Responsibility Flashcards

Who is Responsible for what

1
Q

Overall responsibility for complying with API 510 (4.1)

A

Owner / User

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

During repairs and alterations who is responsible for Quality Control (4.3)

A

Repair Organization

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Assure owner that inspection, NDE, repairs, and pressure testing activities meet code (4.4)

A

Inspector

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Evaluate and accept NDE results (4.4)

A

Inspector

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Develop the inspection plan for vessels and pressure relief devices. (5.1.2.1)

A

Inspector or Engineer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Designate potential damage mechanisms and where they may occur (5.1.2.1)

A

Corrosion Specialist

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Chooses to conduct RBI assessment (5.2.1)

A

Owner / User

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Review prior vessel history prior to inspections (5.3.5)

A

Inspector

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Familiar with conditions, causes, and characteristics of potential damage mechanisms (5.4.2)

A

Inspector

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Perform Internal Inspection (5.5.2.1)

A

Inspector

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Determine whether it’s necessary to remove deposits or lining (5.5.2.3)

A

Inspector and Corrosion Specialist

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Perform On-Stream Inspection (5.5.3.1)

A

Inspector or Examiner

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Approve On-Stream inspection work performed by Examiners (5.5.3.1)

A

Inspector

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Perform External Inspection (5.5.4.1.1)

A

Inspector or Qualified Others

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Take thickness measurements (5.5.5.1)

A

Inspector or Examiner

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Review thickness data to look for anomalies and if short-term corrosion rate changes significantly (5.5.5.3)

A

Inspector and Corrosion Specialist

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Assure those taking thickness measurements are trained and qualified (5.5.5.4)

A

Owner / User

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Determine locations of CML’s for vessels with localized corrosion (5.6.3.1)

A

Corrosion Specialist

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Involve if the # of CML’s will be significantly reduced or eliminated (5.6.3.2)

A

Corrosion Specialist

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Define the type of damage, the NDE technique, and extent of examination (5.7.1.1)

A

Inspector and Engineer or Corrosion Specialist

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Perform UT flaw detection for finding linear flaws (5.7.1.3)

A

Industry-Qualified UT Angle Beam Examiners

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

After a repair a pressure test shall be applied if _______ believes that one is necessary and specifies it in the repair plan (5.8.2.1)

A

Inspector

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Review use of a component pressure test in lieu of complete vessel hydro (5.8.2.2)

A

Engineer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

Determine the test pressure for non-code related pressure tests (5.8.3.2)

A

Owner / User

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

Hydro static pressure test of 300 series stainless steel, verify water quality and the vessel is drained and dried (5.8.5.2)

A

Inspector

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

Approved substituting NDE for a pressure test (5.8.8.1)

A

Inspector and Engineer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

Verify new materials are consistent with those specified (5.9.1)

A

Inspector

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

When verifying new materials, determine the sampling percentage (5.9.1)

A

Inspector or Owner / User

29
Q

PMI new materials during repairs and alterations (5.9.1)

A

Inspector or Examiner

30
Q

If incorrect material found in existing vessel, determine amount of verification (5.9.2)

A

Inspector

31
Q

Asses crack-like flaws attributed to environmental cracking (5.10.3)

A

Engineer or Corrosion Specialist

32
Q

Assess preferential corrosion in welds (5.10.3)

A

Inspector

33
Q

Inspect new vessels at time of installation (6.2.1.1)

A

Inspector

34
Q

Review and approve RBI assessments that extend intervals beyond 10 years (6.3.2)

A

Inspector and Engineer

35
Q

Determine the External and Internal inspection interval (6.4.1 & 6.5.1.1)

A

Inspector or Engineer

36
Q

Approve the use of On-Stream inspection in lieu of Internal (6.5.2.1)

A

Inspector

37
Q

Determine the pressure relief device interval (6.6.3.1)

A

Inspector or Engineer or Qualified Others (PTV-Tech)

38
Q

Inspector recommendations can be changed or deleted after review (6.9)

A

Engineer or Inspection Supervision

39
Q

Select which corrosion rate (Short v.s Long) reflects the current condition (7.1.1.2)

A

Inspector and Corrosion Specialist

40
Q

Maintain vessel and relief device records (7.8.1)

A

Owner / User

41
Q

Authorize all vessel repairs (8.1.2)

A

Inspector

42
Q

Authorize all repairs to Div. 1 & 2 (8.1.2)

A

Inspector and Engineer

43
Q

Authorize all alterations (8.1.2)

A

Inspector and Engineer

44
Q

Designate hold point [Fabrication Approvals] (8.1.2)

A

Inspector

45
Q

Repairs - Approve all methods of design, materials, WPS’s, NDE, and testing (8.1.3.1)

A

Inspector or Engineer

46
Q

Alterations - Approve all methods of design, materials, WPS’s, NDE, and testing (8.1.3.1)

A

Inspector and Engineer

47
Q

Approve all repair and alteration work at hold points (8.1.3.2)

A

Inspector

48
Q

Approve all repair and alteration work at completion of work (8.1.3.2)

A

Inspector

49
Q

Approve all nozzle instillations (8.1.4)

A

Engineer

50
Q

Allow temporary weld repairs to remain in place past ‘‘Next Opportunity’’ (8.1.6.1.1)

A

Inspector and Engineer

51
Q

Determine that a crack will not propagate from under a fillet weld patch (8.1.6.1.2.1)

A

Engineer

52
Q

Approve the use of fillet-welded patch repairs (8.1.6.1.2.1)

A

Inspector and Engineer

53
Q

Approve use of lap band repair (8.1.6.1.3.a)

A

Inspector and Engineer

54
Q

Authorize the repair welding of cracks at stress concentrations (8.1.6.2.1)

A

Engineer

55
Q

Review the repair procedures for stainless steel cladding (8.1.6.4.1)

A

Inspector and Engineer

56
Q

Monitor the repairs made to stainless steel cladding (8.1.6.4.3)

A

Inspector

57
Q

Allow exceptions to preheat temperatures (8.1.7.3)

A

Engineer

58
Q

Maintain record of qualified WPS’s and WPQ’s (8.1.7.2.2)

A

Repair Organization

59
Q

Monitor preheat temperatures (8.1.7.3)

A

Inspector

60
Q

Review the use of a local PWHT in lieu of a full encirclement PWHT (8.1.7.4.2.a)

A

Engineer

61
Q

Review the use of preheat in lieu of PWHT (8.1.7.4.3.1.2)

A

Engineer

62
Q

Review the use of controlled deposit welding in lieu of PWHT (8.7.1.4.3.1.2)

A

Engineer

63
Q

Approve use of alternate NDE methods after repairs and alterations (8.1.8.3)

A

Inspector and Engineer

64
Q

Perform calculations for rerate (8.2.1.a)

A

Engineer or Manufacture

65
Q

Oversee the attachment of a name plate after rerating was performed (8.2.2)

A

Inspector

66
Q

An On-Stream inspection may be substituted for the internal inspection provided this substitution is approved by _________?

A

Inspector Only!

67
Q

Companies that use API 510 must?

A

Either employ or have access to an authorized inspection agency

68
Q

During vessel repairs or alterations, who is required to maintain welding records?

A

Repair Organization

69
Q
A vessel service has changed. Inspector must obtain probable corrosion rate for new operation. Which of the following is preferred way to establish the corrosion rate for the new service?
A - Similar Service
B - Owner Experience
C - published data
D - inspect after 1000 hours
A

A - Similar service