Revision Flashcards

1
Q

What is an SPI and what does it mean when it is < 1 or >1

A

SPI : Schedule Performance Index/indicator
SPI < 1 : The project is behind schedule
SPI > 1 The project is ahead of schedule

Schedule performance indicator = earned value / planned value
SPI = EV / PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Regulatory requirements are…

A

Non-negotiable

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Parts of “Bottom Up Estimating” budgeting and resources

A
  • Apply estimating techniques at the activity level
  • Add up the estimates for all detailed activities
  • Estimate all work at the detailed level
  • Break down the work
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Facts of a ‘Network Diagram’

A
  • Collection of any set of related tasks is a path.
  • One Start and One End
  • Each task can have more than one successor
  • All tasks have at least one successor and predecessor (EXCEPT BEGINNING AND END)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

A document called ____________ is created by decomposing the project scope into smaller, more manageable elements.

A

Work Breakdown Structure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Timothy is moving house and wants to keep his old house as a rental property. What format should he be operating?

A

Personal , i.e. no company format

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Steve and Sally are getting married and there is a national wedding consultant who specializes in Caribbean themed weddings. Sally gets in touch with her to ask about menu options. Which of the activity resource estimation tools and techniques is being used.

A

Expert judgment.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

As a PM you come up with three estimates (one where everything goes wrong, one where some things go wrong, and one where nothing goes wrong) for the cost of your project, and average them together to come up with a final number.

Which activity duration estimation tools and techniques is being used?

A

Three-point estimate.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

You are a PM who has done 4 projects that are very similar to the current one, and in all four of them it took exactly the same amount of time.

Which activity duration estimation tools and techniques is being used?

A

Analogous estimating.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

The activity duration estimation tools:

A
  • Expert judgment.
  • Parametric estimating.
  • Analogous estimating.
  • Parabolic incline returns.
  • Three-point estimate.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Once you have finished defining the Project what is the next task?

A

Project planning.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Is the following statement True or False?

“The majority of projects fail”

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Chris is teaching water sports and wants to take advantage of limited liability in the event of an unfortunate accident. What company format should he be operating?

A

Private Limited Company

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

On a network diagram, the critical path is

A

The path with the largest sum

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

You are buying vehicles for a company. A functional requirement maybe that the vehicle is capable of taking a load from a warehouse to a shop.

A

False

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

“The system should be available from 9 AM to 5 PM Monday to Friday” is an example of a non-functional requirement

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What type of requirement is the following?

A verification email is to be sent to user whenever he/she registers for the first time on some software system.

A

Functional.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Company Formats:

A
  • Limited Liability Partnership
  • Sole Trader
  • Public Limited Company
  • Private Limited Company
  • Personal , i.e. no company format
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Sanjep wants to set up an investment business. He wants to sell shares in his investment company, using the AIM stock exchange. > What format should he have for the company?

A

Public Limited Company

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

From your experience you know that a highway is €1 million per lane per km. How much for 10 km of two lane dual carriageway?

A

€40 million

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Jack and Jill are accountants wishing to combine resources and set up an accountancy firm. What format should they have for the company?

A

Limited Liability Partnership

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

David wants to set up a business with his friend Tommy with Split ownership, where they sell goods on Ebay. What format should he have for the company?

A

Personal

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

What does the acronym SWOT stand for?

A

Strength, Weakness, Opportunity, Threat.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

4 P’s of Marketing

A
  • Product
  • Price
  • Place
  • Promotion
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

What is the following is the best reflection of the state of a business at a specific moment in time?

A

Balance Sheet

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

The Balance Sheet equation states that:

A

Assets = Liabilities + Shareholders Equity.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

A company pays for stationary worth £500 using cash? How is this transaction entered onto the company balance sheet?

A

Decrease cash by £500 and decrease retained profits by £500.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

Tax Avoidance is:

A

Taking legal measures to reduce your tax bill.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

What is a companies Turnover?

A

Sum of all the money paid into the company.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

What is a companies profit?

A

Sum of turnover minus the cost of sales and admin. Can be positive or negative.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

What is Your USP?

A

‘unique selling point’ - The thing that sets your product / service apart from the competition.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

What is ‘Project Management’ ?

