Quantification and Costing of Construction Works Flashcards

1
Q

What does NRM stand for?

A

New Rules of Measurement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is NRM

A

Published by RICS
Comprises of 3 volumes
Provides a consistent basis for the production of order of cost estimates and cost plans
Provides added confidence and accuracy to employers
In the event that a firm is persuade for negligence, the use of NRM would provide a means of defence as it represents best practice

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is NRM1

A

Order of cost estimating and cost planning for capital building works

Enabling more effective and accurate cost advice to be given to clients, as well as facilitating better cost control

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is NRM2

A

Detailed measurement for building work

Allowing surveyors to prepare bills of quantites

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is NRM3

A

Order of cost estimating and cost planning for building maintenance works

Gives guidance on the quantification and description of maintenance works for the purpose of preparing initial order of costs estimates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

According to NRM1, the term risk allowance refers to:

A

the amount added to the base cost estimate for item that cannot be precisely predicted to arrive at the cost limit

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

GIA

A

Gross Internal Area
Internal face of the perimeter wall at each floor area
Excludes; balconies, canopies, external walls

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

NIA

A

Net Internal Area
Useable space / rentable space

Excludes; structural walls, columns, lift lobbies, toilets, plant area

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

GEA

A

Gross External Area
Area of building measured externally at each floor area

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is a provisional sum

A

Money included in the contract for work that cannot be fully defined at the time of tender

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is a defined provisional sum

A

A provisional sum that are sufficiently well defined. Allowing contractor to make allowances for them

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is a undefined provisional sum

A

No allowance for programme or prelims is allowed for within the contract sum

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

How are provisional sums expended

A
  • The CA should issue an instruction for its expenditure
  • The final account payable will be adjusted (the PS is omitted and replaced with actual costs
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is cut and fill excavation

A

Process of excavation whereby the material that is cut / stripped is re-used elsewhere on the site

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What would you expect the % of NIA to GIA to be

A

Office building : 70-85%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is the Bill of Quantities

A

document that provides a project specific measured quantities of items identified in drawings and specifications

16
Q

What is the purpose of a BofQ

A

Purpose of the BofQ is to provide the estimator with an accurate picture of the scope of works

17
Q

Why would you use BofQ instead of schedule of work?

A

BofQ breaks the works section down into more detail
Simplifies the tender process, contractors will be pricing the same quantities, simplifying the tender analysis

18
Q

Advantages of using BofQ

A
  • Simplified tender analysis
  • Detailed
  • Effective document for interim payments and preparing the final account
19
Q

Disadvantages of BofQ

A
  • Time consuming to produce
  • Potential for errors when measuring the project
20
Q

How would you structure a BofQ

A

In accordance with NRM2
- Prelims
- Facilitating works
- Substructure
- Superstructure
- Internal Finishes
- Fittings, Furnishings and Equipment
- Services
- External Works
- Provisional Sums
- Dayworks