RIBA Plan of work Flashcards

1
Q

At what stage should a building regulation review be undertaken of the scheme?

A

Stage 3

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

At what stage should you submit the planning application

A

Stage 3

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What team is involved at stage 0?

A

Client team only

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

When should you informa the client that other consultants may be needed to complete the project?

A

Stage 0

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

At what stage is the brief developed?

A

Stage 1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

When do you identify Health and Safety risks?

A

Stage 0

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What team is involved in stage 1?

A

Client team only

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

At what stage is the design team assembled?

A

Stage 1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

When should feasibility studied be undertaken?

A

Stage 1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What do you understand through completing a feasibility study?

A

If the brief can be accommodated for

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

At what stage do fire safety requirements begin to inform the brief?

A

Stage 1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is Stage 0?

A

Strategic Definition

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is Stage 1?

A

Preparation and Briefing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

When are sustainability outcomes first considered?

A

Stage 0

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

When are CDM regulations first considered?

A

Stage 1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What team is involved at Stage 2 level?

A

Client and Design team

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

At what stage do specialist consultants come together to create an ‘architectural concept?

A

Stage 2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What should be produced when considering the design concept?

A

Options and appraisals

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

When is the design first reviewed?

20
Q

Stage 2 definition

A

Concept and briefing

21
Q

at what point should the concept of the building begin to align with a fire safety strategy?

22
Q

At what stage should you seek pre-app planning advice?

23
Q

Define stage 3

A

Spatial coordination

24
Q

At what stage are the lead designer and design team (with the potential addition of construction team, depending on the specific procurement route) necessary in the project’s involvement?

25
At what stage are the building regulations in the scheme reviewed?
Stage 3
26
When is planning submitted?
Stage 3
27
At what stage is health and safety construction info obtained?
Stage 3
28
Define Stage 4
Technical Design
29
At what stage is the building regs application submitted?
Stage 4
30
what should be done with health and safety information at stage 4?
Include requirements in tender documents
31
At what stage will you recieve tender returns?
Stage 4
32
# 2 bullets How may the project be presented at stage 4?
* hand sketches * BIM model
33
Who is the main team involved at stage 5?
construction team
34
define stage 5
manufacturing and construction
35
At what stage does the involvement of the client/design team depend on the procurement strategy and construction contract?
Stage 5
36
At what stage do you recive pre-commencement planning conditions?
stage 4
37
At what stage does the PD/PC comeplete the health and safety file?
Stage 5
38
Where is the safety file included once it is completed?
In the building manual
39
At what stage is the building completed?
Stage 6
40
At which stage is information 'handed over' to the client and building users?
Stage 6
41
define Stage 6
Handover
42
When is the building manual handed over to users?
stage 6
43
what is the architect's role during stage 6?
to conduct a light-touch post-occupancy review
44
what is a post-occupancy review?
A review of the building once it has been handed over to assess how it is immediately performing
45
define stage 7
In-use
46
At what point are the design and construction team no longer involved?
Stage 7