Balancing Authority Flashcards
The BA operates within _________?
the metered boundaries that establish the BA Area.
What is included within the BA area?
Every generator, transmission facility, and End-use Customer.
Purpose of the BA?
- Maintain balance between load and resources in real time.
How does BA keep balance between load and resources in real time?
- Keeps actual interchange = to scheduled interchange.
2. Meeting frequency bias obligation
Load-Resource balance is measured by:
BA’s Area Control Error (ACE).
What organization requires the BA to maintain its ACE within acceptable limits?
NERC
BA’s authority for what 4 types of resource management? (4)
- Frequency control through tie-line bias.
- Regulation service deployment.
- Load-following through economic dispatch
- Interchange Implementation
The BA controls ,____________ within its area to meet its frequency bias obligation?
Resources
To maintain its ACE within acceptable limits, the BA controls a set of generators within its BA area that are capable of providing_______________?
Regulation Service.
BA performs ____________ and ____________. Besides the BA, ___________ may also perform the same functions.
unit commitment, economic dispatch,
Generator operators.
The BAs receive _________ __________ from one or more Interchange Authority (ies).
Confirmed Interchange
The BAs receive _______ _________ ______ from Market Operator and /or unit commitment and dispatch from _________ that has bilateral arrrangements for generation within the market or the BA area. The BA provides this commitment and dispatch schedules to the _________.
Resource Dispatch Plans
LSE
RC
The BA approves as Arranged Interchange with respects to its ________ ________. The BA provides its approval or denial to the _________ ______ _________.
ramping requirements of the generation
Interchange Authorities.
In event of energy emergencies, the BA can do what and with in accordance with who? (4)
- Public appeals
- demand-side management programs
- Load Shedding
- the RC
IF BA cannot comply with NERC’s Reliability Standards regarding __________ ________ and ______, it must take action under its own initiative or direction by the RC.
frequency control
ACE