Risk Assessment Flashcards

1
Q

Why must a risk assessment be completed?

A

To assess what employees do and how to mitigate the risks they are exposed to

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is an accident?

A

An unplanned, undesired occurrence which may result in harm or loss

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is a hazard?

A

Anything that has the potential to cause loss or harm

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is a risk?

A

How likely it is that a hazard will actually cause harm or loss

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the stages of risk assessment?

A

HAZID
HAZOP
Evaluation of risks
Implementing control measures
Recording findings
Reviewing & revising

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is HAZID?

A

HAZard IDentification
The first stage in risk analysis identifying potential causes of harm from equipment, electricity, substances and environment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is HAZOP?

A

A structured and systematic technique for risk management that identifies potential hazards

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How are likelihood and consequence measured?

A

In tables from 1-5, 1 being rare/insignificant, 5 being almost certain/catastrophic

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What does a risk matrix do?

A

Defines level of risk considering probability of an incident
The four risk levels are low (green), medium-low (yellow), medium-high (orange) and high (red)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are different controls of risk?

A

Elimination (i.e. removal of dangerous chemicals)
Reduction/substitution (i.e. using a less flammable substance)
Isolation (i.e. operating a machine remotely)
Engineering controls (i.e. machine guards)
Administration controls (i.e. different training)
PPE

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are some typical control measures?

A

Machine guarding
Machine isolation
PPE

How well did you know this?
1
Not at all
2
3
4
5
Perfectly