Equations and Formulas Flashcards
SPI =
EV / PV
SPI > 1 then project is ahead of schedule
SPI < 1 then project is behind schedule
Company Profit =
Sum of turnover - cost of sales and admin
Company turnover =
sum of all money paid into the company
PV =
Total budget * Planned % complete
AC =
EV / PV
Hourly rate * Total hours spent
SV =
EV - PV
If SV is negative then project is behind schedule
If SV is positive then project is ahead of schedule
CV =
EV - AC
If CV is negative then project is over budget
If CV is positive then project is under budget
CPI =
EV / AC
If CPI > 1 then project is efficient in utilizing resources
If CPI < 1 then project is not efficient in utilizing resources
ROR =
( (cumulative net cash flow) / (Project life * Investment) ) * 100
NPV (year n) =
(Cash flow year n) / (1 + r )^n
r = discount rate % / 100
Total NPV =
sum: (NPV (year n))
Assets =
Liabilities + Shareholders equity
EV =
Sum : (AC * % completed)
AC/EAC = % work actually completed