consistency

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Brooming should not be more than ___ in depth

A

1.5mm

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Used to restrain and guide out of control vehicles that will cause least damage

A

Guard Rails

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Concrete Vibrators are not allowed to be operated longer than ____ seconds

A

15

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Simplest form of road by shaping and smoothing natural soil

A

Earth Road

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Ensure adhesion of the surface course to the binder course

A

Tack Coat

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Composed of one part Portland Cement and two parts Aggregate so and water to handle it easily

A

Mortar

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Painted sticks placed along the side of the road as guide and reference in elevation

A

Blue Tops

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Signs round and in blue colors

A

Obligatory

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Located beneath or alongside the roadway collecting surface water

A

Drainage structure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Means by which road users is advised as to detailed requirements affecting road use

A

Traffic Control Devices

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Concrete’s ability to be placed in a prepared form w/o honeycomb

A

Workability

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Removal of saturated mixtures of soils and organic matter

A

Unsuitable Excavation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Forms should be made of ___ of an approved section

A

Steel

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

Undertaken after the curing period before the pavement is opened

A

Sealing of Joints

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

Removing earth from its original position in a cut

A

Excavation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

Small rectangle device fixed to the pavement surface supplement pavement markings

A

Raised Pavement Markers

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

Used for lane control. White in color, 5m in length (urban) 7.5m in high speed road

A

Pavement arrow

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

Earth fill below the pavement to raise the road

A

Embankment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

Excavation of common materials used as embankment fill

A

Common Excavation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

Constructed when there’s an interruption of more than 30 mins in concreting

A

Construction Joint

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

PCCP (Abbrev meaning)

A

Portland and Concrete Cement Pavement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

structure that link barangays and cities in the country, serves as medium in transporting goods

A

Road

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

Philippine Traffic signs conform to the _____ of the United Nations on Road traffic and Road Signs

A

1968 Vienna Conventions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q

Pressing of soil particles to expel air from the mass and filling the voids to make the material more dense

A

Compaction

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q

Used to inform road users of potentially hazardous roadway conditions

A

Warning Devices

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
36
Q

it is sometimes termed as an all weather road

A

Gravel Road

37
Q

tool for economic road building, material conservation, investment protection and roadway upgrading

A

Soil Stabilization

38
Q

Conducted on site in order to determine if the required compaction specification has been attained

A

Field Density Test

39
Q

A bituminous layer below the surface or wearing course

A

Binder Course

40
Q

The uppermost structural component of the roadway, provide resistances to wear and shearing stress

A

Surface Course

41
Q

Average depth needed in excavating the natural found to satisfy the designed grade

A

Cut / Excavation

42
Q

Serves to provide structural capacity to bituminous concrete slabs

A

Base and Subbase courses

43
Q

Signs that are small and rectangular, supplement information on the main sign

A

Additional Information

44
Q

Necessary to divert traffic from any existing roadway whenever the construction operations block the flow of traffic

A

Detour Roads

45
Q

Done within 24 hours after concrete pouring water using cooled diamond edge saw blade

A

Concrete Sawing

46
Q

Signs shall have a yellow background and red border

A

Yield

47
Q

Determines actual position of the road structure based on the plans

A

AS-Stake Survey

48
Q

Structural layer which accepts greater compressive stress than the subgrade and reduces the deformation of the pavement

A

Subbase Course

49
Q

Essential ingredient in rigid pavements, most structural concrete

A

PC - Portland Cement

50
Q

The upper layer of natural soil which may be undisturbed local materials or soil elsewhere

A

Subgrade

51
Q

used to grade concrete in such manner to prevent segregation

A

Screeding

52
Q

Three Elements of the Road System

A

The Road
The Vehicle
The Driver

53
Q

Forms for concrete shall remain in place undisturbed within ___ hours after pouring

A

24

54
Q

Deformed bars used in construction and longitudinal joints together with keys to tie 2 slabs together

A

Tie bars

55
Q

Load transfer devices in joints to transfer loads from one slab to another

A

Dowels

56
Q

small reflective panels mounted on guide post as an effective aid for night driving

A

Delineators

57
Q

Suitable material from sources outside the roadway

A

Borrow

58
Q

Layer of material placed on an existing surface to eliminate irregularities placing an overlaying course

A

Leveling Course

59
Q

Signs are rectangular with a white or yellow plate with a symbol that stands for service

A

Information Sign

60
Q

Excavation and disposal of materials regardless of its nature

A

Unclassified Excavation

61
Q

Normally consist of lines, patterns words and symbols

A

Traffic Markings

62
Q

After grouting, the surface is cured for a period of at least __ days from installation

A

3 days

63
Q

____ shape shall be used for STOP signs only

A

Octagonal

64
Q

are normally used in expansion joints, and their diameter, spacing and length would be similar to that indicated for contraction joints

A

Dowel Bars

65
Q

Upper level of natural soil which may be undisturbed local materials

A

Subgrade

66
Q

After the concrete has been struck off and consolidated, it is further smoothed by means of ________

A

Floating

67
Q

______ shape shall be used for regulating traffic

A

Round

68
Q

Suitable native material obtained from roadway cuts or borrow areas

A

Selected Borrow

69
Q

Employed more FREQUENTLY than any other devices to regulate, warn or guide road users

A

Traffic Signs

70
Q

Suitable materials which can be common or rock which are brought and compacted together to form a stable embankment

A

Embankment Fill

71
Q

Means removing and disposing all surface objects including vegetation tress and other objects not designated along the roadway

A

Clearing and Grubbing

72
Q

Substance other than aggregates water and Portland cement that can be added to concrete to improve its properties

A

Admixture

73
Q

serves to stabilize the base and bind it to the paving material

A

Prime Coat

74
Q

meant to stabilize the foundation bed to avoid possible settlement that impair the function of drainage

A

Foundation Fill

75
Q

Are suitable materials excavated along the road traverse which are disposed as excess of embankment

A

Surplus Excavation

76
Q

necessary for the hydration to take place so that the concrete may harden properly and prevent loss of moisture during curing

A

Concrete Curing

76
Q

Maximum number of words that can be placed as pavement marking

A

3

77
Q

should be smooth yet skid resistant, quiet when in contact with tires

A

Wearing Course

78
Q

made of mineral aggregate mixed with asphalt laid at high temperature of 275 to 300 deg.

A

Asphalt Concrete Pavement

79
Q

Angle of constructed soil plane usually expressed in proportion of length and depth

A

Slope

80
Q

Consists of igneous, sedimentary and metamorphic rocks which cannot be excavated with blasting

A

Rock Excavation

81
Q

Constructed along side the road as protection from erosion

A

Slope Protection

82
Q

described as flexible pavement

A

Asphalt Road

83
Q

Fill may be obtained by _________ with bulldozer from borrow pits

A

Quarrying

84
Q

Describe the compressive strength of concrete mix

A

Water-Cement Ratio

85
Q

Compaction Trial of not less than ____ sq.m is done to determine the actual capability of compaction

A

500

86
Q

treatment applied to concrete during hardening period to protect against early shrinkage due to lose of moisture

A

Curing Agent

87
Q

Raised rim of concrete which forms the edge of the sidewalk

A

Curb and Gutter

88
Q

Provided to relieve the tensile stresses due to temperature

A

Contraction Joint