risk management Flashcards
what are the 4 steps of risk management?
- identify and respond to risks specific to a project/organisation
- assess their impact against cost, schedule and performance
- plan strategies to mitigate risk
- control risks as they occur
define risk management
a 4-step, proactive, iterative process involving everyone
list some risk identification techniques
- brainstorming
- interviewing
- learning from experience
- checklists
list some sources of risk
- technical
- legal and commercial
- environmental
- political
- competition
- low-volume products
- financial and economic
- IT and cyber threats
- security
- political
- international collaboration
- supply chain fragility
- market forces
- single source supply
- skills and labour
why must we categorise risk?
helps organisations identify where to put their resources so risks can be controlled
what are the key outputs of identifying risk?
- clear project objectives
- documented assumptions
- RM strategy
- RM plan that must be updated for the life of the project
- risk register (dynamic and so must be constantly reviewed and refreshed)
what are the two types of risk analysis methods?
- qualitative: low, medium and high ranges against probability and impact (3x3 or 5x5 matrix)
- quantitative: 3 point estimates for cost, schedule, and performance, more specific percentage
what does a high risk value mean for probability, performance impact, cost impact, and schedule impact?
- probability = > 50% chance
- performance impact = major shortfalls in key parameters
- cost impact = large increase in cost > £5m
- schedule impact = long project delay > 6 months
what does a medium risk value mean for probability, performance impact, cost impact, and schedule impact?
- probability = 20% - 50% chance
- performance impact = some shortfalls in one or two areas
- cost impact = significant increase in cost £1m - £5m
- schedule impact = significant project delay 1 - 5 months
what does a low risk value mean for probability, performance impact, cost impact, and schedule impact?
- probability = < 20% chance
- performance impact = few shortfalls in secondary parameters
- cost impact = small increase in cost < £1m
- schedule impact = short project delay
what are the outputs of risk analysis?
- prioritized list of risks
- agreed risk ownership
- qualitative risk data (high, medium, low)
- quantitative risk data (3-point estimates)
what risk mitigation do we have?
- tolerate: take the risk and live with consequences
- reject risk: it is not valid
how can we handle risks?
- terminate: take actions to eliminate the risk
- treat/reduce: reduce risk to a tolerable level
- transfer: to another party (e.g. insurance)
- acceptance: as it is not cost effective to manage it
- avoidance: by doing things differently
what must we consider in risk reduction plans?
- fallback and contingency plans (enables ‘what-if’ scenarios)
- secondary risks (do your mitigation actions have additional inherent risks?)
- post mitigation analysis (has your mitigation action improved the probability of success?)
- risks with interdependencies (risks that are linked to each other)
- opportunities (are there opportunities to further improve against project objectives?)
what are the outputs of risk reduction planning?
- risk handling options
- post-handling probabilities and/or impacts
- identified secondary risks
- trigger/decision points
- updated project plan