Project Finance Control and Reporting Flashcards

1
Q

What is a cost report?

A

Used to monitor and manage cost throughout the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is included in a cost report?

A

Contract sum total
Value of instructed and potential variations
Ongoing claims
Provisional sum adjustments
Anticipated final account total
Total of certified payments

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is a cashflow used for?

A

Planning tool that shows the predicted flow of cash in and out of a project
Shows if a project is running ahead / behind programme
Once construction is underway the cashflow projection will typically form an S Curve

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Contractor cashflow

A

Will typically show construction costs (material, labour and plant)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Employers cashflow

A

Will consider most elements of a project including, legal fees, statutory fees

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Benefits of an accurate cash flow projection

A

Provides an early indication of financial difficulties if actual expenditure is lagging behind forecast
Ensures appropriate level of funding is in place for future payments

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

If payment to the contractor are behind the projection, what might this indicate

A

Indication that construction works is behind the programme (delays)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

If the contractor’s monthly valuation is ahead of the cash flow projection, what might this indicate

A

Project is ahead of programme or contractor is overclaiming

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Life Cycle Costing (LCC)

A

A method for measuring and managing the lifetime costs of a project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Key advantages of LCC

A

Long term value - ensures the project has the highest possible value

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is a variation?

A

Alteration or modification to the design, quality or quantity of the contract works

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Why does a variation arise?

A
  • Change in spec
  • Discrepancies between contract docs or statutory requirements
  • Errors or omissions
  • Deficiencies in employers requirements
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is Dayworks?

A

Method valuing construction work according to the time spent carrying out work, together with the value of the plant and materials resources used

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What information is needed to be able to assess dayworks?

A
  • Timesheets
  • Plant and material used
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is Loss and Expense

A

L&E reimburses the contractor for direct loss and/or expense as a result of the progress of the works being materially affected by relevant matters for which the client is responsible

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Example of loss and expense

A
  • Failure to give the contractor possession / access of the site
  • Delays in receiving instruction
  • Disruptions causes by works being carried out by the client