A

Project management is the application of knowledge, skills, tools, and techniques
applied to project activities in order to meet or exceed stakeholder needs and expectations from a project.
PMBOK definition

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

The triple constraint

A
  • Cost/Resource
  • Schedule/Time
  • Scope/Quality
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q

Scope Creep

A

Add Time: delay the project to give you more time to add the functionality ($)

Add Cost- recruit, hire or acquire more people to do the extra work ($)

Cut Quality- trade off some non-essential requirements for the new requirements ($)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q

Project Life-Cycle

A
  1. Project Initiation
  2. Project Planning
  3. Project Execution
  4. Project Closure
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
36
Q

SMART objectives:

A

Specific;
Measurable;
Acceptable;
Realistic;
Time based.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
37
Q

Project ‘Scope’

A
  • defining what the project will deliver
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
38
Q

What a project scope statement may contain

A
  • Product Scope
  • Project Scope
  • Deliverables
  • Product/Project Acceptance criteria
  • What is not part of the project
  • Constraints or Assumptions
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
39
Q

The five steps of articulation

A
  1. Ask customers to define their needs as clearly as possible
  2. Query all aspects of the need
  3. Research the need to ensure it is thoroughly understood
  4. Formulate the need as accurately as possible
  5. Ask customers to respond to the formulation of the need, and revise it accordingly.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
40
Q

Regulatory Requirements

A

Internal and external; usually non negotiable

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
41
Q

Business Requirements

A

needs of the sponsoring organization; always from a
management perspective

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
42
Q

User Requirements

A

What the users need to do with the system or product

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
43
Q

Functional and Non Functional Requirements

A

What the system needs to be able to do to satisfy the business and user needs in terms of function and functionality

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
44
Q

Technical Requirements

A

How the system needs to be designed and implemented to provide required functionality and fulfill required operational characteristics.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
45
Q

The purpose of a project plan:

A

Guides Project Execution
Documents project assumptions
Facilitates Communication
Provides baseline for measurement and control

46
Q

WBS (Work Breakdown Structure)

A

Provides a framework for organizing and managing the approved project scope

Helps ensure you have defined all the work that makes up the project

Provides a framework for planning and controlling costs and schedule information

47
Q

Expert Opinion :

A

Individual who has done it many times

Internal or External to the organization

Industry expert

Utilize for new technology or unfamiliar with the subject

48
Q

Published Estimating Data :

A

 Articles
 Books
 Journals
 periodicals

49
Q

Parametric Modeling

A
  • Characteristics of project allows use of a model
  • Use statistics, formulae, spreadsheets

Example- Highway is $1 million per
lane per mile. How much for 10 miles
of four lane highway?

50
Q

Critical Path

A
  • Provides a graphical view of the project
  • Predicts the time required to complete the project
  • Shows which activities are critical to maintaining the schedule and which are not.
  • Demonstrates the longest path of the project
  • Drives the project completion date
  • Any delay will cause the entire project to be delayed
51
Q

Contract Types: Y axis ($$) vs X axis (Effort)

A
  • Fixed Price (Profit m = negative, cost (revenue) m = 0)
  • Cost-Plus (Profit m = 0, cost (revenue) m = negative)
  • Time and materials (Profit m = positive, cost (revenue) m = more positive than profit m)
52
Q

What is Project Control?

A

The process whereby the project manager determines the degree to which the project plan is being met.

The focus is on:
– Schedule
– Budget
– Resource Allocation

53
Q

What does PV stand for?

A

Planned Value ( Total cost of work scheduled)

54
Q

PV =

A

Hourly rate * total hours planned

Planned value = sum:(planned costs x % planned)

55
Q

What does AC stand for?

A

Actual Costs (Earned value/Planned Value)
AC = EV/PV

56
Q

AC =

A

Hourly rate * total hours spent

Actual costs = sum:($ for all tasks)

57
Q

What does EV stand for?

A

Earned Value (Budgeted Cost of Work Performed, BCWP)

Total cost of the work completed as of the reporting date

58
Q

EV =

A

Baseline cost * % work actually completed

AC/EAC = % work actually completed

Earned value = sum: (Actual costs x % completed)

59
Q

What does EAC stand for?

