Equations and Formulas Flashcards

1
Q

SPI =

A

EV / PV

SPI > 1 then project is ahead of schedule

SPI < 1 then project is behind schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Company Profit =

A

Sum of turnover - cost of sales and admin

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Company turnover =

A

sum of all money paid into the company

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

PV =

A

Total budget * Planned % complete

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

AC =

A

EV / PV

Hourly rate * Total hours spent

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

SV =

A

EV - PV

If SV is negative then project is behind schedule

If SV is positive then project is ahead of schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

CV =

A

EV - AC

If CV is negative then project is over budget

If CV is positive then project is under budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

CPI =

A

EV / AC

If CPI > 1 then project is efficient in utilizing resources

If CPI < 1 then project is not efficient in utilizing resources

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

ROR =

A

( (cumulative net cash flow) / (Project life * Investment) ) * 100

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

NPV (year n) =

A

(Cash flow year n) / (1 + r )^n

r = discount rate % / 100

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Total NPV =

A

sum: (NPV (year n))

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Assets =

A

Liabilities + Shareholders equity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

EV =

A

Sum : (AC * % completed)

AC/EAC = % work actually completed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly