Quantification and Costing of Construction Works Flashcards
What does NRM stand for?
New Rules of Measurement
What is NRM
Published by RICS
Comprises of 3 volumes
Provides a consistent basis for the production of order of cost estimates and cost plans
Provides added confidence and accuracy to employers
In the event that a firm is persuade for negligence, the use of NRM would provide a means of defence as it represents best practice
What is NRM1
Order of cost estimating and cost planning for capital building works
Enabling more effective and accurate cost advice to be given to clients, as well as facilitating better cost control
What is NRM2
Detailed measurement for building work
Allowing surveyors to prepare bills of quantites
What is NRM3
Order of cost estimating and cost planning for building maintenance works
Gives guidance on the quantification and description of maintenance works for the purpose of preparing initial order of costs estimates
According to NRM1, the term risk allowance refers to:
the amount added to the base cost estimate for item that cannot be precisely predicted to arrive at the cost limit
GIA
Gross Internal Area
Internal face of the perimeter wall at each floor area
Excludes; balconies, canopies, external walls
NIA
Net Internal Area
Useable space / rentable space
Excludes; structural walls, columns, lift lobbies, toilets, plant area
GEA
Gross External Area
Area of building measured externally at each floor area
What is a provisional sum
Money included in the contract for work that cannot be fully defined at the time of tender
What is a defined provisional sum
A provisional sum that are sufficiently well defined. Allowing contractor to make allowances for them
What is a undefined provisional sum
No allowance for programme or prelims is allowed for within the contract sum
How are provisional sums expended
- The CA should issue an instruction for its expenditure
- The final account payable will be adjusted (the PS is omitted and replaced with actual costs
What is cut and fill excavation
Process of excavation whereby the material that is cut / stripped is re-used elsewhere on the site
What would you expect the % of NIA to GIA to be
Office building : 70-85%