A

EAC - Estimated At Completion = estimated cost of the project at the end of the project

60
Q

What does SV stand for?

A

Scheduled variance

61
Q

SV =

A

SV = EV - PV

Schedule variance = earned value – planned value

If SV is negative then the project is behind schedule
If SV is positive then the project is ahead of schedule

62
Q

CV and CPI

A

These are measures of how close the work is to being accomplished on budget (CV) and the efficiency of utilization of resources (CPI)

Cost variance = earned value – actual cost

CV = EV – AC

If CV is negative then the project is over budget
If CV is positive then the project is under budget

Cost performance indicator = earned value / actual cost

CPI = EV / AC

If CPI is > 1 then the project is efficient in utilizing resources
If CV is < 1 then the project is inefficient in utilizing resources

63
Q

What does SPIN stand for?

A

Situation

Problem

Implication

Need Payoff

64
Q

The value chain (full life-cycle of a product)

A

Raw material
Extraction
Manufacture
Consumer
Recycle

65
Q

What is Porter Market Forces?

A

A method for analyzing the competitive environment

66
Q

‘First Movers’ Advantages + Disadvantages

A

Advantages:
Brand recognition
Switching Costs
Economies of Scale

Disadvantages:
Cheaper to copy
Learning from mistakes
Established markets

67
Q

Up selling

A

Increases sale value - increase profit margin

68
Q

down selling

A

Increases markets and access to buyers

69
Q

Cross selling

A

Increases markets and sales value

70
Q

What is a patent?

A

An exclusive right granted to preclude others from using an invention

71
Q

The different structures

A
  • Functional Structure
  • Divisional Structure
  • Flatarchy
  • Matrix Structure
72
Q

Functional Structure

A

-A bureaucratic structure
-Defined by skills/tasks
-Creates Teams to tackle different business aspects
-Each team has a manager

73
Q

Functional Structure Advantages + Disadvantages

A

Advantages -
Simple
Creates simply effective Teams and Teamwork

Disadvantages
Creates Silos
Communication and Competition

74
Q

Divisional Structure

A

-Normally associated with Very large, Multi national companies
-Each Division works separately on its goal
-Maybe a division geographically
-Can also be across the Value Chain

75
Q

Flatarchy

A

Developed from the flat type of organisational structure
-Defined by no (if possible) levels of management
-Used by smaller organisations (but not exclusively)
-maybe one manager reporting to executive levels

76
Q

Divisional Structures Advantages + Disadvantages

A

Advantages
-Concentration of efforts
-Centralised leadership

Disadvantages
-Communication
-Conflicting interests
-Complication (tax)

77
Q

Flatarchy Advantages + Disadvantages

A

Advantages
-Morale
-Lean/Agile
-Cost efficient

Disadvantages
-conflict
-lack of clarity
-Complexity

78
Q

Matrix Structure

A
  • Employees split into teams
  • Each team answers to two or more managers / leaders
79
Q

Matrix Structure Advantages + Disadvantages

A

Advantages
-Creates communication
-Flexible / rewarding workplace environment

Disadvantage
-Confusion
-Conflict
-Cost
-Efficiency

80
Q

Incorporartion versus unincorporation

A

“Incorporation is the process by which a new or existing business registers as a limited
company’’

81
Q

Sole Trader

A

Sole proprietor (ownership and responsibility)
Not a separate legal Entity
Full liability
Responsible for all your tax affairs (self assessment)

82
Q

Sole Trader Advantages + Disadvantages

A

Advantages
-Full ownership
-Flexible
-Limited regulation
-Simple

Disadvantages
-Full liability
-Difficult to raise investment
-Profits subject to income tax
-Workload

83
Q

Partnership

A

Two or more people
Share Liability / Profits / Control
Can be formal / informal
Responsible for tax affairs (self assessment)
Not a separate legal entity

84
Q

Partnership Advantages + Disadvantages

A

Advantages
- Share liability
-Greater funding options
-Flexible
-Limited regulation
-Simple

Disadvantages
- Share ownership
- Responsible for others decisions
- Difficult to raise investment
- Profits subject to income tax
- Workload

