Q

Why is the RC purview so broad? (2)

A
  1. Reliability of the wide-area takes precedence over a single local area.
  2. It must be able to calculate Interconnection Reliability Limits that involves system and facility operating parameters beyond its own area and within its area.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

In what way is the Transmission Operator differ with RC with respect to operating areas?

A

The TO is only concern with its operating area.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How and when can the RC assist the TO? (2)

A
  1. The RC can relieve operating equipment or facility overloads through transmission relief measures IF
  2. Market based dispatch procedures were not adequate.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Can the RC approve or deny tags?

Can the RC receive tags?

A
  1. No and No.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Can RC curtail tags?

A

Yes. 2. RC may curtail Interchange transactions until they are arranged and ready for implementation as Interchange Schedules.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What does the RC’s Transmission loading relief requests be used to accomplished?

A

Transmission loading requests can reduce, remove, or halt flows or impending interchange transactions.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

The RC receives what from the BAs?

A

Dispatch plans

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What does the RC receive from Generators Operators and transmission operators?

A

Generation and Transmission maintenance schedules.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

The RC can deny what?

A

Outage requests.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Who is usually responsible for reliability of local transmission systems? (2)

A

The Transmission Operator. However, the RC may issue a dispatch adjustment if aware of a potential SOL violation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

The RC can do what during Real Time system reliability emergencies: (4)

A
  1. Curtail Interchange Schedules.
    2) Direct redispatch to alleviate congestion.
    3) Ensure energy balance and Interconnection frequency.
    4) Directing load shedding.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

If the BA cannot achieve resource demand balance, the RC may: (4)

A
  1. Invoke public appeals.
  2. Demand-side management
  3. Direct Load Shedding.
  4. Voltage reduction
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Who is responsible for reliability of local transmission system in accordance with SOLs?

A

Transmission Operator.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is SOL?

A

System Operating Limits

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What can the Reliability Coordinator do if becomes aware of a potential SOL violation?

A

Issue a dispatch adjustment.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Who is responsible for real-time system reliability?

A

The RC.

17
Q

What can the RC do to maintain real-time system reliability? (5)

A
  1. Curtail Interchange Schedules.
  2. Direct redispatch to alleviate congestion.
  3. Mitigate energy and transmission emergencies.
  4. Ensure energy balance and Interconnection frequency.
  5. Direct Load Shedding.
18
Q

In emergencies and in collaboration with the BAs and TO, the RC can: (4)

A
  1. Invoke public appeals
  2. Voltage reductions.
  3. demand-side management
  4. load shedding if BA cannot achieve resource-demand balance.
19
Q

RC can direct and coordinate system restoration with who?

A

TO and BAs.