At what stage should a building regulation review be undertaken of the scheme?
Stage 3
At what stage should you submit the planning application
Stage 3
What team is involved at stage 0?
Client team only
When should you informa the client that other consultants may be needed to complete the project?
Stage 0
At what stage is the brief developed?
Stage 1
When do you identify Health and Safety risks?
Stage 0
What team is involved in stage 1?
Client team only
At what stage is the design team assembled?
Stage 1
When should feasibility studied be undertaken?
Stage 1
What do you understand through completing a feasibility study?
If the brief can be accommodated for
At what stage do fire safety requirements begin to inform the brief?
Stage 1
What is Stage 0?
Strategic Definition
What is Stage 1?
Preparation and Briefing
When are sustainability outcomes first considered?
Stage 0
When are CDM regulations first considered?
Stage 1
What team is involved at Stage 2 level?
Client and Design team
At what stage do specialist consultants come together to create an ‘architectural concept?
Stage 2
What should be produced when considering the design concept?
Options and appraisals
When is the design first reviewed?
Stage 2
Stage 2 definition
Concept and briefing
at what point should the concept of the building begin to align with a fire safety strategy?
Stage 2
At what stage should you seek pre-app planning advice?
Stage 2
Define stage 3
Spatial coordination
At what stage are the lead designer and design team (with the potential addition of construction team, depending on the specific procurement route) necessary in the project’s involvement?
Stage 3