85
Q

Limited Partnership

A

NOT a Limited Liability Partnership
General and limited partners
Limited Partners have liability limited to the investment
-
Must register with Companies House

86
Q

Limited Company

A

Companies are ‘incorporated’ and a separate legal entity
Must register at companies house with
- a memorandum
- Articles of Association

Limited by shares (Most common members own shares)

Limited by Guarantee (members guarantee to pay a set amount if company goes into liquidation)

Must register with HMRC and pay cooperation tax
- companies liable must make annual tax returns

87
Q

Memorandum

A

Cannot be amended

Record that initial members wish to form a company

A legal document signed by all initial shareholders
(guarantors)

88
Q

Articles of Association

A

Contract between the company and its members
A set of legally binding rules for the company

  • Framework for:
    Decisions
    Ownership
    Control
89
Q

Public limited company (plc)

A
  • Must have at least two directors and a qualified secretary
  • IPO Initial Public offering
  • Must have issued shares to a minimum of £50,000
  • can become listed by floating on a recognised stock
    market
90
Q

Limited Company Advantages + Disadvantages

A

Advantages
- Limited Liability
- Can generate investment more easily
- Tax advantages
- Owner retains significant control

Disadvantages
- Complicated
- Accounting responsibilities
- Relatively inflexible

91
Q

PLC advantages and disadvantages

A

Advantages
- Limited Liability
- Can generate investment easily
- Shared risk

Disadvantages
- Complicated
- Accounting responsibilities
- Relatively inflexible
- Much more regulated
- Vulnerable to takeovers

92
Q

Limited liability partnership

A

Basics,
- a ‘body corporate’ and a separate legal entity
- Limited liability
- Share of profit set by members agreement
- Must register at companies house

93
Q

Limited liability partnership Advantages + disadvantages

A

Advantages
- Limited Liability
- Increased internal flexibility
- Tax advantages

Disadvantages
- Complicated set up
- Must publish Annual reports
- Partner Disagreements

94
Q

What is a trust

A

Trusts are unincorporated and have no legal identity
- A legal device to hold assets (on behalf of a person of or organization)
- Run by a group of trustees (legal responsibility)

95
Q

VAT

A

A general tax added to most products and services
Must register if turnover is over £85,000 in one tax year
The VAT you pay is the balance between the VAT you have
paid and the VAT you have charged

96
Q

Community Interest Company

A

Must submit a community interest statement
-
Must have an Asset lock limited transfer of assets
-
Are subject to cap on dividends and interest paid

97
Q

Dividends

A

The Shareholders share of the profits
Determined by the companies board of directors
Often paid quarterly.
A dividend yield is the dividend per share divided by the share price

98
Q

Insolvency

A

When an entity can’t pay its obligations when they are due.
Eventually can lead to bankruptcy

99
Q

Bankruptcy

A

Is a Legal status and or process

A process where entities that cannot repay debts seek protection from its creditors.

A declaration of insolvency and initiated by the courts

100
Q

Cash flow diagram

A

A-B Investment
B-C The heavy Investment
“start up”
C-D The cash flow turns
D-E Profit is made
E+ As time continues profits
tend to reduce as sales
decrease and costs rise

101
Q

Rate of return =

A

= (cumulative net cash flow (f to c) / project life (g) * investment (c) ) * 100

102
Q

NPV in year n=

A

cash flow in year n / (1+r)^n

103
Q

r =

A

discount rate (%)/ 100

104
Q

Total NPV =

A

sum: cash flow in year n/(1+r)^n

t = lifetime of project

105
Q

Working Capital

A

The money needed to run the company day to day
Represents operating liquidity

106
Q

Seed funding

A

Very Early Investment
Huge Risk
Exchanged cash for start
up capital for equity

107
Q

ROI

A

The return (profit) gathered from the initial investment.
Generally given as a percentage.
Generally total profit divided by the initial investment.
(but can be given for a specific period)

108
Q

ROR

A

Percentage return in the value of an investment over a time period

109
Q

NPV

A

The current value of the future monies (profits) given a specific discount rate

110
Q

IRR

A

the rate of growth that an investment is expected to generate