cost estimating Flashcards
define cost estimating
collecting and analysing historical data and applying quantitative models, tools and techniques, and norms databases to predict the cost of a project
what must our cost estimates be?
estimates must be credible (i.e. believable) and timely (to support business decisions), which means it has to be: robust (based on sound data), accurate, comprehensive, replicable, auditable
approx 6
what are some reasons to develop cost estimates?
- support decision making for annual budgeting, resource planning, and investment appraisals
- estimate total project cost
- determine whether a project is financially worth doing (ROI)
- determine cash flow
- use as the basis for project control: measures project progress
- assess impacts of changing technology, new equipment, or new operating or maintenance concepts
define cash flow
timing of money flow into and out of the project
approx 10
what are some challenges and limitations of cost estimation
- historical data is subject to estimator interpretation and so supporting assumptions must be provided
- cannot produce results that are better than input data
- cannot predict political impacts, particularly with government-related projects
- cannot substitute for sound judgment, management, or control
- cannot make the final decisions (cost estimates support decisions)
- incomplete project scope and requirements
- unreliable or unavailable data – too much or too little data
- time constraints
- inadequate systems can make data inaccessible
- documenting the estimate
what does documenting a cost estimate need to include?
- reason for development / stage in project life cycle
- who estimate is for / decisions it will support
- scope included/excluded
- assumptions, exclusions, and dependencies (AEDs)
what does the total project cost consist of?
total direct costs + total indirect costs = total project cost
what are direct costs and provide some examples
- are directly attributable/chargeable to a project or activity
- represent real cash outflows
- must be paid as project progresses
examples:
- labour: cost of people directly employed (expressed in monetary terms or person-hours)
- materials: material in final product (raw or machined/fabricated) and additional material
- plant and equipment: machinery, tools etc (used or hired)
define indirect costs and how do we allocate indirect labour costs?
- indirect costs (overheads) cover all resources within an organisation being used by the project, i.e. they are attributable/allocated to (shared across) all projects
- ratio percentages are often used to allocate indirect labour costs (non-touch labour, e.g. management) to a project – ratio used is arbitrary and depends on project/industry sector
give some examples of indirect costs
rent, lighting, heating, insurance, admin, hr, marketing, advertising
what would a ratio percentage of 15% mean if the total direct labour costs were £1m?
a ratio percentage of 15% adds a 15% indirect labour cost to the estimate, i.e. if direct labour costs were £1m then indirect labour costs would be £150k and so total labour costs would be £1,150,000
give reasons for cost increases
- complexity
- Scope/requirements changes - we need to prevent scope creep (adding new scope without budgeting for it)
- Making decisions with incomplete information (uncertainty)
- Long project durations
- Loss of experience / time between projects - firing staff, staff stopping and working on other projects
- Concurrent engineering - common in complex projects = entering manufacturing phase when design phase not completed
- poor risk and supply chain management
- People: skill sets and mentality (optimistic or pessimistic)
- Lack of knowledge management and lessons learned - reinforcing failure by not learning from mistakes
- Legislation - new regulations can have impacts on the way we work
- Politics - highly political projects influence decisions
define what is meant by concurrent engineering
starting the manufacturing phase when design not completed
what is scope creep?
adding new scope without budgeting for it
what are the different types of cost estimating?
- life cycle cost estimate (LCCE)
- independent cost estimate (ICE)
- estimate at completion (EAC) / latest revised estimate (LRE)
- rough order of magnitude estimate (ROM)
describe the life cycle cost estimate (LCCE)
- ‘cradle-to-grave’ estimate covering all costs associated with the project for its complete life cycle from concept through to disposal
- should be performed as early in the life cycle as possible as the opportunity to minimise total project costs diminishes rapidly as the design and development of a system proceeds
describe the independent cost estimate (ICE)
- an ICE is an LCCE developed by an estimator who is not associated with the project in question
- based on identical information used for the original estimate, a different estimating methodology is used to develop an unbiased estimate to test the original estimate for accuracy and reasonableness
describe the estimate at completion (EAC) / latest revised estimate (LRE)
- used for projects that have already started
- provides update on what project is likely to cost based on what has already happened
describe the rough order of magnitude estimate (ROM)
- used when little specific information is known about the project
- more likely to overestimate rather than underestimate costs, and so it is sometimes called a maximum or not-to-exceed estimate
what are cost models?
cost estimates are used to build cost models that are run through simulation software to obtain statistical outputs that indicate levels of confidence (between 0% and 100%) in achieving the estimate