RIBA Plan of work Flashcards

1
Q

At what stage should a building regulation review be undertaken of the scheme?

A

Stage 3

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

At what stage should you submit the planning application

A

Stage 3

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What team is involved at stage 0?

A

Client team only

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

When should you informa the client that other consultants may be needed to complete the project?

A

Stage 0

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

At what stage is the brief developed?

A

Stage 1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

When do you identify Health and Safety risks?

A

Stage 0

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What team is involved in stage 1?

A

Client team only

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

At what stage is the design team assembled?

A

Stage 1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

When should feasibility studied be undertaken?

A

Stage 1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What do you understand through completing a feasibility study?

A

If the brief can be accommodated for

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

At what stage do fire safety requirements begin to inform the brief?

A

Stage 1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is Stage 0?

A

Strategic Definition

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is Stage 1?

A

Preparation and Briefing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

When are sustainability outcomes first considered?

A

Stage 0

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

When are CDM regulations first considered?

A

Stage 1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What team is involved at Stage 2 level?

A

Client and Design team

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

At what stage do specialist consultants come together to create an ‘architectural concept?

A

Stage 2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What should be produced when considering the design concept?

A

Options and appraisals

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

When is the design first reviewed?

A

Stage 2

20
Q

Stage 2 definition

A

Concept and briefing

21
Q

at what point should the concept of the building begin to align with a fire safety strategy?

A

Stage 2

22
Q

At what stage should you seek pre-app planning advice?

A

Stage 2

23
Q

Define stage 3

A

Spatial coordination

24
Q

At what stage are the lead designer and design team (with the potential addition of construction team, depending on the specific procurement route) necessary in the project’s involvement?

A

Stage 3

25
Q

At what stage are the building regulations in the scheme reviewed?

A

Stage 3

26
Q

When is planning submitted?

A

Stage 3

27
Q

At what stage is health and safety construction info obtained?

A

Stage 3

28
Q

Define Stage 4

A

Technical Design

29
Q

At what stage is the building regs application submitted?

A

Stage 4

30
Q

what should be done with health and safety information at stage 4?

A

Include requirements in tender documents

31
Q

At what stage will you recieve tender returns?

A

Stage 4

32
Q

2 bullets

How may the project be presented at stage 4?

A
  • hand sketches
  • BIM model
33
Q

Who is the main team involved at stage 5?

A

construction team

34
Q

define stage 5

A

manufacturing and construction

35
Q

At what stage does the involvement of the client/design team depend on the procurement strategy and construction contract?

A

Stage 5

36
Q

At what stage do you recive pre-commencement planning conditions?

A

stage 4

37
Q

At what stage does the PD/PC comeplete the health and safety file?

A

Stage 5

38
Q

Where is the safety file included once it is completed?

A

In the building manual

39
Q

At what stage is the building completed?

A

Stage 6

40
Q

At which stage is information ‘handed over’ to the client and building users?

A

Stage 6

41
Q

define Stage 6

A

Handover

42
Q

When is the building manual handed over to users?

A

stage 6

43
Q

what is the architect’s role during stage 6?

A

to conduct a light-touch post-occupancy review

44
Q

what is a post-occupancy review?

A

A review of the building once it has been handed over to assess how it is immediately performing

45
Q

define stage 7

A

In-use

46
Q

At what point are the design and construction team no longer involved?

A

Stage 7